May 27, 2026 MDOT letting: 17 contracts, $87.4M

MDOT let 17 contracts worth $87.4M at the low bid, with 3.29 bidders per contract (the 12-month average is 3.70). APAC - Mississippi, Inc. won the most, $43.4M; 13 firms won at least one contract. The closest finish: Intersection Improvements on US 45 from Misso Road to Magnolia Drive, and Mill &, decided by 0.2% ($51K). MDOT later rejected the bids on 2 more contracts from this letting and re-let them.

Awarded at low bid
$87.4M
17 contracts
Bidders per contract
3.29
single-bid 18%
Low bid vs. estimate
−1.7%
median
Low-to-second gap
$2.3M
median 2.8%
CallContractLow bidderLow bidSecondGapBiddersvs. estimate
1Intersection Improvements on US 45 from Misso Road to Magnolia Drive, and Mill & Overlay approximately 12 miles of existNoxubee · Overlay & resurfacing · 109403301APAC - Mississippi, Inc.2nd: Falcon Contracting Company, Inc.$20.6M$20.7M0.2%2+9.6%
2Pavement Restoration of US 49 from the Hinds County Line to the Yazoo County Line, and ITS Improvements on US 49 from NoMadison, Hinds, Yazoo · Construction & widening · 105530301APAC - Mississippi, Inc.2nd: Superior Asphalt, Inc.$18.6M$18.9M1.4%4−8.9%
13Buildings project, George CountyGeorge · Buildings & other · 109467301Warren Paving, Inc.$7.0M––1+7.8%
21Widening of US 51 from Glenwild to North StreetGrenada · Construction & widening · 109767301Falcon Contracting Company, Inc.2nd: Lehman-Roberts Company$5.8M$5.9M2.0%2+9.5%
7Traffic Signal Improvements on MS 16 at Van Buren, and Mill & Overlay approximately 6 miles of MS 35 from Pleasant Hill Leake · Overlay & resurfacing · 109770302Superior Asphalt, Inc.2nd: Dickerson & Bowen, Inc.$5.4M$5.6M2.4%4+2.9%
6Overlay approximately 11.4 miles of SR 15 from Ovett-Scarbrough Road to south of Tuckers Crossing, and Overlay approximaJones · Overlay & resurfacing · 109465301Dunn Roadbuilders, LLC2nd: Walters Construction Co., Inc.$4.3M$4.5M4.2%2−10.9%
16Scrub Seal & Overlay approximately 12 miles of MS 172 from the junction of US 72 to the Junction of US 72Tishomingo · Overlay & resurfacing · 310038301WG Construction Company, Inc.2nd: APAC - Mississippi, Inc.$4.2M$4.3M1.5%2+9.5%
14Mill & Overlay 10 miles of SR 371 from the Mantachie Corp. limit to the Prentiss County LineItawamba · Overlay & resurfacing · 307877301APAC - Mississippi, Inc.2nd: WG Construction Company, Inc.$4.1M$4.1M0.3%3+1.5%
4Restricted Crossing U-Turn (RCUT) on US 84 at MS 33Franklin · Construction & widening · 109580301Midway Construction, Inc.2nd: Simmons Erosion Control, Inc.$3.8M$4.3M15.3%2−6.5%
11Bridge Replacement on SR 427 (Bridge No. 4.4) between SR 488 & SR 16Leake · Bridge replacement · 102372302Joe McGee Construction Company, Inc.2nd: Cook & Son, LLC$3.1M$3.1M0.5%8−11.9%
15Mill & Overlay approximately 7 miles of SR 4 from east of Church Street to west of the Junction with SR 371 at Hobo StatPrentiss · Overlay & resurfacing · 109758301WG Construction Company, Inc.2nd: APAC - Mississippi, Inc.$2.8M$3.2M12.2%2−1.7%
19Thin Lift Overlay of MS 16 from Thompson Drive to the Intersection of MS 15Neshoba · Overlay & resurfacing · 310197301Dickerson & Bowen, Inc.2nd: Superior Asphalt, Inc.$2.6M$2.8M8.4%5−11.5%
5Bridge Replacement on SR 15 over Cypress Branch on Bridge No. 15.7Harrison · Bridge replacement · 108392301Holliday Construction, LLC2nd: Chris Albritton Construction Company, Inc.$2.4M$2.7M13.7%5−10.0%
22Building Improvements at District 1 Shop Electrical UpgradesLee · Buildings & other · 503808301Flagstar Construction Company, Inc.$853K––1+9.0%
9Installation of Center Line Rumble Strips on MS 18 from Old Port Gibson Road to the Copiah County LineHinds · Construction & widening · 109926301Traffic Control Products Company, Inc.$748K––1+5.9%
10Bridge Repair on I-55 over Star Landing Road (Bridge Nos. 285.9A & 285.9B)DeSoto · Bridge repair & rehab · 110040301Century Construction Group, Inc.2nd: Key, LLC$609K$629K3.2%7−7.4%
12Bridge Preventive Maintenance on I-55 (Bridge Nos. 237.3A & 237.3B) over Hentz RoadPanola · Bridge repair & rehab · 108781302Century Construction Group, Inc.2nd: Talbot Brothers Contracting Co., Inc.$435K$450K3.4%5−9.3%

Bids rejected and re-let

CallContractLow bidderLow bidBiddersvs. estimateRe-let
3Widening on I-10 at MS 605 WB RampHarrison · 109879301Necaise Brothers Construction Co., Inc.$1.4M3+21.3%Jul 28, 2026
17Thin Lift Overlay approximately 10.2 miles of MS 467 from beginning of maintenance to South of EdwardsHinds · 110008301APAC - Mississippi, Inc.$4.9M3+23.6%Jul 28, 2026

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew.