162 lettings, 1,008 contracts, $6.10B at the low bid. Open any letting for each contract's low and second bidder, margin and comparison with MDOT's estimate.
| Letting | Type | Contracts | Rejected | Awarded | Bidders / contract | Single-bid | Low vs. estimate | Low-to-second gap | Largest contract |
|---|---|---|---|---|---|---|---|---|---|
| Oct 27, 2026 | Regular | 15 | – | $347M | 2.20 | 40% | +4.8% | $7.9M | Construction project, Madison County$188M · T. L. Wallace Construction, Inc. |
| Sep 29, 2026 | Special | 1 | – | $57.2M | 6.00 | 0% | −0.4% | $4.5M | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Impro$57.2M · Hemphill Construction Company, Inc. |
| Sep 22, 2026 | Regular | 11 | – | $28.5M | 4.09 | 9% | −9.1% | $2.9M | Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben $11.5M · Cook & Son, LLC |
| Sep 1, 2026 | Special | 2 | – | $54.0M | 4.50 | 0% | −4.6% | $4.0M | Bridge Replacements on SR 32 between Webb & Charleston (Brid$47.2M · Talbot Brothers Contracting Co., Inc. |
| Aug 25, 2026 | Regular | 8 | 2 | $23.3M | 4.00 | 13% | +5.2% | $2.3M | Mill & Overlay approximately 11 miles of US 61 from 0.5 mile$12.2M · APAC - Mississippi, Inc. |
| Aug 21, 2026 | Emergency | 2 | – | $1.9M | 4.00 | 0% | −17.9% | $267K | Emergency Slope Repair & Pipe Cleanout on SR 26$1.5M · Dunn Roadbuilders, LLC |
| Jul 28, 2026 | Regular | 11 | 1 | $56.9M | 4.64 | 0% | −1.7% | $7.3M | Bridge Replacement on SR 28 between Copiah County Line & Pin$25.1M · Chris Albritton Construction Company, Inc. |
| Jun 30, 2026 | Special | 2 | – | $5.2M | 4.00 | 0% | −10.2% | $398K | Thin Lift Overlay approximately 10.1 miles of MS 35 from 4 F$2.7M · APAC - Mississippi, Inc. |
| Jun 23, 2026 | Regular | 8 | – | $33.4M | 3.50 | 13% | −4.5% | $1.3M | Overlay and OGFC Lift from east of the Shorecrest Road Overp$9.9M · Warren Paving, Inc. |
| Jun 12, 2026 | Emergency | 1 | – | $1.8M | 4.00 | 0% | +6.9% | $228K | Emergency Slide Repair on SR 178 approximately 0.66 miles so$1.8M · GeoStabilization International, LLC |
| Jun 5, 2026 | Special + emergency | 9 | 1 | $29.5M | 2.78 | 33% | +7.4% | $1.0M | Overlay approximately 14.3 miles of MS Highway 7 beginning a$7.0M · Lehman-Roberts Company |
| May 27, 2026 | Regular | 17 | 2 | $87.4M | 3.29 | 18% | −1.7% | $2.3M | Intersection Improvements on US 45 from Misso Road to Magnol$20.6M · APAC - Mississippi, Inc. |
| May 8, 2026 | Special | 3 | – | $15.5M | 3.00 | 0% | −16.7% | $1.5M | Seal & Overlay approximately 16 miles of MS 501 from SR 18 t$7.2M · Southern Paving, LLC |
| Apr 28, 2026 | Regular | 9 | 1 | $80.6M | 3.33 | 0% | −9.2% | $3.4M | I-10 Jackson County Welcome Center$35.2M · T. L. Wallace Construction, Inc. |
| Apr 17, 2026 | Special | 3 | – | $10.9M | 8.00 | 0% | −24.7% | $394K | Construction project, Attala County$6.6M · CTC Disaster Response, Inc. |
| Apr 10, 2026 | Special | 3 | – | $24.9M | 3.67 | 0% | −10.3% | $1.8M | Pavement Restoration on US 49 from Madison County Line to 0.$12.0M · APAC - Mississippi, Inc. |
| Mar 24, 2026 | Regular | 6 | – | $25.1M | 2.67 | 0% | −11.9% | $3.0M | Seal & Overlay approximately 12.1 miles of US 61 from the Tu$11.5M · Lehman-Roberts Company |
