No contract priced this item in the last 12 months.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| May 29, 2024 | Overlay approximately 5 miles of SR 370 from 0.1 mile east of Dumas to SRTippah, Union | 11 MI | $8,000 | $8,000 | 4 |
| Jan 24, 2024 | Mill & Overlay approximately 3 miles of US 45 from Ripley Road to SRPrentiss | 5 MI | $7,000 | $7,000 | 4 |
| Nov 28, 2023 | Overlay approximately 10.5 miles on USPrentiss | 21 MI | $7,000 | $7,000 | 4 |
| Jul 25, 2023 | Overlay approximatelyTippah | 18 MI | $7,100 | $7,100 | 2 |
| May 23, 2023 | Overlay approximatelyTishomingo | 15 MI | $6,900 | $6,900 | 2 |
| Jul 27, 2022 | Mill & Overlay approximately 10 miles of SR 4 from the Prentiss County Line to SRTishomingo | 15 MI | $6,300 | $6,300 | 2 |
| May 24, 2022 | / 3 07770301 Prentiss & Lee Mill & Overlay 11 miles of SR 145 from 1.Lee | 24 MI | $5,800 | – | 1 |
| Mar 22, 2022 | Overlay approximatelyTippah | 8 MI | $6,000 | $6,000 | 2 |
| Jan 25, 2022 | Overlay approximately 12.5 miles on SRMonroe | 27 MI | $5,000 | $5,000 | 3 |
| Nov 23, 2021 | Overlay approximately 7.5 miles on USAlcorn | 13 MI | $5,000 | – | 1 |
| Jun 22, 2021 | Mill & Overlay approximately 2 miles on SR 389 from SR 182 to USOktibbeha | 2 MI | $4,800 | $4,800 | 4 |
| Apr 27, 2021 | Overlay approximatelyLawrence | 1 MI | $4,500 | $4,500 | 2 |
| Mar 23, 2021 | Overlay approximatelyPontotoc | 16 MI | $4,500 | $4,500 | 2 |
| Mar 23, 2021 | Overlay approximatelyAlcorn | 16 MI | $4,500 | $4,500 | 2 |
| Jan 26, 2021 | Overlay approximatelyPontotoc | 11 MI | $4,500 | $4,500 | 3 |
| Sep 22, 2020 | Overlay approximatelyLee | 29 MI | $4,400 | $4,400 | 3 |
| Aug 25, 2020 | Overlay approximatelyPontotoc | 13 MI | $4,910 | $4,500 | 4 |
| Aug 25, 2020 | Overlay approximatelyTishomingo | 19 MI | $4,500 | $4,500 | 3 |
| Mar 24, 2020 | Mill & Overlay approximately 23 miles of USLee | 42 MI | $3,800 | – | 1 |
| Jan 28, 2020 | Overlay approximatelyPanola | 18 MI | $3,800 | – | 1 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.