The low bidder priced asphalt for tack coat at a median $4.15 per gallon over the last 12 months (95 contracts), up 4% from the year before and up 26% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Overlay approximately 7 miles of MS 48 from SR 24 to Magnolia Progress RoadPike | 13K GAL | $3.90 | $3.90 | 3 |
| Oct 27, 2026 | OGFC Lift on I-59 from US 45 to approximately 0.248 miles north of the Russell InterchangeLauderdale | 4.8K GAL | $3.25 | – | 1 |
| Oct 27, 2026 | Fog Seal approximately 6.2 miles of I-59 from 0.8 mile north of CR 39 to the Jasper/ClarkeJasper, Clarke | 152 GAL | $4.29 | $5.39 | 2 |
| Oct 27, 2026 | Fog Seal approximately 5 miles of I-59 from the Forrest County Line to the Forrest County Lamar, Forrest | 402 GAL | $4.35 | – | 1 |
| Oct 27, 2026 | Mill & Overlay approximately 13.7 miles of I-59 from 0.5 miles north of the McNeil Exit toPearl River | 32K GAL | $8.00 | – | 1 |
| Oct 27, 2026 | Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery | 36K GAL | $4.00 | – | 1 |
| Oct 27, 2026 | Construction project, Madison CountyMadison | 143K GAL | $4.45 | $4.50 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 38K GAL | $3.85 | $4.00 | 3 |
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 8.3K GAL | $4.00 | $4.70 | 4 |
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 2.4K GAL | $4.13 | – | 1 |
| Oct 27, 2026 | Mill & Overlay approximately 17 miles of I-22 beginning 1 mile west of the Landfill Road EMarshall | 83K GAL | $3.50 | $3.88 | 4 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 35K GAL | $5.50 | $5.27 | 6 |
| Sep 22, 2026 | Mill & Overlay approximately 2.5 miles of US 49 from SR 1 to the Isle of Capri ParkwayCoahoma | 4.3K GAL | $4.00 | – | 1 |
| Sep 22, 2026 | Remove OGFC & Replace with Micro-Surface on I-55 for approximately 14.1 miles from approxiDeSoto, Tate | 789 GAL | $4.73 | $8.74 | 3 |
| Sep 22, 2026 | Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha | 36K GAL | $4.26 | – | 4 |
| Sep 22, 2026 | Bridge Repair on US 82 over Bogue Phalia (Bridge No. 22.1B) & Bridge Repair on MS 438 overWashington | 40 GAL | $11.00 | $13.00 | 4 |
| Sep 22, 2026 | Bridge Repair on US 45 over Norfolk Southern Railroad (Bridge Nos. 275.6A & 275.6B)Alcorn | 95 GAL | $6.50 | $10.00 | 7 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 1.3K GAL | $5.70 | $5.70 | 3 |
| Sep 1, 2026 | Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie | 4.3K GAL | $4.19 | $4.32 | 6 |
| Aug 25, 2026 | Overlay approximately 3.6 miles of MS 550 from SR 28 to the Lincoln County LineJefferson | 4.5K GAL | $4.85 | $4.60 | 4 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.