| Feb 24, 2026 | Regular | 11 | – | $38.9M | 3.64 | 18% | −8.6% | $2.4M | Mill & Overlay approximately 9.8 miles of SR 25 from Renfroe$10.4M · Superior Asphalt, Inc. |
| Feb 3, 2026 | Special | 16 | 2 | $60.2M | 4.00 | 13% | −3.2% | $3.1M | Bridge Replacement on SR 178 (Bridge Nos. 33.6, 34.1, 35.2, $15.0M · Ste-Bil Grading Inc. |
| Nov 25, 2025 | Regular | 9 | – | $31.3M | 5.56 | 0% | −20.5% | $1.1M | Mill & Overlay approximately 10 miles on US 45A from the Chi$14.6M · Cook & Son, LLC |
| Nov 20, 2025 | Regular | 1 | – | $673K | 5.00 | 0% | −14.9% | $8K | Emergency Slide Repair on MS 478 approximately 0.90 miles SE$673K · Key, LLC |
| Oct 29, 2025 | Regular | 1 | – | $2.5M | 3.00 | 0% | −30.1% | $1.2M | Bridge Repair on I-220 over Lynch Street (Bridge Nos. 0.5A &$2.5M · Gibson & Associates, Inc. |
| Oct 28, 2025 | Regular | 11 | 3 | $31.9M | 3.18 | 18% | −5.5% | $3.1M | Mill & Overlay approximately 6 miles on I-20 from Clinton to$8.6M · APAC - Mississippi, Inc. |
| Sep 24, 2025 | Regular | 1 | – | $207K | 1.00 | 100% | −32.1% | $0 | Bridge Repair on SR 22 (Bridge No. 0.1) over I-20$207K · Gibson & Associates, Inc. |
| Sep 23, 2025 | Regular | 9 | 1 | $147M | 3.44 | 0% | −2.4% | $16.4M | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0$139M · Talbot Brothers Contracting Co., Inc. |
| Sep 16, 2025 | Regular | 2 | – | $9.1M | 3.00 | 0% | −2.8% | $962K | Mill & Overlay approximately 7 miles on I-55 from Byram to M$8.7M · Dickerson & Bowen, Inc. |
| Sep 4, 2025 | Regular | 2 | – | $7.2M | 4.00 | 0% | +4.7% | $92K | Roundabout on I-55 at the Brookway Boulevard Interchange$5.5M · T. L. Wallace Construction, Inc. |
| Aug 26, 2025 | Regular | 14 | 1 | $58.1M | 3.29 | 7% | −15.2% | $2.6M | Mill & Overlay approximately 4.3 miles of I-55 Carroll Co fr$13.8M · Lehman-Roberts Company |
| Aug 22, 2025 | Regular | 1 | – | $248K | 4.00 | 0% | −49.3% | $121K | Removal and Disposal of Debris on various routes throughout $248K · Cleer Creek Construction LLC |
| Jul 31, 2025 | Regular | 3 | – | $96.2M | 2.00 | 33% | −22.5% | $15.6M | Safety Improvements on MS 67 from US 49 to the I-10 "Superst$68.7M · Huey P Stockstill, LLC |
| Jul 22, 2025 | Regular | 15 | 1 | $35.8M | 2.67 | 7% | −4.1% | $4.0M | Mill & Overlay approximately 10 miles of SR 389 from US 82 t$6.6M · Falcon Contracting Company, Inc. |
| Jun 26, 2025 | Regular | 4 | – | $95.9M | 3.75 | 0% | −24.2% | $25.7M | Bridge Replacements on US 80 between Chunky & Meehan (Bridge$87.9M · Cotton Creek Transport, Inc. |
| Jun 25, 2025 | Regular | 2 | – | $2.2M | 3.00 | 0% | +4.0% | $236K | Bridge Repair on SR 43 over the Pearl River Relief (Bridge N$1.1M · Ste-Bil Grading Inc. |
| Jun 24, 2025 | Regular | 5 | – | $13.2M | 3.20 | 0% | −16.8% | $2.3M | Overlay approximately 9.8 miles on SR 18 from Tallahala Cree$5.1M · Dunn Roadbuilders, LLC |
| May 28, 2025 | Regular | 13 | 3 | $37.2M | 3.23 | 8% | −17.4% | $3.6M | Remove & Replace OGFC Lift on approximately 2 miles of I-220$11.3M · APAC - Mississippi, Inc. |
| Apr 30, 2025 | Regular | 2 | – | $5.9M | 2.50 | 0% | −1.4% | $358K | Mill & Overlay & Concrete Rehabilitation on approximately 2 $3.9M · A J Construction, Inc. |
| Apr 23, 2025 | Regular | 1 | – | $996K | 5.00 | 0% | −12.0% | $160K | Bridge Repair on SR 33 (Bridge No. 34.6)$996K · Hemphill Construction Company, Inc. |
| Apr 22, 2025 | Regular | 10 | 1 | $22.1M | 3.10 | 10% | −1.0% | $13.3M | Tree Removal along Various Routes in District 7$4.0M · Holliday Construction, LLC |
| Apr 1, 2025 | Regular | 2 | – | $13.5M | 2.50 | 0% | −10.3% | $1.6M | Roundabout Construction on SR 15 at SR 16 & Bridge Replaceme$9.0M · Cook & Son, LLC |
| Mar 25, 2025 | Regular | 6 | – | $38.6M | 2.83 | 17% | −0.2% | $2.5M | Installation of Median Cable Barrier on I-22 from Coldwater $15.2M · Ste-Bil Grading Inc. |
| Mar 4, 2025 | Regular | 1 | – | $97.4M | 2.00 | 0% | +8.5% | $7.0M | Grade Bridge, Pave 2-Lane on SR 19 from 0.25 miles South of $97.4M · W. G. Yates & Sons Construction Company |
| Feb 25, 2025 | Regular | 11 | 1 | $85.9M | 3.09 | 18% | −1.5% | $9.9M | Mill & Overlay approximately 14 miles of US 72 from the Tipp$14.8M · APAC - Mississippi, Inc. |
| Feb 4, 2025 | Regular | 1 | – | $9.5M | 1.00 | 100% | +24.7% | $0 | Roundabout Construction on SR 15 at SR 16 & Bridge Replaceme$9.5M · Joe McGee Construction Company, Inc. |
| Jan 31, 2025 | Regular | 1 | – | $2.2M | 1.00 | 100% | +7.3% | $0 | Construction of Administration Building Water Well Upgrades$2.2M · Paramount Construction Group, LLC |
| Jan 28, 2025 | Regular | 11 | 1 | $67.7M | 3.09 | 18% | −5.5% | $2.6M | Mill & Overlay approximately 7 miles of SR 16 from lane mile$15.1M · Falcon Contracting Company, Inc. |
| Dec 5, 2024 | Special | 12 | – | $52.8M | 2.67 | 17% | −2.8% | $6.0M | Interchange Reconstruction on I-20 at Flowers$13.4M · T. L. Wallace Construction, Inc. |
| Dec 3, 2024 | Special | 1 | – | $1.7M | 4.00 | 0% | −3.6% | $642K | Bridge Repair on SR 2 over the Tuscumbia River and reliefs ($1.7M · Century Construction Group, Inc. |
| Nov 26, 2024 | Regular | 16 | – | $77.9M | 3.25 | 13% | −7.6% | $4.2M | Mill & Overlay approximately 15 miles of US 45A from the Nox$13.1M · Falcon Contracting Company, Inc. |
| Nov 7, 2024 | Special | 1 | – | $24.6M | 4.00 | 0% | +8.2% | $1.1M | Bridge Replacement on SR 12 over the Sunflower River (Bridge$24.6M · Malouf Construction, LLC |
| Oct 22, 2024 | Regular | 17 | – | $64.0M | 2.47 | 29% | −12.0% | $3.4M | Bridge Repair on I-20 over the Big Black River & Reliefs (Br$17.1M · Key, LLC |
| Oct 10, 2024 | Emergency | 3 | 1 | $2.1M | 2.33 | 0% | −21.6% | $985K | Emergency Slide Repair on US 80 in Forest$1.1M · Joe McGee Construction Company, Inc. |
| Oct 2, 2024 | Special | 2 | – | $6.2M | 2.50 | 0% | +10.0% | $271K | Bridge Repair on US 82 over Bogue Phalia (Bridge Nos. 22.1 A$3.5M · Gibson & Associates, Inc. |
| Sep 25, 2024 | Regular | 9 | – | $31.8M | 2.56 | 11% | −7.6% | $2.8M | Overlay approximately$9.5M · APAC - Mississippi, Inc. |
| Sep 4, 2024 | Special | 7 | – | $20.3M | 2.86 | 0% | −10.1% | $1.4M | Mill & Overlay approximately 15 miles of SR 2 from the Tippa$4.7M · APAC - Mississippi, Inc. |
| Aug 27, 2024 | Regular | 5 | – | $12.6M | 3.40 | 0% | −13.3% | $1.7M | Construction project, Yalobusha County$11.1M · Phillips Contracting Co., Inc. |
| Jul 30, 2024 | Special | 2 | – | $37.1M | 3.50 | 0% | −8.9% | $7.7M | Pavement Restoration on approximately 11 miles of US 49 from$29.2M · APAC - Mississippi, Inc. |
| Jul 24, 2024 | Special | 1 | – | $559K | 4.00 | 0% | −45.3% | $51K | Construction project, Jefferson County$559K · Maynord Landscaping Co., Inc. |
| Jul 23, 2024 | Regular | 14 | 1 | $41.4M | 2.29 | 21% | −8.2% | $3.1M | Scrub Seal & Overlay approximately 10 miles of US 61 from Cl$9.7M · Lehman-Roberts Company |
| Jul 16, 2024 | Emergency | 1 | – | $257K | 4.00 | 0% | −56.7% | $245K | Emergency Removal & Replacement of existing pipe located on $257K · Holliday Construction, LLC |
| Jul 11, 2024 | Special | 5 | – | $87.0M | 3.20 | 20% | −0.9% | $887K | Construction project, Madison County$59.5M · Eutaw Construction Company, Inc. |
| Jun 25, 2024 | Regular | 6 | 3 | $13.1M | 2.50 | 0% | +20.6% | $4.8M | Overlay approximately$5.3M · Cook & Son, LLC |
| Jun 11, 2024 | Special | 1 | – | $4.9M | 5.00 | 0% | −36.9% | $495K | Construction project, Lafayette County$4.9M · Cook & Son, LLC |
| Jun 4, 2024 | Special | 1 | – | $15.9M | 7.00 | 0% | −20.9% | $1.8M | Bridge Replacements on US$15.9M · Ste-Bil Grading Inc. |
| May 29, 2024 | Regular | 15 | 1 | $42.8M | 2.47 | 7% | −12.2% | $6.1M | Overlay approximately$6.5M · APAC - Mississippi, Inc. |
| May 1, 2024 | Special | 1 | – | $1000K | 4.00 | 0% | −19.0% | $86K | Construction project, Madison County$1000K · Talbot Brothers Contracting Co., Inc. |
| Apr 23, 2024 | Regular | 12 | 4 | $228M | 2.42 | 17% | −8.1% | $39.0M | Grade, Drain, Pave on SR 2 from existing SR 15 to SR$195M · W. G. Yates & Sons Construction Company |
| Apr 2, 2024 | Special | 1 | – | $17.5M | 7.00 | 0% | −27.4% | $3.4M | Construction project, Madison County$17.5M · Talbot Brothers Contracting Co., Inc. |
| Mar 26, 2024 | Regular | 4 | 1 | $87.1M | 1.25 | 75% | +5.0% | $1.0M | Pavement Restoration of approximately 5 miles of I-55 from S$76.0M · Barriere Construction Company, LLC |
| Mar 15, 2024 | Emergency | 1 | – | $398K | 3.00 | 0% | +50.0% | $88K | Construction project, Forrest County$398K · Key, LLC |
| Mar 5, 2024 | Special | 2 | – | $6.1M | 3.00 | 0% | −17.7% | $1.1M | Construction project, Kemper County$3.1M · T. L. Wallace Construction, Inc. |
| Feb 27, 2024 | Regular | 5 | – | $15.8M | 2.00 | 20% | −14.4% | $514K | Mill & Overlay approximately 15 miles of SR 12 from US 49W t$5.5M · A J Construction, Inc. |
| Jan 31, 2024 | Special | 4 | – | $23.4M | 4.00 | 0% | +1.0% | $650K | Bridge Replacement on US$12.2M · Century Construction Group, Inc. |
| Jan 24, 2024 | Regular | 13 | – | $163M | 2.54 | 23% | −11.5% | $10.1M | Construction project, Jackson County$79.4M · Eutaw Construction Company, Inc. |
| Dec 5, 2023 | Special | 3 | – | $223M | 2.67 | 33% | +2.8% | $9.0M | Widening of I-10 from Diamondhead to County Farm Road, Insta$156M · Huey P Stockstill, LLC |
| Nov 28, 2023 | Regular | 9 | – | $48.7M | 2.56 | 33% | −18.0% | $2.1M | Construction project, Warren County$9.9M · Superior Asphalt, Inc. |
| Nov 7, 2023 | Emergency | 1 | – | $480K | 2.00 | 0% | −24.6% | $15K | Construction project, Harrison County$480K · Key, LLC |
