MDOT pay item · 406-A002

Cold Milling of Bituminous Pavement, All Depths: Mississippi winning bid prices

The low bidder priced cold milling of bituminous pavement, all depths at a median $5.50 per square yard over the last 12 months (7 contracts), down 8% from the year before and up 10% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$5.50
7 contracts
Median, prior 12 months
$6.00
16 contracts
Median, 2020
$5.00
19 contracts
Winner vs. field
level with
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$0$5$10$15$202020202120222023202420252026*$5.50
Price vs. quantityEvery winning price since 2020 (log scale)
$0$10$20$30$40$501.0K10K100K
Does quantity matter?Median winning price by quantity band
$0$5$10$15$15.00≤1.9K$10.001.9K–5.5K$5.005.5K–15K$3.45>15K

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Sep 22, 2026Remove OGFC & Replace with Micro-Surface on I-55 for approximately 14.1 miles from approxiDeSoto, Tate400 SY$1.14$26.073
Jun 30, 2026Thin Lift Overlay approximately 10.1 miles of MS 35 from 4 Forks to the Grenada County LinCarroll2.1K SY$17.55$17.553
May 27, 2026Overlay approximately 11.4 miles of SR 15 from Ovett-Scarbrough Road to south of Tuckers CJones8.2K SY$3.00$2.752
May 27, 2026Bridge Replacement on SR 15 over Cypress Branch on Bridge No. 15.7Harrison1.4K SY$5.50$5.905
Apr 28, 2026Overlay approximately 14.5 miles on US 98 from 1.05 miles east of SR 29 to the Greene CounPerry16K SY$3.45$3.252
Mar 24, 2026Seal & Overlay approximately 12.1 miles of US 61 from the Tunica Agriculture Center to theTunica3.4K SY$19.00$17.002
Feb 24, 2026Mill & Overlay approximately 4.2 miles of SR 311 from Landfill Road to Liles Road and apprMarshall2.3K SY$24.15$10.054
Jul 22, 2025Mill & Overlay approximately 3 miles on US 45A from the beginning of the 5-Lane section toClay50K SY$4.96$4.482
Jun 24, 2025Overlay approximately 9.8 miles on SR 18 from Tallahala Creek Bridge to Intersection of SRJasper10K SY$3.00$3.003
Jun 24, 2025Seal & Overlay approximately 4.8 miles of US 82 from West Greensboro Street to West of HenMontgomery19K SY$3.15$2.952
May 28, 2025Mill & Overlay approximately 4 miles of SR 485 from SR 15 to SR 21Neshoba2.8K SY$2.50$15.154
May 28, 2025Overlay approximately 7 miles of SR 15 from the intersection SR 67 North, known as FederalHarrison13K SY$4.65$9.822
May 28, 2025Overlay approximately 8 miles of US 84 from Chambers Road to Middle Fork CreekFranklin4.6K SY$7.00$9.632
Mar 25, 2025Mill & Overlay approximately 7 miles of I-20 from 5.1 miles east of SR 15 to 2.3 miles easNewton6.9K SY$8.15–1
Mar 25, 2025Bridge Repair on SR 149 over Unnamed Stream (Bridge No. 108.1)Covington640 SY$25.00$54.503
Mar 25, 2025Bridge Repair on SR 149 over Unnamed Stream (Bridge No. 108.1)Covington128 SY$25.00$1753
Feb 25, 2025Mill & Overlay approximately 8 miles of US 98 from the end of the 5-Lane to the Bogue ChitPike1.4K SY$44.00–1
Feb 25, 2025Remove & Replace approximately 17 miles of OGFC on I-10 from the Pearl River Bridge to wesHancock566K SY$3.00–1
Dec 5, 2024Mill & Overlay approximately 6 miles of SR 5 from 0.1 miles north of Shop to US 72Benton2.5K SY$9.00$11.005
Dec 5, 2024Overlay approximately 7 miles of SR 15 from the Stone County Line south 7.4 miles, known aHarrison, Stone7.0K SY$5.00$5.422

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.