10 counties run from the Newton office: Hinds, Kemper, Lauderdale, Leake, Madison, Neshoba, Newton, Noxubee, Rankin, Scott. District 5 let 27% of Mississippi's highway dollars over the last three years, first of six districts.
Over the last three years T. L. Wallace Construction, Inc. won 21% of the district's dollars, followed by APAC - Mississippi, Inc. (16%) and Cotton Creek Transport, Inc. (11%). 68 firms bid here and 36 won at least once.
| Firm | Bids | Wins | Win rate | Awarded | Share | Median margin when winning |
|---|---|---|---|---|---|---|
| T. L. Wallace Construction, Inc.Columbia | 8 | 3 | 38% | $192M | 21.4% | 3.3% |
| APAC - Mississippi, Inc.Richland | 32 | 18 | 56% | $142M | 15.9% | 5.3% |
| Cotton Creek Transport, Inc.Laurel | 5 | 3 | 60% | $102M | 11.4% | 22.6% |
| W. G. Yates & Sons Construction CompanyJackson | 5 | 1 | 20% | $97.4M | 10.9% | 7.2% |
| Hemphill Construction Company, Inc.Florence | 12 | 4 | 33% | $61.2M | 6.8% | 12.8% |
| Key, LLCMadison | 30 | 10 | 33% | $60.2M | 6.7% | 6.2% |
| Eutaw Construction Company, Inc.Madison | 2 | 1 | 50% | $59.5M | 6.6% | 0.9% |
| Dickerson & Bowen, Inc.Brookhaven | 23 | 5 | 22% | $24.6M | 2.7% | 8.4% |
| Joe McGee Construction Company, Inc.Lake | 17 | 6 | 35% | $20.3M | 2.3% | 3.2% |
| Superior Asphalt, Inc.Byram | 15 | 3 | 20% | $18.8M | 2.1% | 0.5% |
| Talbot Brothers Contracting Co., Inc.Nesbit | 3 | 2 | 67% | $18.5M | 2.1% | 14.1% |
| Falcon Contracting Company, Inc.Columbus | 9 | 1 | 11% | $15.1M | 1.7% | 2.8% |
| Vance Brothers, LLCKansas City | 3 | 2 | 67% | $11.5M | 1.3% | 18.1% |
| Cook & Son, LLCSmithville | 9 | 1 | 11% | $9.0M | 1.0% | 4.3% |
| A J Construction, Inc.Flowood | 13 | 2 | 15% | $8.3M | 0.9% | 2.9% |
| County | Contracts | Awarded | Bidders / contract | Single-bid | Low vs. estimate |
|---|---|---|---|---|---|
| Madison | 23 | $332M | 3.04 | 4% | −6.7% |
| Neshoba | 10 | $139M | 3.10 | 10% | +4.8% |
| Rankin | 16 | $121M | 2.94 | 13% | −2.2% |
| Hinds | 25 | $96.7M | 2.76 | 20% | −8.2% |
| Lauderdale | 12 | $50.0M | 2.42 | 8% | −3.5% |
| Newton | 5 | $42.4M | 2.40 | 20% | −4.1% |
| Leake | 8 | $33.1M | 3.88 | 0% | −10.3% |
| Noxubee | 4 | $29.5M | 3.75 | 0% | −9.1% |
| Kemper | 4 | $18.9M | 3.00 | 0% | −16.2% |
| Scott | 3 | $4.6M | 2.00 | 0% | −10.1% |
| Work type | Contracts | Awarded | Bidders / contract | Low vs. estimate |
|---|---|---|---|---|
| Overlay & resurfacing | 31 | $197M | 3.19 | −6.7% |
| Construction & widening | 34 | $363M | 2.74 | −5.3% |
| Bridge repair & rehab | 18 | $197M | 3.06 | −0.9% |
| Bridge replacement | 7 | $120M | 3.71 | +4.6% |
| Intersections & safety | 3 | $10.6M | 2.67 | +4.1% |
| Buildings & other | 5 | $8.4M | 3.60 | −3.1% |
| Let | Contract | Low bidder | Low bid | Bidders | Gap to 2nd | vs. estimate |
|---|---|---|---|---|---|---|
| Oct 27, 2026 | OGFC Lift on I-59 from US 45 to approximately 0.248 miles north of the Russell Interchange & Fog Seal approximLauderdale · Overlay & resurfacing | APAC - Mississippi, Inc. | $3.9M | 1 | – | +9.7% |
| Oct 27, 2026 | Construction project, Madison CountyMadison · Construction & widening | T. L. Wallace Construction, Inc. | $188M | 3 | 2.9% | +4.8% |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 471 at the SR 25 InterRankin · Bridge repair & rehab | Hemphill Construction Company, Inc. | $57.2M | 6 | 7.9% | −0.4% |
| Aug 25, 2026 | Bridge Replacement on SR 486 (Bridge No. 1.0)Neshoba · Bridge replacement | Ste-Bil Grading Inc. | $2.4M | 4 | 3.0% | +8.1% |
