MDOT District 3 · Yazoo City

District 3: $344M let in three years, 3.45 bidders a contract

12 counties run from the Yazoo City office: Bolivar, Claiborne, Copiah, Holmes, Humphreys, Issaquena, Jefferson, Sharkey, Sunflower, Warren, Washington, Yazoo. District 3 let 10% of Mississippi's highway dollars over the last three years, sixth of six districts.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Awarded, last 12 months
$123M
up 15% vs. prior 12 months
Contracts, last 12 months
24
prior 12 months: 26
Bidders per contract
3.45
statewide 3.15 · last 3 years
Single-bid contracts
14%
statewide 14% · last 3 years
Low bid vs. MDOT estimate
−7.8%
statewide −6.8% · median
On MDOT's proposed list
40
projects, next 12 months
Map

Counties in District 3

01 · Trend

Work and competition by year

Dollars awardedDistrict 3, by year
$0$50M$100M$150M$200M$27.6M2020$186M2021$79.8M2022$65.3M2023$154M2024$53.0M2025$121M2026*
Bidders per contractDistrict 3 against the state
0.01.02.03.04.05.02020202120222023202420252026*D3 4.30State
02 · Who wins

APAC - Mississippi, Inc. leads District 3

Over the last three years APAC - Mississippi, Inc. won 36% of the district's dollars, followed by Hemphill Construction Company, Inc. (12%) and Malouf Construction, LLC (7%). 63 firms bid here and 29 won at least once.

Share of District 3 dollarsLast 3 years, top 10 firms
0%10%20%30%40%APAC - Mississippi, Inc.36.3%Hemphill Construction Company, In…12.4%Malouf Construction, LLC7.1%Century Construction Group, Inc.5.4%Ste-Bil Grading Inc.5.4%Key, LLC4.6%Gibson & Associates, Inc.4.2%T. L. Wallace Construction, Inc.3.9%Dickerson & Bowen, Inc.3.4%Superior Asphalt, Inc.2.9%
FirmBidsWinsWin rateAwardedShareMedian margin when winning
APAC - Mississippi, Inc.Richland312065%$125M36.3%9.1%
Hemphill Construction Company, Inc.Florence9222%$42.7M12.4%2.2%
Malouf Construction, LLCSidon11100%$24.6M7.1%4.4%
Century Construction Group, Inc.Tupelo15747%$18.7M5.4%8.5%
Ste-Bil Grading Inc.Waterford5240%$18.6M5.4%9.8%
Key, LLCMadison23626%$15.9M4.6%10.0%
Gibson & Associates, Inc.Balch Springs16531%$14.4M4.2%7.9%
T. L. Wallace Construction, Inc.Columbia4125%$13.4M3.9%16.0%
Dickerson & Bowen, Inc.Brookhaven11545%$11.6M3.4%8.8%
Superior Asphalt, Inc.Byram9111%$9.9M2.9%3.5%
A J Construction, Inc.Flowood13215%$9.0M2.6%0.5%
Southern Paving, LLCFoxworth3267%$5.5M1.6%7.7%
Bluff City Construction Co LLCMemphis11100%$4.4M1.3%26.1%
Simmons Erosion Control, Inc.Lake4125%$4.0M1.2%–
RPF Emergency Services, LLCHoover11100%$3.4M1.0%3.5%
03 · Counties

County by county, last 3 years

CountyContractsAwardedBidders / contractSingle-bidLow vs. estimate
Warren9$87.0M3.8911%+3.9%
Yazoo14$65.8M3.7921%−13.6%
Holmes15$38.9M4.0713%−10.4%
Sunflower10$33.0M3.6010%−14.3%
Copiah17$30.4M4.006%−1.3%
Washington8$24.3M4.0013%−1.6%
Humphreys4$23.4M4.000%−4.6%
Jefferson7$14.4M2.8629%−1.3%
Bolivar4$9.7M3.5025%−14.7%
Sharkey4$7.8M4.000%−5.2%
Issaquena1$4.1M7.000%−8.8%
Claiborne3$3.8M3.000%−1.0%

