MDOT let 25 contracts worth $76.7M at the low bid, with 2.60 bidders per contract (the 12-month average is 3.70). APAC - Mississippi, Inc. won the most, $25.3M; 15 firms won at least one contract. The closest finish: Overlay approximately, decided by 1.8% ($18K). MDOT later rejected the bids on 3 more contracts from this letting and re-let them.
| Call | Contract | Low bidder | Low bid | Second | Gap | Bidders | vs. estimate |
|---|---|---|---|---|---|---|---|
| 10 | Overlay approximatelyRankin · Overlay & resurfacing · 108604301 | APAC - Mississippi, Inc.2nd: Dickerson & Bowen, Inc. | $10.0M | $11.3M | 12.6% | 3 | −10.3% |
| 16 | Overlay approximatelyMadison · Overlay & resurfacing · 108231301 | APAC - Mississippi, Inc.2nd: Dickerson & Bowen, Inc. | $8.0M | $8.4M | 4.3% | 4 | −9.3% |
| 8 | Overlay approximatelyBolivar · Overlay & resurfacing · 107766301 | APAC - Mississippi, Inc. | $7.3M | – | – | 1 | +10.7% |
| 19 | Overlay project, Webster CountyWebster · Overlay & resurfacing · 307471301 | Falcon Contracting Company, Inc.2nd: Gregory Companies, LLC dba Murphree Paving | $5.7M | $5.8M | 2.0% | 4 | +11.7% |
| 7 | Safety Improvements along SRTishomingo · Intersections & safety · 106857301 | Cook & Son, LLC2nd: Century Construction Group, Inc. | $5.7M | $6.3M | 10.1% | 5 | +11.9% |
| 2 | Overlay approximatelyHinds · Overlay & resurfacing · 107950301 | W. E. Blain & Sons, Inc.2nd: Dickerson & Bowen, Inc. | $5.1M | $5.8M | 13.7% | 2 | −6.0% |
| 6 | Overlay approximatelyJefferson Davis · Overlay & resurfacing · 107526301 | W. E. Blain & Sons, Inc.2nd: Looks Great Services of MS, Inc. | $4.9M | $6.0M | 22.1% | 2 | +61.9% |
| 23 | Mill & Overlay approximately 8.5 miles on SR 32 from the end of the 4-lane section in Charleston to USTallahatchie, Yalobusha · Overlay & resurfacing · 307473301 | Lehman-Roberts Company | $4.1M | – | – | 1 | +11.2% |
| 28 | Overlay approximatelyDeSoto · Overlay & resurfacing · 108655301 | Lehman-Roberts Company2nd: APAC-Tennessee, Inc. | $3.9M | $4.5M | 14.4% | 2 | +12.1% |
| 18 | Overlay approximatelyNewton · Overlay & resurfacing · 108661301 | Dunn Roadbuilders, LLC2nd: Walters Construction Co., Inc. | $3.3M | $3.4M | 2.6% | 2 | +1.8% |
| 3 | Thin Lift Overlay approximately 10 miles on SR 35 from SR 28 to SRSmith · Overlay & resurfacing · 108367301 | W. E. Blain & Sons, Inc. | $2.7M | – | – | 1 | +10.8% |
| 1 | Intersection Improvements on USJefferson · Intersections & safety · 108425301 | G. Rayborn Contracting, LLC2nd: T. L. Wallace Construction, Inc. | $2.7M | $2.7M | 2.3% | 2 | +4.9% |
| 5 | Overlay approximately 7.5 miles on SRStone · Overlay & resurfacing · 107944301 | Warren Paving, Inc.2nd: Huey P Stockstill, LLC | $2.1M | $2.4M | 10.4% | 3 | −23.5% |
| 12 | Overlay approximatelyPearl River · Overlay & resurfacing · 108225301 | Huey P Stockstill, LLC2nd: Warren Paving, Inc. | $1.6M | $1.7M | 5.3% | 2 | −9.9% |
| 25 | Overlay approximatelyCovington · Overlay & resurfacing · 306997301 | Warren Paving, Inc.2nd: Dunn Roadbuilders, LLC | $1.5M | $1.5M | 2.8% | 3 | −14.1% |
| 11 | Widen, Level & Thin Lift Overlay approximately 5 miles on SR 589 from US 11 to 1.6 miles North of Old HighwayLamar · Overlay & resurfacing · 108227301 | Warren Paving, Inc.2nd: Huey P Stockstill, LLC | $1.3M | $1.9M | 39.5% | 2 | −5.6% |
| 15 | Construction project, Harrison CountyHarrison · Construction & widening · 108675301 | Weaver Electric, Inc.2nd: Lamey Electric, Inc. | $1.2M | $1.4M | 17.7% | 4 | +50.8% |
| 21 | Mill & Overlay approximately 2 miles on SR 389 from SR 182 to USOktibbeha · Overlay & resurfacing · 307460301 | Falcon Contracting Company, Inc.2nd: Gregory Companies, LLC dba Murphree Paving | $1.2M | $1.3M | 5.2% | 4 | −6.8% |
| 20 | Scrub Seal approximately 18 miles on SR 341 from the Calhoun County Line to SRPontotoc · Construction & widening · 306966301 | J. J. Ferguson Sand & Gravel, Inc.2nd: Kimes & Stone Construction Company, Inc. | $1.1M | $1.2M | 10.9% | 3 | +9.1% |
| 24 | Overlay approximatelyPerry · Overlay & resurfacing · 307488301 | Warren Paving, Inc.2nd: Dunn Roadbuilders, LLC | $1.1M | $1.1M | 3.4% | 2 | −1.0% |
| 27 | Overlay approximatelyPike · Overlay & resurfacing · 307443301 | Dickerson & Bowen, Inc.2nd: Barriere Construction Company, LLC | $980K | $998K | 1.8% | 2 | −4.6% |
| 26 | Overlay approximately 2 miles on US 51 from Louisiana State Line to SRPike · Overlay & resurfacing · 307442301 | Dickerson & Bowen, Inc.2nd: Barriere Construction Company, LLC | $684K | $817K | 19.5% | 2 | −7.1% |
| 13 | Bridge Joint Repairs on US 51, (Bridge Nos.Grenada, Yalobusha · Bridge repair & rehab · 108620302 | Sunbelt Sealing, Inc.2nd: A-1 Sealing, Inc. | $189K | $231K | 22.4% | 4 | −36.1% |
| 9 | Construction project, Madison CountyMadison · Construction & widening · 108616301 | Key, LLC2nd: Gibson & Associates, Inc. | $154K | $159K | 3.3% | 2 | −35.8% |
| 14 | Construction project, Madison CountyMadison · Construction & widening · 107998301 | Simmons Erosion Control, Inc.2nd: Key, LLC | $127K | $154K | 21.0% | 3 | −23.6% |
| Call | Contract | Low bidder | Low bid | Bidders | vs. estimate | Re-let |
|---|---|---|---|---|---|---|
| 4 | Overlay approximatelyLauderdale · 108605301 | APAC - Mississippi, Inc. | $4.4M | 1 | +20.5% | Sep 28, 2021 |
| 17 | Overlay approximatelyIssaquena · 108211301 | APAC - Mississippi, Inc. | $6.0M | 1 | +19.2% | Sep 28, 2021 |
| 22 | Overlay approximatelyHumphreys · 307475301 | APAC - Mississippi, Inc. | $3.0M | 1 | +19.1% | Sep 28, 2021 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew.
BidCrew tracks every DOT letting: line-item prices, competitor history, and a predicted low bid before you submit.