No contract priced this item in the last 12 months.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Jul 23, 2024 | Overlay approximatelyLamar | 8 MI | $8,180 | $8,290 | 2 |
| Jul 23, 2024 | Overlay approximatelyMontgomery | 5 MI | $7,075 | – | 1 |
| May 29, 2024 | Overlay approximatelyLauderdale | 2 MI | $7,560 | $7,280 | 2 |
| Mar 26, 2024 | Pavement Restoration of approximately 5 miles of I-55 from SR 24 to US 98 & Roundabout ConPike | 12 MI | $10,375 | $9,688 | 2 |
| Jan 24, 2024 | Overlay approximatelyFranklin | 10 MI | $7,100 | – | 1 |
| Jan 24, 2024 | Construction project, Jackson CountyJackson | 17 MI | $8,352 | $8,076 | 2 |
| Jan 24, 2024 | Overlay approximatelyCoahoma | 27 MI | $7,600 | – | 1 |
| Dec 5, 2023 | Widening of I-10 from Diamondhead to County Farm Road, Installation of ITS Components fromHancock, Harrison | 28 MI | $9,050 | – | 1 |
| Dec 5, 2023 | Add 2 Lanes on US 49 from O'Neal Road to north of School Road, known as Federal Aid ProjecHarrison | 5 MI | $8,991 | $8,545 | 2 |
| Nov 28, 2023 | Overlay approximatelyCovington | 14 MI | $6,400 | – | 1 |
| Oct 24, 2023 | Construction project, Wayne CountyWayne | 1 MI | $7,503 | $7,485 | 3 |
| May 23, 2023 | Mill & Overlay approximately 6 miles of US 49 from Myers Creek to USForrest | 10 MI | $7,865 | – | 1 |
| Apr 25, 2023 | Overlay approximatelyAdams | 11 MI | $8,300 | – | 1 |
| Apr 25, 2023 | Construction project, Wilkinson CountyWilkinson | 1 MI | $7,000 | $14,500 | 3 |
| Feb 28, 2023 | Overlay approximatelyPearl River | 32 MI | $7,200 | – | 1 |
| Jan 25, 2023 | Overlay approximatelyForrest | 2 MI | $6,740 | $6,740 | 3 |
| Nov 22, 2022 | Overlay approximatelyTate | 27 MI | $7,900 | – | 1 |
| Nov 22, 2022 | Overlay approximatelyWayne | 13 MI | $5,885 | $6,100 | 3 |
| Oct 25, 2022 | Grade, Drain, Bridge & Pave 4-Lane approximately 9 miles of SR 57 from I-10 to Vancleave, Jackson | 16 MI | $9,800 | $11,028 | 2 |
| Jul 27, 2022 | Safety Improvements on approximatelyPrentiss | 22 MI | $6,300 | – | 1 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.