MDOT let 8 contracts worth $54.1M at the low bid, with 2.75 bidders per contract (the 12-month average is 3.70). Key, LLC won the most, $25.7M; 6 firms won at least one contract. The closest finish: Construction project, Bolivar County, decided by 0.6% ($2K).
| Call | Contract | Low bidder | Low bid | Second | Gap | Bidders | vs. estimate |
|---|---|---|---|---|---|---|---|
| 3 | Bridge Replacements on USFranklin · Bridge replacement · 100888301 | Key, LLC2nd: Cotton Creek Transport, Inc. | $25.7M | $32.1M | 24.6% | 2 | +7.0% |
| 2 | Overlay approximatelySimpson · Overlay & resurfacing · 108245301 | APAC - Mississippi, Inc.2nd: Dickerson & Bowen, Inc. | $11.4M | $13.0M | 13.8% | 4 | −20.4% |
| 4 | Mill & Overlay approximately 11 miles of SR 27 from the Copiah County Line to SRHinds · Overlay & resurfacing · 108725301 | APAC - Mississippi, Inc.2nd: Dickerson & Bowen, Inc. | $4.7M | $5.2M | 12.0% | 4 | −20.4% |
| 6 | Overlay approximatelyAmite · Overlay & resurfacing · 109367301 | Dickerson & Bowen, Inc.2nd: APAC - Mississippi, Inc. | $4.3M | $5.5M | 29.2% | 2 | −9.8% |
| 9 | Overlay approximatelyWilkinson · Overlay & resurfacing · 109248301 | APAC - Mississippi, Inc. | $3.0M | – | – | 1 | +6.0% |
| 5 | Construction project, Harrison CountyHarrison · Construction & widening · 108824301 | JLB Contractors, LLC2nd: Colony Construction, LLC | $2.3M | $2.4M | 2.6% | 2 | −30.4% |
| 7 | Intersection Improvements on USMadison · Intersections & safety · 108504301 | Hemphill Construction Company, Inc.2nd: Joe McGee Construction Company, Inc. | $2.2M | $3.3M | 46.7% | 3 | −20.1% |
| 8 | Construction project, Bolivar CountyBolivar · Construction & widening · 108777303 | Century Construction Group, Inc.2nd: Talbot Brothers Contracting Co., Inc. | $410K | $412K | 0.6% | 4 | −44.8% |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew.