BidCrew Data
BidCrew Data / Mississippi / Prices / 6" High Performance Cold Plastic Traffic Stripe, Continuous Yellow
MDOT pay item · 628-J001

6" High Performance Cold Plastic Traffic Stripe, Continuous Yellow: Mississippi winning bid prices

No contract priced this item in the last 12 months.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
–
Median, prior 12 months
–
Median, 2020
$7.50
25 contracts
Winner vs. field
level with
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$7$8$9$102020202120222023202420252026*$9.50
Price vs. quantityEvery winning price since 2020 (log scale)
$4$6$8$10$121001.0K10K
Does quantity matter?Median winning price by quantity band
$0$2$4$6$8$8.00≤565$8.00565–1.6K$8.001.6K–4.0K$8.00>4.0K

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
May 29, 2024Thin Lift Overlay on approximately 9 miles of SR 63 from Clara to SR 184 & approximately 2Wayne1.2K LF$9.00$9.202
May 29, 2024Overlay approximatelyGeorge610 LF$8.75$8.382
Apr 23, 2024Grade, Drain, Pave on SR 2 from existing SR 15 to SRTippah3.9K LF$12.00$12.532
Jan 24, 2024Interchange Reconstruction on I-10 at Diamondhead, known as Federal Aid Project No. NHPP-0Hancock732 LF$9.50$9.203
Jan 24, 2024Mill & Overlay approximately 3 miles of US 45 from Ripley Road to SRPrentiss566 LF$10.00$10.004
Dec 5, 2023Bridge Replacement on US 11 at Hobolochitto Creek in Picayune (Bridge No. 11.3), known as Pearl River2.9K LF$8.00$9.455
Dec 5, 2023Widening of I-10 from Diamondhead to County Farm Road, Installation of ITS Components fromHancock, Harrison4.3K LF$9.00–1
Nov 28, 2023Overlay approximatelyChickasaw5.9K LF$7.75$8.003
Nov 28, 2023Construction project, Jones CountyJones320 LF$12.00$12.004
Nov 28, 2023Overlay approximately 10.5 miles on USPrentiss5.7K LF$9.00$9.004
Jul 25, 2023Overlay approximatelyPearl River934 LF$10.00–1
Jun 27, 2023Construction projectDistrict 6560 LF$6.00$7.002
Jun 27, 2023Safety Improvements on approximatelyLowndes17K LF$10.00$10.002
May 23, 2023Mill & Overlay approximately 6 miles of US 49 from Myers Creek to USForrest12K LF$7.00–1
May 23, 2023Overlay approximatelyJasper182 LF$12.00–1
Apr 25, 2023Overlay approximatelyCalhoun300 LF$7.00$7.003
Feb 28, 2023Overlay approximatelyLamar161 LF$8.85–1
Feb 28, 2023Overlay approximatelyPearl River11K LF$9.00–1
Feb 28, 2023Bridge Replacement on SRMadison386 LF$11.00$10.505
Jan 25, 2023Overlay approximatelyMonroe530 LF$8.00$8.252

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.

Price this item against every competitor

BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.

Request access