| Jul 28, 2026 | Building Improvements at MDOT Parking Garage DowntownHinds · Buildings & other | Python Corporation | $1.2M | 4 | 23.0% | +9.6% |
| Jul 28, 2026 | Thin Lift Overlay approximately 10.2 miles of MS 467 from beginning of maintenance to South of EdwardsHinds · Overlay & resurfacing | A J Construction, Inc. | $4.3M | 3 | 1.5% | −1.7% |
| Jun 23, 2026 | Bridge Repair on SR 22 over Persimmon Creek (Bridge No. 32.5)Madison · Bridge repair & rehab | Hemphill Construction Company, Inc. | $83K | 7 | 17.8% | +7.4% |
| May 27, 2026 | Thin Lift Overlay of MS 16 from Thompson Drive to the Intersection of MS 15Neshoba · Overlay & resurfacing | Dickerson & Bowen, Inc. | $2.6M | 5 | 8.4% | −11.5% |
| May 27, 2026 | Bridge Replacement on SR 427 (Bridge No. 4.4) between SR 488 & SR 16Leake · Bridge replacement | Joe McGee Construction Company, Inc. | $3.1M | 8 | 0.5% | −11.9% |
| May 27, 2026 | Installation of Center Line Rumble Strips on MS 18 from Old Port Gibson Road to the Copiah County LineHinds · Construction & widening | Traffic Control Products Company, Inc. | $748K | 1 | – | +5.9% |
| May 27, 2026 | Traffic Signal Improvements on MS 16 at Van Buren, and Mill & Overlay approximately 6 miles of MS 35 from PleaLeake · Overlay & resurfacing | Superior Asphalt, Inc. | $5.4M | 4 | 2.4% | +2.9% |
| May 27, 2026 | Pavement Restoration of US 49 from the Hinds County Line to the Yazoo County Line, and ITS Improvements on US Madison, Hinds, Yazoo · Construction & widening | APAC - Mississippi, Inc. | $18.6M | 4 | 1.4% | −8.9% |
| May 27, 2026 | Intersection Improvements on US 45 from Misso Road to Magnolia Drive, and Mill & Overlay approximately 12 mileNoxubee · Overlay & resurfacing | APAC - Mississippi, Inc. | $20.6M | 2 | 0.2% | +9.6% |
| Apr 28, 2026 | District 5 Placement of Raised Pavement Markers throughout the DistrictDistrictwide · Construction & widening | Arkansas Sign & Barricade, Inc. | $451K | 3 | 3.3% | −47.2% |
| Apr 28, 2026 | Ultra-Thin Overlay & Safety Improvements on approximately 8 miles of existing SR 482 from north of the SR 16 tNeshoba · Overlay & resurfacing | Superior Asphalt, Inc. | $3.0M | 4 | 0.5% | −5.7% |
| Letting | County | Route | Scope | Description |
|---|---|---|---|---|
| November 2026 | Madison | MS 463 | Traffic Signal | HWY 463 at Stribling Road |
| November 2026 | Hinds | US 80 | Median Barrier | US 80 from Clinton-Raymond Road to Shaw Road |
| November 2026 | Madison | I 55 | OGFC Lift | I-55 from Church Rd to Heindl Road |
| November 2026 | Madison | I 55 | Bridge Repair | I-55 over Church Road (Bridge #s 112.3 A & 112.3 B) |
| November 2026 | Madison | I 55 | Fog Seal | I-55 from Heindl Road to Yazoo County Line |
| November 2026 | Districtwide | Storm Damage | District 5 Emergency Maintenance Contract | |
| November 2026 | Scott | Building Construction | Construction of Scott Co. Bulk Salt Storage | |
| November 2026 | Lauderdale | Building Construction | Construction of Lauderdale Co. Bulk Salt Storage | |
| November 2026 | Madison | Building Construction | Construction of Madison Co. Bulk Salt Storage | |
| January 2027 | Newton | MS 492 | Mill & Overlay | MS 492 from east of Sipsey Creek To Old MS 15 |
| January 2027 | Newton | MS 489 | Mill & Overlay | MS 489 through City of Union |
| January 2027 | Newton | US 80 | Bridge Replacement | US 80 Bridge Repl (119.4, 119.2, 119.5 & 119.8) |
| January 2027 | Hinds | Pedestrian Walkway | Lakeland Drive Pedestrian Bridge | |
