MDOT let 3 contracts worth $24.9M at the low bid, with 3.67 bidders per contract (the 12-month average is 3.70). APAC - Mississippi, Inc. won the most, $12.0M; 3 firms won at least one contract. The closest finish: Asphalt Overlay approximately 12 miles SR 28 from Jefferson County Line to 1 mil, decided by 4.5% ($174K).
| Call | Contract | Low bidder | Low bid | Second | Gap | Bidders | vs. estimate |
|---|---|---|---|---|---|---|---|
| 1 | Pavement Restoration on US 49 from Madison County Line to 0.8 miles North of Old Highway 49Yazoo · Construction & widening · 108150304 | APAC - Mississippi, Inc.2nd: Dickerson & Bowen, Inc. | $12.0M | $13.0M | 8.3% | 3 | −10.3% |
| 2 | Mill & Overlay approximately 7 miles of US 82 from 1 mile east of Military Road to the Alabama State LinLowndes · Overlay & resurfacing · 108649301 | Falcon Contracting Company, Inc.2nd: APAC - Mississippi, Inc. | $9.1M | $9.7M | 7.0% | 2 | +9.7% |
| 3 | Asphalt Overlay approximately 12 miles SR 28 from Jefferson County Line to 1 mile East of Sylvarena RoadCopiah · Overlay & resurfacing · 109044301 | Dickerson & Bowen, Inc.2nd: APAC - Mississippi, Inc. | $3.9M | $4.0M | 4.5% | 6 | −16.3% |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew.
BidCrew tracks every DOT letting: line-item prices, competitor history, and a predicted low bid before you submit.