By type of work, last 3 years

Work typeContractsAwardedBidders / contractLow vs. estimate
Overlay & resurfacing28$112M2.57−6.7%
Construction & widening17$85.5M3.82−19.4%
Bridge repair & rehab20$80.2M4.35+2.1%
Bridge replacement5$59.4M5.20−1.0%
Intersections & safety3$7.0M1.00−1.3%
Buildings & other1$576K2.00+74.5%
04 · Recent contracts

The last 15 contracts

LetContractLow bidderLow bidBiddersGap to 2ndvs. estimate
Oct 27, 2026Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 miles east of the MS Warren · Bridge repair & rehabHemphill Construction Company, Inc.$41.8M32.0%+40.4%
Sep 22, 2026Bridge Repair on SR 433 over Mound Creek (Bridge No. 11.6)Yazoo · Bridge repair & rehabGibson & Associates, Inc.$125K428.9%−15.3%
Sep 22, 2026Bridge Repair on US 82 over Bogue Phalia (Bridge No. 22.1B) & Bridge Repair on MS 438 over Bogue Phalia (BridgWashington · Bridge repair & rehabGibson & Associates, Inc.$1.8M47.9%+9.1%
Aug 25, 2026Overlay approximately 3.6 miles of MS 550 from SR 28 to the Lincoln County LineJefferson · Overlay & resurfacingDickerson & Bowen, Inc.$756K46.5%−0.2%
Aug 25, 2026Mill & Overlay approximately 0.5 miles East of US 61Washington · Overlay & resurfacingAPAC - Mississippi, Inc.$2.1M1–+9.6%
Aug 25, 2026Bridge Repair on SR 434 on Bridge No. 0.7 and Bridge Rehabilitation on SR 434 on Bridge No. 2.3Sharkey · Bridge repair & rehabKey, LLC$2.9M37.6%+9.0%
Aug 25, 2026Mill & Overlay approximately 11 miles of US 61 from 0.5 miles North of US 80/SR27 Intersection to 0.36 miles NWarren · Overlay & resurfacingAPAC - Mississippi, Inc.$12.2M315.3%+8.6%
Jul 28, 2026Bridge Repair on SR 16/SR 149 over SR 3 & Yazoo River (Bridge No. 203.3)Yazoo · Bridge repair & rehabCentury Construction Group, Inc.$6.7M58.5%−5.0%
Jul 28, 2026Bank Stabilization on SR 12 over Big Black River (Bridge No. 83.4)Holmes, Attala · Bridge repair & rehabWilco, Inc.$2.7M107.7%−20.1%
Jun 5, 2026Mill & Overlay approximately 3 miles of MS 16/149 from MS 3 to US 49Yazoo · Overlay & resurfacingAPAC - Mississippi, Inc.$2.6M1–+9.9%
May 8, 2026Scrub Seal and Overlay approximately 8 miles of SR 12 from Black Creek in Lexington to Ellington RoadHolmes · Overlay & resurfacingSouthern Paving, LLC$3.2M25.0%−1.6%
Apr 17, 2026Construction project, Bolivar & Holmes & Humphreys & Sharkey & Sunflower & Washington & Yazoo CountyBolivar, Holmes, Humphreys, Sharkey, Sunflower, Washington, Yazoo · Construction & wideningRPF Emergency Services, LLC$3.4M83.5%−19.4%
Apr 10, 2026Asphalt Overlay approximately 12 miles SR 28 from Jefferson County Line to 1 mile East of Sylvarena RoadCopiah · Overlay & resurfacingDickerson & Bowen, Inc.$3.9M64.5%−16.3%
Apr 10, 2026Pavement Restoration on US 49 from Madison County Line to 0.8 miles North of Old Highway 49Yazoo · Construction & wideningAPAC - Mississippi, Inc.$12.0M38.3%−10.3%
Feb 24, 2026Widen & Overlay approximately 10 miles of SR 149 from 0.3 Miles South of SR 14 to US 49WHumphreys · Overlay & resurfacingAPAC - Mississippi, Inc.$7.9M25.2%+1.2%
05 · Coming up

