MDOT let 17 contracts worth $15.9M at the low bid, with 2.35 bidders per contract (the 12-month average is 3.70). APAC - Mississippi, Inc. won the most, $7.3M; 6 firms won at least one contract. The closest finish: Overlay approximately, decided by 1.5% ($31K). MDOT later rejected the bids on 1 more contract from this letting and re-let it.
| Call | Contract | Low bidder | Low bid | Second | Gap | Bidders | vs. estimate |
|---|---|---|---|---|---|---|---|
| 1 | Overlay approximatelyWashington · Overlay & resurfacing · 107723301 | APAC - Mississippi, Inc. | $3.5M | – | – | 1 | +14.5% |
| 5 | Overlay approximatelyCarroll · Overlay & resurfacing · 306960301 | APAC - Mississippi, Inc.2nd: Lehman-Roberts Company | $2.1M | $2.1M | 1.5% | 2 | −4.1% |
| 4 | Overlay approximatelyMonroe · Overlay & resurfacing · 306954301 | APAC - Mississippi, Inc.2nd: Falcon Contracting Company, Inc. | $1.7M | $1.9M | 6.2% | 3 | −4.3% |
| 12 | Overlay approximately 8 miles of SR 584 from Junction SRAmite · Overlay & resurfacing · 307072301 | Dickerson & Bowen, Inc.2nd: W. E. Blain & Sons, Inc. | $1.4M | $1.6M | 14.5% | 3 | −21.0% |
| 6 | Overlay approximately 6.1 miles of SRClaiborne · Overlay & resurfacing · 306959301 | W. E. Blain & Sons, Inc.2nd: Dickerson & Bowen, Inc. | $1.2M | $1.3M | 4.2% | 3 | −5.3% |
| 7 | Mill & Overlay approximately 1.Scott · Overlay & resurfacing · 306934301 | W. E. Blain & Sons, Inc.2nd: Dickerson & Bowen, Inc. | $1.2M | $1.2M | 4.6% | 2 | +13.7% |
| 11 | Scrub Seal & Mill & Overlay approximately 3 miles of SR 184 from Junction USLawrence · Overlay & resurfacing · 307071301 | Dickerson & Bowen, Inc.2nd: W. E. Blain & Sons, Inc. | $1.1M | $1.2M | 6.5% | 2 | +6.8% |
| 14 | Construction projectDistrict 2 · Construction & widening · 307196301 | Highway Safety Systems, L.L.C.2nd: Simmons Erosion Control, Inc. | $533K | $575K | 7.8% | 2 | −9.3% |
| 8 | Overlay approximatelyLeake · Overlay & resurfacing · 307046301 | Dickerson & Bowen, Inc.2nd: APAC - Mississippi, Inc. | $505K | $676K | 33.8% | 2 | −21.4% |
| 10 | Construction projectDistrict 7 · Construction & widening · 307120301 | J. L. McCool Contractors, Inc.2nd: Traffic Control Products Company, Inc. | $494K | $593K | 20.1% | 3 | +27.8% |
| 3 | Bridge Joint Repairs on I-10, SR 63, and USJackson · Bridge repair & rehab · 108403301 | Sunbelt Sealing, Inc.2nd: Olympus Painting Contractors, Inc. | $473K | $919K | 94.2% | 2 | −4.6% |
| 13 | Construction projectDistrict 1 · Construction & widening · 307195301 | Highway Safety Systems, L.L.C.2nd: Simmons Erosion Control, Inc. | $439K | $499K | 13.7% | 2 | −22.1% |
| 16 | Construction projectDistrict 5 · Construction & widening · 307198301 | Highway Safety Systems, L.L.C.2nd: Simmons Erosion Control, Inc. | $419K | $458K | 9.1% | 2 | −14.9% |
| 9 | Mill & Overlay approximately 0.5 miles of SR 492 from Decatur Street to SRNewton · Overlay & resurfacing · 307087301 | W. E. Blain & Sons, Inc.2nd: Dickerson & Bowen, Inc. | $289K | $308K | 6.5% | 3 | +7.0% |
| 17 | Construction projectDistrict 6 · Construction & widening · 307199301 | Highway Safety Systems, L.L.C.2nd: Simmons Erosion Control, Inc. | $230K | $276K | 19.7% | 3 | −29.1% |
| 15 | Construction projectDistrict 3 · Construction & widening · 307197301 | Highway Safety Systems, L.L.C.2nd: Simmons Erosion Control, Inc. | $180K | $203K | 13.1% | 2 | −32.9% |
| 18 | Construction projectDistrict 7 · Construction & widening · 307200301 | Highway Safety Systems, L.L.C.2nd: Simmons Erosion Control, Inc. | $127K | $171K | 34.7% | 3 | – |
| Call | Contract | Low bidder | Low bid | Bidders | vs. estimate | Re-let |
|---|---|---|---|---|---|---|
| 2 | Overlay approximately 7 miles of SR 492 from the Newton County Line to SR 19 and approximately 1 mile of SR 492 from theNeshoba, Newton · 106114302 | Dickerson & Bowen, Inc. | $2.4M | 3 | +5.1% | Jan 26, 2021 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew.