MDOT let 13 contracts worth $26.9M at the low bid, with 2.38 bidders per contract (the 12-month average is 3.70). T. L. Wallace Construction, Inc. won the most, $8.9M; 9 firms won at least one contract. The closest finish: Construction project, Copiah County, decided by 0.7% ($5K).
| Call | Contract | Low bidder | Low bid | Second | Gap | Bidders | vs. estimate |
|---|---|---|---|---|---|---|---|
| 2 | Construction project, Marion CountyMarion · Construction & widening · 102471301 | T. L. Wallace Construction, Inc. | $8.9M | – | – | 1 | −5.6% |
| 7 | Overlay approximatelyDeSoto · Overlay & resurfacing · 307079301 | Lehman-Roberts Company2nd: Standard Construction Company, Inc. | $4.5M | $5.1M | 15.1% | 2 | +3.3% |
| 1 | Mill & Overlay approximately 8 miles of SR 8 from 0.37 miles West of SR 9 to stop bar at SRCalhoun · Overlay & resurfacing · 107960301 | Gregory Companies, LLC dba Murphree Paving2nd: Century Construction Group, Inc. | $3.1M | $3.2M | 4.6% | 4 | +7.1% |
| 6 | Mill & Overlay on US 278 from SR 25 to SRMonroe · Overlay & resurfacing · 306970301 | Falcon Contracting Company, Inc.2nd: APAC - Mississippi, Inc. | $2.9M | $3.3M | 12.5% | 4 | −5.4% |
| 10 | Overlay approximatelyClarke · Overlay & resurfacing · 307114301 | Dunn Roadbuilders, LLC2nd: Walters Construction Co., Inc. | $2.0M | $2.2M | 13.0% | 2 | −19.4% |
| 9 | Construction project, Noxubee CountyNoxubee · Construction & widening · 306928301 | Falcon Contracting Company, Inc.2nd: Gregory Companies, LLC dba Murphree Paving | $1.3M | $1.6M | 22.9% | 3 | −19.3% |
| 13 | Mill & Overlay approximately 1 mile of SR 930 from Junkin Street/Melrose Avenue to SR 555, approximately 1 mile of SR 93Adams · Overlay & resurfacing · 307073301 | W. E. Blain & Sons, Inc. | $799K | – | – | 1 | −2.1% |
| 12 | Construction project, Walthall CountyWalthall · Construction & widening · 306940301 | Dickerson & Bowen, Inc.2nd: Dunn Roadbuilders, LLC | $783K | $852K | 8.9% | 3 | −15.4% |
| 3 | Construction project, Copiah CountyCopiah · Construction & widening · 108280301 | Key, LLC2nd: Century Construction Group, Inc. | $755K | $761K | 0.7% | 3 | −16.0% |
| 8 | Mill & Overlay approximately 1.3 miles of SR 19 from end of proposed 4-Lane to SRNeshoba · Overlay & resurfacing · 306932301 | Dickerson & Bowen, Inc.2nd: APAC - Mississippi, Inc. | $716K | $925K | 29.2% | 2 | −18.5% |
| 11 | Overlay approximately 2.3 miles of SRCovington · Overlay & resurfacing · 307070301 | W. E. Blain & Sons, Inc.2nd: Dunn Roadbuilders, LLC | $560K | $598K | 6.8% | 2 | −22.5% |
| 4 | Construction project, Madison CountyMadison · Construction & widening · 108402301 | Key, LLC2nd: Century Construction Group, Inc. | $467K | $471K | 1.0% | 3 | −2.0% |
| 5 | Construction projectDistrict 1 · Construction & widening · 306953301 | Akca, LLC | $266K | – | – | 1 | −2.3% |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew.
BidCrew tracks every DOT letting: line-item prices, competitor history, and a predicted low bid before you submit.