| Nov 2, 2023 | Special | 1 | 1 | $57.8M | 2.00 | 0% | +15.7% | $12.9M | Bridge Replacements & Bank Stabilization on US 98 at the Pea$57.8M · T. L. Wallace Construction, Inc. |
| Oct 26, 2023 | Emergency | 1 | – | $278K | 2.00 | 0% | +6.1% | $81K | Construction project, Lauderdale County$278K · Key, LLC |
| Oct 24, 2023 | Regular | 9 | 2 | $48.1M | 2.67 | 22% | −21.8% | $5.8M | Overlay approximately$28.2M · APAC - Mississippi, Inc. |
| Oct 12, 2023 | Emergency | 1 | – | $828K | 3.00 | 0% | −39.8% | $32K | Construction project, Hinds County$828K · Key, LLC |
| Sep 27, 2023 | Regular | 4 | – | $50.0M | 4.75 | 0% | +10.5% | $2.1M | Construction project, Jackson County$27.9M · Key, LLC |
| Aug 22, 2023 | Regular | 8 | – | $54.1M | 2.75 | 13% | −20.3% | $10.8M | Bridge Replacements on US$25.7M · Key, LLC |
| Aug 1, 2023 | Emergency | 2 | – | $61.6M | 2.00 | 0% | +70.7% | $2.5M | Construction project, Pontotoc County$58.7M · Talbot Brothers Contracting Co., Inc. |
| Jul 25, 2023 | Regular | 10 | – | $37.7M | 1.70 | 40% | +5.3% | $1.4M | Overlay approximately 16 miles of SR 448 from SR 1 to US$6.4M · APAC - Mississippi, Inc. |
| Jun 27, 2023 | Regular | 8 | – | $40.3M | 2.75 | 0% | −11.2% | $5.2M | Safety Improvements on approximately$19.8M · Falcon Contracting Company, Inc. |
| Jun 23, 2023 | Emergency | 1 | – | $420K | 1.00 | 100% | +54.0% | $0 | Construction project, Forrest County$420K · Key, LLC |
| May 30, 2023 | Special | 1 | – | $8.9M | 2.00 | 0% | +8.7% | $1.3M | Bridge Replacements on SR 397 between SR$8.9M · Cotton Creek Transport, Inc. |
| May 23, 2023 | Regular | 17 | – | $68.7M | 2.24 | 35% | −6.8% | $6.0M | Overlay approximately$12.6M · APAC - Mississippi, Inc. |
| May 2, 2023 | Emergency | 4 | – | $5.8M | 4.00 | 0% | −16.6% | $872K | Bridge Replacement on SR 415 over Bowie Branch between SR$2.9M · Cotton Creek Transport, Inc. |
| Apr 25, 2023 | Regular | 11 | – | $40.3M | 2.27 | 36% | −19.7% | $2.8M | Bridge Replacement on SR$6.9M · Chris Albritton Construction Company, Inc. |
| Mar 28, 2023 | Regular | 4 | – | $13.5M | 2.75 | 50% | −13.9% | $90K | Overlay approximately 3.4 miles of SR$5.0M · APAC - Mississippi, Inc. |
| Feb 28, 2023 | Regular | 6 | – | $60.5M | 3.50 | 33% | −2.7% | $1.3M | Overlay approximately$37.7M · Huey P Stockstill, LLC |
| Jan 27, 2023 | Emergency | 1 | – | $759K | 8.00 | 0% | −22.8% | $22K | Construction project, Holmes County$759K · Hemphill Construction Company, Inc. |
| Jan 25, 2023 | Regular | 13 | 1 | $52.2M | 2.69 | 31% | −2.7% | $3.0M | Overlay approximately$17.5M · Falcon Contracting Company, Inc. |
| Dec 2, 2022 | Emergency | 3 | – | $1.6M | 1.67 | 67% | −37.8% | $49K | Emergency Bridge Repair on US$941K · Riverside Construction Company, Inc. |
| Nov 22, 2022 | Regular | 15 | 2 | $84.8M | 2.20 | 33% | +2.8% | $6.1M | Overlay approximately$28.4M · Lehman-Roberts Company |
| Oct 31, 2022 | Special | 3 | – | $12.1M | 1.00 | 100% | +15.3% | $0 | Safety Improvements along SR$6.2M · Phillips Contracting Co., Inc. |
| Oct 25, 2022 | Regular | 13 | – | $253M | 2.00 | 46% | −11.2% | $23.1M | Grade, Drain, Bridge & Pave 4-Lane approximately 9 miles of $213M · W. G. Yates & Sons Construction Company |
