November 2, 2023 MDOT letting: 1 contract, $57.8M

MDOT let 1 contract worth $57.8M at the low bid, with 2.00 bidders per contract (the 12-month average is 3.70). T. L. Wallace Construction, Inc. won the most, $57.8M. MDOT later rejected the bids on 1 more contract from this letting and re-let it.

Awarded at low bid
$57.8M
1 contracts
Bidders per contract
2.00
single-bid 0%
Low bid vs. estimate
+15.7%
median
Low-to-second gap
$12.9M
median 22.3%
CallContractLow bidderLow bidSecondGapBiddersvs. estimate
7Bridge Replacements & Bank Stabilization on US 98 at the Pearl River (Bridge Nos. 118.5A & 118.5B), known as Federal AidMarion · Bridge replacement · 102445301T. L. Wallace Construction, Inc.2nd: W. G. Yates & Sons Construction Company$57.8M$70.6M22.3%2+15.7%

Bids rejected and re-let

CallContractLow bidderLow bidBiddersvs. estimateRe-let
5Interchange Reconstruction on I-10 at Diamondhead, known as Federal Aid Project No. NHPP-0010-01(161) / 107509301 in HanHancock · 107509301Huey P Stockstill, LLC$18.0M2+42.1%Jan 24, 2024

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew.