The low bidder priced saw cut, full depth at a median $8.38 per linear foot over the last 12 months (80 contracts), up 1% from the year before and down 33% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Overlay approximately 7 miles of MS 48 from SR 24 to Magnolia Progress RoadPike | 583 LF | $11.62 | $11.00 | 3 |
| Oct 27, 2026 | OGFC Lift on I-59 from US 45 to approximately 0.248 miles north of the Russell InterchangeLauderdale | 1.7K LF | $20.00 | – | 1 |
| Oct 27, 2026 | Fog Seal approximately 6.2 miles of I-59 from 0.8 mile north of CR 39 to the Jasper/ClarkeJasper, Clarke | 11K LF | $5.77 | $7.99 | 2 |
| Oct 27, 2026 | Fog Seal approximately 5 miles of I-59 from the Forrest County Line to the Forrest County Lamar, Forrest | 1.4K LF | $10.80 | – | 1 |
| Oct 27, 2026 | Mill & Overlay approximately 13.7 miles of I-59 from 0.5 miles north of the McNeil Exit toPearl River | 16K LF | $10.00 | – | 1 |
| Oct 27, 2026 | Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery | 2.7K LF | $13.25 | – | 1 |
| Oct 27, 2026 | Construction project, Madison CountyMadison | 41K LF | $7.45 | $7.50 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 29K LF | $10.25 | $10.00 | 3 |
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 402 LF | $8.50 | $12.28 | 4 |
| Oct 27, 2026 | Mill & Overlay approximately 17 miles of I-22 beginning 1 mile west of the Landfill Road EMarshall | 7.8K LF | $9.60 | $8.75 | 4 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 38K LF | $8.00 | $8.72 | 6 |
| Sep 22, 2026 | Bridge Repair on SR 532 over Stream (Bridge No. 13.5)Covington | 250 LF | $48.45 | $49.23 | 6 |
| Sep 22, 2026 | Remove OGFC & Replace with Micro-Surface on I-55 for approximately 14.1 miles from approxiDeSoto, Tate | 2.0K LF | $9.45 | $9.68 | 3 |
| Sep 22, 2026 | Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha | 2.1K LF | $12.00 | – | 4 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 329 LF | $19.00 | $24.00 | 3 |
| Sep 1, 2026 | Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie | 1.1K LF | $10.00 | $11.75 | 6 |
| Aug 25, 2026 | Overlay approximately 3.6 miles of MS 550 from SR 28 to the Lincoln County LineJefferson | 357 LF | $1.00 | $9.25 | 4 |
| Aug 25, 2026 | Mill & Overlay approximately 0.5 miles East of US 61Washington | 378 LF | $27.00 | – | 1 |
| Aug 25, 2026 | Bridge Repair on SR 434 on Bridge No. 0.7 and Bridge Rehabilitation on SR 434 on Bridge NoSharkey | 48 LF | $56.00 | $50.00 | 3 |
| Aug 25, 2026 | Mill & Overlay approximately 11 miles of US 61 from 0.5 miles North of US 80/SR27 IntersecWarren | 2.8K LF | $14.84 | $14.84 | 3 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.