40 District 3 projects on MDOT's proposed list

LettingCountyRouteScopeDescription
November 2026BolivarUS 61Bridge Preventive MaintenanceUS 61 (Bridge # 247.7)
November 2026HolmesUS 51Bridge Preventive MaintenanceUS 51 (Bridge # 148.4)
November 2026YazooMS 3Bridge Preventive MaintenanceMS 3 (Bridge # 38.1)
November 2026YazooBuilding ConstructionConstruction of Yazoo Co. Bulk Salt Storage
November 2026WarrenBuilding ConstructionConstruction of Warren Co. Bulk Salt Storage
November 2026BolivarBuilding ConstructionConstruction of Bolivar Co. Bulk Salt Storage
November 2026WashingtonBuilding ConstructionConstruction of Washington Co. Bulk Salt Storage
November 2026HolmesBuilding ConstructionConstruction of Holmes Co. Bulk Salt Storage
December 2026DistrictwideStorm DamageDistrict 3 Emergency Maintenance Contract
January 2027SunflowerMS 3Bridge ReplacementSR 3 BTW US 82 and US 49W (95.0)
January 2027WashingtonUS 82Bridge PreservationUS 82 over MS River Bridge
January 2027ClaiborneMS 18Bridge ReplacementSR 18 Bridge Replacement (#10.4)
January 2027WarrenI 20Building Construction - Welcome CenterI-20 Commissioner Dick Hall Hospitality Station
January 2027YazooMS 3OverlayMS 3 from O'Neill Creek to Yazoo City
January 2027BolivarMS 161Ultra-thin OverlayMS 161 from Merigold to Shelby
January 2027BolivarUS 61OverlayUS 61 From End 5-Lane North of Cleveland to Jones Bayou
January 2027BolivarUS 61OverlayUS 61 from Jones Bayou to approximately 0.2 mile north of Jones Bayou
January 2027BolivarUS 61SafetyUS 61 at MS 32, West/East Mound Bayou Road, and MS 161 (South Merigold) - Installing low cost directional medians
March 2027DistrictwideBridge RepairD3 - Pile/Encasement Repair Project (9 Bridges)
March 2027WashingtonMS 12Mill & OverlaySR 12 From Hollandale to US 61
March 2027WashingtonUS 61RoundaboutUS 61 at MS 12
March 2027YazooUS 49EOverlayUS 49E From North of US 49W to Holmes County Line
April 2027JeffersonMS 28Bridge ReplacementSR 28 bridge removal over Abandoned RR (Bridge #2.4), bridge replacement over Boles Creek (Bridge #2.7), and box replacement
April 2027DistrictwideRaised Pavement MarkersDistrict Wide RPM - D3
May 2027CopiahPAT HARRISON DRIVEBridge RepairPat Harrison Drive over I-55 (Bridge # 67.6)
June 2027SunflowerMS 32Bridge ReplacementSR 32 Bridge Replacement (#29.0)
June 2027HolmesEBENEZER PICKENS ROADBridge RepairEbenezer-Pickens Road over I-55 (Bridge # 139.3)
July 2027WarrenUS 61Mill & OverlayUS 61 just north of Hullum Road to Concrete section at Pemberton intersection
July 2027JeffersonMS 552Ultra-thin OverlayMS 552 from US 61 to end of state maintenance
July 2027WarrenMS 3Mill & OverlayMS 3 from US 61 to the Yazoo County Line
July 2027SunflowerMS 448Bridge RepairMS 448 over Porters Bayou (Bridge #20.6)
July 2027YazooMS 433Ultra-thin OverlayMS 433 from US 49 to 0.85 mile north of MS 16
August 2027CopiahI 55Bridge Preventive MaintenanceI-55 over Bye Branch (Bridge #s 49.2A & 49.2B)
August 2027HumphreysMS 7Bridge Preventive MaintenanceMS 7 over Bear Creek ( Bridge # 5.2)
August 2027YazooUS 49WBridge Preventive MaintenanceUS 49W over US 49E (Bridge # 39.8)
August 2027WarrenUS 61Bridge RepairUS 61 (Bridge # 112.7)
September 2027SunflowerUS 82Bridge ReplacementUS 82 BTW US 49W and SR 3 (38.3A & 38.3B)
September 2027HumphreysMS 12Bridge RepairMS 12 over Yazoo River (Bridge # 35.5)
September 2027IssaquenaMS 1Bridge RepairMS 1 over Steele Bayou (Bridge # 4.7)
October 2027CopiahMS 28Bridge ReplacementSR 28 Bridge Replacement (#37.6)

Source: MDOT Schedule of Proposed Projects, Nov 21, 2026.

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. * 2026 through 2026-10-27.