| Oct 5, 2022 | Special | 1 | – | $1.2M | 1.00 | 100% | −6.8% | $0 | Construction project, Hinds County$1.2M · Joe McGee Construction Company, Inc. |
| Sep 28, 2022 | Regular | 19 | – | $85.2M | 2.05 | 47% | −1.5% | $5.2M | Construction project, Jackson County$25.2M · T. L. Wallace Construction, Inc. |
| Sep 27, 2022 | Emergency | 2 | – | $1.0M | 2.00 | 50% | −17.1% | $38K | Bridge Repair on SR$560K · M & N Excavators, Inc. |
| Sep 9, 2022 | Emergency | 0 | 2 | $0 | – | – | – | $0 | – |
| Aug 23, 2022 | Regular | 5 | 1 | $39.3M | 2.20 | 20% | +8.1% | $1.5M | Overlay project, Hinds & Rankin County$22.1M · APAC - Mississippi, Inc. |
| Aug 19, 2022 | Emergency | 1 | 1 | $76K | 4.00 | 0% | −1.0% | $48K | Bridge Repair on US$76K · Century Construction Group, Inc. |
| Jul 27, 2022 | Regular | 10 | 3 | $49.0M | 2.00 | 50% | +6.8% | $1.3M | Overlay approximately$17.2M · APAC - Mississippi, Inc. |
| Jul 7, 2022 | Emergency | 1 | – | $725K | 4.00 | 0% | −6.7% | $6K | Debris Removal & Embankment Stabilization on US$725K · Century Construction Group, Inc. |
| Jun 29, 2022 | Emergency | 1 | – | $1.3M | 3.00 | 0% | −25.8% | $178K | Construction project, Jackson County$1.3M · Key, LLC |
| Jun 28, 2022 | Regular | 13 | 4 | $26.4M | 3.15 | 0% | +1.2% | $2.4M | Overlay approximately 8.5 miles of US$7.9M · Falcon Contracting Company, Inc. |
| May 24, 2022 | Regular | 22 | 4 | $146M | 1.68 | 59% | +5.4% | $4.9M | 9 ) / 107958303 Coahoma Mill & Overlay approximately 12 mile$21.7M · Lehman-Roberts Company |
| May 10, 2022 | Emergency | 1 | – | $89K | 4.00 | 0% | – | $36K | Bridge Repair (Bridge No. 68.1) on Country Club Road over US$89K · Gibson & Associates, Inc. |
| May 4, 2022 | Special | 1 | – | $6.4M | 1.00 | 100% | +2.4% | $0 | Overlay approximately$6.4M · APAC - Mississippi, Inc. |
| Apr 26, 2022 | Regular | 15 | – | $60.3M | 2.07 | 40% | +5.1% | $4.2M | Overlay approximately$8.9M · APAC - Mississippi, Inc. |
| Apr 8, 2022 | Emergency | 1 | – | $440K | 5.00 | 0% | −5.0% | $68 | Bridge Repair on SR$440K · Joe McGee Construction Company, Inc. |
| Mar 22, 2022 | Regular | 13 | 3 | $83.1M | 1.85 | 31% | +5.7% | $1.7M | Overlay approximately$39.0M · APAC - Mississippi, Inc. |
| Mar 4, 2022 | Emergency | 2 | – | $885K | 3.00 | 0% | −27.2% | $59K | Construction project, Hancock County$810K · Key, LLC |
| Mar 2, 2022 | Special | 2 | – | $27.5M | 10.00 | 0% | −28.1% | $780K | Construction project, Calhoun County$24.2M · Manhattan Road & Bridge Company |
| Feb 23, 2022 | Regular | 15 | 2 | $98.3M | 2.40 | 33% | −1.2% | $7.8M | Construction project, Calhoun County$24.6M · T. L. Wallace Construction, Inc. |
| Jan 25, 2022 | Regular | 10 | 2 | $50.5M | 3.80 | 10% | +3.1% | $3.0M | Bridge Replacement on SR$11.5M · Key, LLC |
| Dec 29, 2021 | Emergency | 1 | – | $2.1M | 5.00 | 0% | +18.7% | $44K | Removal and Disposal of Debris on various routes throughout $2.1M · Dozer, LLC |
| Nov 30, 2021 | Emergency | 1 | – | $686K | 5.00 | 0% | −12.4% | $92K | Construction project, Madison County$686K · Key, LLC |
| Nov 23, 2021 | Regular | 9 | – | $152M | 2.44 | 33% | −0.1% | $17.0M | Grade, Drain, Bridge & Pave 4-Lane for approximately 9 miles$137M · Eutaw Construction Company, Inc. |
| Nov 2, 2021 | Special | 1 | – | $3.7M | 6.00 | 0% | −47.3% | $188K | Construction project, DeSoto County$3.7M · Louis - Company, LLC |
| Oct 26, 2021 | Regular | 12 | 1 | $52.8M | 2.58 | 8% | +1.4% | $3.1M | Bridge Replacements on SR$29.8M · W. G. Yates & Sons Construction Company |
| Oct 7, 2021 | Emergency | 1 | – | $1.8M | 4.00 | 0% | −23.4% | $356K | Emergency Slide Repair on SR$1.8M · T. L. Wallace Construction, Inc. |
| Sep 28, 2021 | Regular | 10 | 3 | $44.0M | 2.80 | 20% | −2.3% | $1.9M | Overlay approximately$16.1M · W. E. Blain & Sons, Inc. |
| Sep 22, 2021 | Emergency | 0 | 1 | $0 | – | – | – | $0 | – |
| Aug 24, 2021 | Regular | 4 | 1 | $29.7M | 3.25 | 0% | +7.6% | $908K | Construction project, Jackson County$25.5M · Talbot Bros Contr Co, Inc & Talbot Bros Grading Co, Inc, AJV |
| Jul 27, 2021 | Regular | 14 | 1 | $99.4M | 2.36 | 21% | +3.1% | $14.5M | Pavement Restoration approximately 14 miles on I-59 from the$66.8M · Dunn Roadbuilders, LLC |
| Jul 22, 2021 | Emergency | 1 | – | $310K | 5.00 | 0% | −40.4% | $42K | Slide Repair on SR 41 approximately 550 feet North of the SR$310K · Cook & Son, LLC |
| Jul 7, 2021 | Emergency | 1 | – | $2.5M | 8.00 | 0% | +11.3% | $19K | Construction project, Copiah County$2.5M · Cotton Creek Transport, Inc. |
| Jun 23, 2021 | Emergency | 1 | – | $148K | 2.00 | 0% | −28.0% | $61K | Bridge Repair on SR$148K · Key, LLC |
| Jun 22, 2021 | Regular | 25 | 3 | $76.7M | 2.60 | 12% | −4.6% | $6.3M | Overlay approximately$10.0M · APAC - Mississippi, Inc. |
| May 26, 2021 | Emergency | 2 | – | $1.1M | 4.00 | 0% | −5.4% | $255K | Removal and Disposal of Debris on various routes in District$672K · Looks Great Services of MS, Inc. |
| May 25, 2021 | Regular | 17 | 1 | $54.0M | 2.94 | 6% | +2.0% | $5.6M | Thin Lift Overlay approximately 8 miles on US 45 from SR 145$8.6M · Dunn Roadbuilders, LLC |
| Apr 27, 2021 | Regular | 15 | 2 | $42.6M | 1.87 | 40% | −3.0% | $2.0M | Overlay approximately$7.2M · APAC - Mississippi, Inc. |
| Mar 23, 2021 | Regular | 12 | 1 | $40.7M | 3.00 | 8% | +3.4% | $5.1M | Bridge Replacement on US$12.5M · Talbot Bros Contr Co, Inc & Talbot Bros Grading Co, Inc, AJV |
| Mar 10, 2021 | Special | 1 | – | $1.4M | 5.00 | 0% | −4.2% | $136K | Construction project, Madison County$1.4M · Olympus Painting Contractors, Inc. |
| Mar 2, 2021 | Special | 11 | 1 | $34.9M | 2.36 | 27% | +1.6% | $3.1M | Overlay approximately$7.3M · APAC - Mississippi, Inc. |
| Jan 26, 2021 | Regular | 10 | – | $52.5M | 2.40 | 40% | +4.3% | $795K | Overlay approximately$20.9M · Lehman-Roberts Company |
| Nov 24, 2020 | Regular | 7 | – | $8.4M | 3.43 | 0% | −4.2% | $780K | Overlay approximately$2.4M · Lehman-Roberts Company |
| Oct 27, 2020 | Regular | 6 | – | $45.6M | 4.00 | 17% | −14.1% | $2.5M | Construction project, Neshoba County$35.6M · W. G. Yates & Sons Construction Company |
| Oct 2, 2020 | Emergency | 1 | – | $939K | 4.00 | 0% | −5.8% | $60K | Construction project, Lee County$939K · Cook & Son, LLC |
| Sep 29, 2020 | Emergency | 2 | – | $1.5M | 3.00 | 0% | −17.2% | $137K | Construction project, Itawamba County$1.1M · Century Construction Group, Inc. |