| January 2027 | Lauderdale | MS 494 | Micro Surface | MS 494 from Newton County Line to MS 19 |
| January 2027 | Hinds | I 55 | OGFC Lift | I-55 from 0.5 mile south of High Street to the Madison County Line |
| January 2027 | Hinds | I 55 | Lighting | I-55 near East Fortification Street to just south of East Woodrow Wilson Avenue |
| January 2027 | Madison | I 55 | OGFC Lift | I-55 from Hinds CL to 0.988 Mi N of I-220 (1.881 Mi) |
| January 2027 | Hinds | I 55 | Fence | I-55 and Old Canton Road Anti-Climb Fencing - 7 locations |
| January 2027 | Madison | I 55 | Fence | I-55 Anti-Climb Fencing - 1 location |
| January 2027 | Noxubee | MS 14 | Micro Surface | MS 14 from US 45 to Alabama State Line |
| February 2027 | Newton | MS 15 | Mill & Overlay | MS 15 from Jasper County Line to north of I-20 |
| March 2027 | Rankin | US 80 | Bridge Replacement | US 80 bridge replacement over KCS RR (#56.8 A & B) |
| March 2027 | Hinds | MS 18 | Overlay | MS 18 from 0.752 mile west of Siwell Road to Greenway Drive |
| April 2027 | Lauderdale | Bridge Repair | I-20/I-59 over 22nd Avenue (Bridge # 153.0B) | |
| April 2027 | Noxubee | MS 145 | Seal & Thin Lift | MS 145 through Shuqualak |
| April 2027 | Noxubee | MS 852 | Micro Surface | MS 852 through Brooksville |
| April 2027 | Noxubee | MS 388 | Scrub Seal & Micro | MS 388 from US 45 to 8.68 miles east of US 45 |
| April 2027 | Scott | US 80 | Cape Seal | US 80 From Kalem to Forest |
| May 2027 | Rankin | US 80 | Bridge Replacement | US 80 Bridge Replacement (#60.8) - grant applied |
| May 2027 | Neshoba | MS 21 | Cape Seal | MS 21 from Scott County Line to Dixon |
| May 2027 | Newton | MS 21 | Cape Seal | SR 21 From Scott CL to Neshoba CL |
| May 2027 | Newton | MS 15 | Scrub Seal & Micro | MS 15 From Henry Mack Smith Road to Neshoba County Line |
| June 2027 | Lauderdale | Bridge Preventive Maintenance | US 80 and MS 19 (Bridge #s 152.6, 25.4A & 25.4B) - Replace bearings, epoxy repair, underseal Bent 1 - Rocker bearing plate removal and reset | |
| June 2027 | Scott | MS 481 | Bridge Preventive Maintenance | MS 481 over Fannegusha Creek (Bridge # 31.7) - Replace bearings, epoxy repair, underseal Bent 1 |
| June 2027 | Hinds | I 55 | Bridge Repair | I- 55 N ramp to Woodrow Wilson Drive (#97.0) |
| June 2027 | Districtwide | Raised Pavement Markers | D5 FY 2028 Districtwide Raised Pavement Markers | |
| June 2027 | Districtwide | Pavement Restoration | 2028 Districtwide Preventative Maintenance District 5 | |
| July 2027 | Lauderdale | MS 19 | Cape Seal | SR 19 From Alabama State Line to 2.456 Mi N of Old SR 19 |
| July 2027 | Leake | MS 35 | Scrub Seal & Micro | MS 35 from end of 4-Lane to Attala County Line |
| August 2027 | Hinds | MS 27 | Bridge Replacement | SR 27 over Tallahala Creek (#102.5) |
| October 2027 | Madison | US 51 | Safety | US 51 from Hinds County Line to just north of Colony Park Boulevard / McCellan Drive - Convert to Boulevard |
| October 2027 | Hinds | US 51 | Mill & Overlay | US 51 from beginning of maintenance to Madison County Line |
| October 2027 | Madison | US 51 | Mill & Overlay | US 51 from Hinds County Line to Rice Road |
| October 2027 | Madison | US 51 | Safety | US 51 from Hinds County Line to just north of Colony Park Boulevard / McCellan Drive - Convert to Boulevard |
Source: MDOT Schedule of Proposed Projects, Nov 21, 2026.
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. * 2026 through 2026-10-27.