BidCrew Data / Mississippi / Prices / 9.5-mm, MT, Asphalt Pavement, Leveling
MDOT pay item · 403-B011 / 907-403-B011

9.5-mm, MT, Asphalt Pavement, Leveling: Mississippi winning bid prices

The low bidder priced 9.5-mm, mt, asphalt pavement, leveling at a median $127 per ton over the last 12 months (4 contracts), down 27% from the year before and up 34% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$127
4 contracts
Median, prior 12 months
$175
7 contracts
Median, 2020
$95.00
4 contracts
Winner vs. field
5% below
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$50$100$150$200$250$3002020202120222023202420252026*$116
Price vs. quantityEvery winning price since 2020 (log scale)
$0$100$200$300$4001001.0K10K
Does quantity matter?Median winning price by quantity band
$0$50$100$150$200$152≤801$149801–1.9K$1461.9K–3.8K$115>3.8K

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
May 27, 2026Widening of US 51 from Glenwild to North StreetGrenada325 TON$160$1552
May 8, 2026Level & Overlay approximately 8.4 miles on SR 18 from Smith County Line to east of Bay SprJasper2.2K TON$116$1703
Mar 24, 2026Mill & Overlay approximately 4.2 miles of US 84 from Bude to the Homochitto River BridgeFranklin3.3K TON$110$1403
Oct 28, 2025Overlay approximately 6 miles on SR 28 from Mize to Taylorsville, known as Project No. SP-Smith836 TON$138$1874
Aug 26, 2025Mill & Overlay approximately 19.5 miles of US 49W from Ruleville to the Coahoma County LinSunflower3.0K TON$175$1853
Jun 24, 2025Seal & Overlay approximately 4.8 miles of US 82 from West Greensboro Street to West of HenMontgomery1.0K TON$149$1542
May 28, 2025Overlay approximately 8 miles of US 84 from Chambers Road to Middle Fork CreekFranklin4.8K TON$115$1162
Apr 30, 2025Scrub Seal & Micro-Surfacing approximately 1.6 miles of SR 305 from End No Access (Golf CoDeSoto25 TON$300$3292
Jan 28, 2025Bridge Repairs on SR 149 over Broad Lake (Bridge No. 206.4) & on US 49W over the Yazoo RivYazoo27 TON$440$4504
Dec 5, 2024Overlay approximately 3 miles of US 61 from the end of the 4-Lane Section to SR 547Claiborne2.0K TON$160$1582
Dec 5, 2024Overlay approximately 6 miles of US 61 from Washington to the Jefferson County LineAdams1.7K TON$175–1
Sep 4, 2024Construction project, Jones CountyJones5.8K TON$126$1263
Jan 24, 2024Overlay approximatelyFranklin1.4K TON$172–1
Jun 27, 2023Overlay approximatelySmith450 TON$127$1352
Apr 25, 2023Overlay approximatelyAdams2.4K TON$178–1
Mar 28, 2023Overlay approximately 3.4 miles of SRWashington9.0K TON$175–1
Nov 22, 2022Overlay approximatelyMarshall1.1K TON$175$1852
Sep 28, 2022Overlay approximatelyGrenada5.1K TON$160–1
May 24, 2022Overlay approximately 5 miles of US 98 from Industrial Park Rd. east to Old Hwy.Walthall1.0K TON$145–1
May 24, 20229 ) / 107958303 Coahoma Mill & Overlay approximately 12 miles on US 61/49 from 0.Coahoma12K TON$132–1

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.