| Sep 22, 2020 | Regular | 13 | 1 | $43.5M | 3.38 | 8% | −6.0% | $9.0M | Construction project, Harrison County$22.5M · C. E. C., Inc. |
| Aug 25, 2020 | Regular | 6 | – | $10.2M | 3.50 | 0% | −7.4% | $1.2M | Mill & Overlay approximately 11 miles of SR 21 from Dixon to$3.3M · Dickerson & Bowen, Inc. |
| Aug 4, 2020 | Emergency | 1 | – | $57K | 2.00 | 0% | −37.4% | $53K | Removal and Disposal of Debris on various routes in District$57K · Holliday Construction, LLC |
| Jul 28, 2020 | Regular | 7 | 1 | $24.3M | 2.29 | 29% | −8.0% | $1.2M | And IM-0059-01(126) / 107825302 in Forrest & Lamar Mill & Ov$11.3M · Dunn Roadbuilders, LLC |
| Jul 23, 2020 | Emergency | 1 | – | $177K | 2.00 | 0% | −30.0% | $60K | Smith. Removal and Disposal of Debris on various routes in D$177K · Looks Great Services of MS, Inc. |
| Jun 23, 2020 | Regular | 17 | 1 | $15.9M | 2.35 | 6% | −4.9% | $1.5M | Overlay approximately$3.5M · APAC - Mississippi, Inc. |
| Jun 18, 2020 | Emergency | 2 | – | $1.3M | 3.50 | 0% | −50.2% | $96K | Slide Repair on US 49 4.7 miles South of SR$1.3M · Hemphill Construction Company, Inc. |
| Jun 11, 2020 | Emergency | 3 | – | $2.4M | 3.67 | 0% | −39.0% | $977K | Bridge Repairs on County Road$1.6M · Century Construction Group, Inc. |
| May 28, 2020 | Emergency | 2 | – | $596K | 3.00 | 0% | −38.0% | $246K | Basin Flood Damage February 2020 in District$310K · T. L. Wallace Construction, Inc. |
| May 27, 2020 | Regular | 13 | – | $26.9M | 2.38 | 23% | −5.6% | $2.1M | Construction project, Marion County$8.9M · T. L. Wallace Construction, Inc. |
| May 21, 2020 | Emergency | 0 | 1 | $0 | – | – | – | $0 | – |
| Apr 28, 2020 | Regular | 14 | – | $30.3M | 2.57 | 14% | −5.5% | $1.8M | Bridge Replacements on SR$13.8M · T. L. Wallace Construction, Inc. |
| Apr 17, 2020 | Emergency | 3 | – | $537K | 4.33 | 0% | −16.8% | $64K | Construction project, Prentiss & Tippah County$212K · J. M. Duncan, Inc. |
| Apr 1, 2020 | Emergency | 1 | – | $2.1M | 8.00 | 0% | −26.2% | $154K | Slide Repair on HWY 16 approximately 1.5 miles East of US$2.1M · Riverside Construction Company, Inc. |
| Mar 26, 2020 | Emergency | 2 | – | $1.7M | 3.50 | 50% | −2.6% | $105K | Construction project, Webster County$1.2M · Cook & Son, LLC |
| Mar 24, 2020 | Regular | 9 | 2 | $87.0M | 2.78 | 44% | +8.6% | $2.6M | Construction project, Jackson County$51.2M · Dement Construction Company, LLC |
| Feb 25, 2020 | Regular | 9 | 2 | $131M | 1.89 | 33% | +4.4% | $3.8M | Grade, Drain, Bridge, & Pave 4-Lane approximately 9 miles of$81.0M · Eutaw Construction Company, Inc. |
| Feb 6, 2020 | Special | 1 | – | $14.2M | 2.00 | 0% | −12.6% | $323K | Overlay approximately$14.2M · Warren Paving, Inc. |
| Jan 28, 2020 | Regular | 16 | 1 | $81.7M | 2.81 | 38% | +3.0% | $1.6M | Overlay approximately$14.6M · APAC - Mississippi, Inc. |
"Rejected" counts contracts whose bids MDOT threw out: the same project came back to a later letting within 18 months. They are not counted as awarded.
BidCrew tracks every DOT letting: line-item prices, competitor history, and a predicted low bid before you submit.