MDOT letting · Emergency

March 26, 2020 MDOT letting: 2 contracts, $1.7M

MDOT let 2 contracts worth $1.7M at the low bid, with 3.50 bidders per contract (the 12-month average is 3.70). Cook & Son, LLC won the most, $1.2M; 2 firms won at least one contract. The closest finish: Construction project, Webster County, decided by 8.9% ($105K).

Awarded at low bid
$1.7M
2 contracts
Bidders per contract
3.50
single-bid 50%
Low bid vs. estimate
−2.6%
median
Low-to-second gap
$105K
median 8.9%
CallContractLow bidderLow bidSecondGapBiddersvs. estimate
2Construction project, Webster CountyWebster · Construction & widening · 108457301Cook & Son, LLC2nd: Phillips Contracting Co., Inc.$1.2M$1.3M8.9%6−6.2%
1Placing Temporary Traffic Crossover on US 49 4.8 miles South of SRYazoo · Construction & widening · 108454301APAC - Mississippi, Inc.$532K––1+0.9%

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew.

Bid the next letting with this data

BidCrew tracks every DOT letting: line-item prices, competitor history, and a predicted low bid before you submit.