The low bidder priced 6" thermoplastic double drop traffic stripe, skip yellow at a median $2,500 per mile over the last 12 months (3 contracts), down 47% from the year before and down 47% since 2024.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 28, 2025 | Overlay approximately 6 miles on SR 28 from Mize to Taylorsville, known as Project No. SP-Smith | 3 MI | $4,500 | $4,500 | 4 |
| Oct 28, 2025 | Placement of Audible Stripe on MS 433 from Yazoo County Line to Ebenezer-Coxburg Road in BHolmes, Yazoo | 8 MI | $2,500 | – | 1 |
| Oct 28, 2025 | Audible Thermoplastic Pavement Markings, Thermoplastic Pavement Markings & Raised PavementChoctaw, Lowndes | 5 MI | $2,500 | – | 1 |
| Sep 23, 2025 | Mill & Overlay approximately 1.1 miles of MS 370 from US 45 to MS 145Lee | 3 MI | $5,000 | $5,000 | 3 |
| Sep 23, 2025 | Thin Lift approximately 2.3 miles of SR 555 from the end of the 4-Lane section to the end Adams | 1 MI | $6,500 | $8,250 | 2 |
| Sep 23, 2025 | Scrub Seal & Overlay approximately 6 miles of SR 27 from I-55 to the Hinds County LineCopiah | 2 MI | $6,000 | $6,000 | 4 |
| Aug 26, 2025 | Mill & Overlay approximately 4 miles of SR 302 from 0.25 mile west of Malone Road to 0.06 DeSoto | 17 MI | $5,000 | $5,084 | 2 |
| Aug 26, 2025 | Overlay approximately 8 miles of US 51 from Osyka to MagnoliaPike | 6 MI | $4,800 | $4,900 | 2 |
| Aug 26, 2025 | Overlay approximately 4.6 miles of SR 552 from the beginning of State Maintenance to SR 28Jefferson | 2 MI | $6,000 | $6,000 | 3 |
| Aug 26, 2025 | Mill & Overlay approximately 19.5 miles of US 49W from Ruleville to the Coahoma County LinSunflower | 19 MI | $3,800 | $3,800 | 3 |
| Aug 26, 2025 | Overlay approximately 6 miles of SR 35 from SR 18 to SR 481Smith | 2 MI | $5,000 | $5,000 | 5 |
| Jul 22, 2025 | Mill & Overlay approximately 8 miles on US 49 east from US 82 to 300 north of SR 442Leflore | 8 MI | $3,800 | $3,800 | 2 |
| Jul 22, 2025 | Mill & Overlay approximately 8 miles of US 49 East from 0.2 mile north of the SR 12 IntersHolmes | 7 MI | $3,800 | – | 1 |
| Jul 22, 2025 | Thin Lift & Overlay approximately 16 miles of SR 43 from just south of Wheats Curve to thePearl River | 9 MI | $3,500 | $3,750 | 2 |
| Jun 26, 2025 | Bridge Replacements on US 80 between Chunky & Meehan (Bridge Nos. 123.1, 123.3, 123.5 & 12Lauderdale, Madison, Newton | 2 MI | $7,500 | $8,665 | 3 |
| May 28, 2025 | Overlay approximately 3.3 miles of SR 42 from Simpson County Line to New HebronLawrence | 1 MI | $4,700 | $4,700 | 3 |
| May 28, 2025 | Overlay approximately 17.7 miles of SR 450 from SR 1 to US 61Bolivar | 17 MI | $3,950 | – | 1 |
| May 28, 2025 | Mill & Overlay approximately 3 miles of SR 178 from North Access Road to Old SR 25Itawamba | 2 MI | $4,500 | $4,500 | 4 |
| May 28, 2025 | Overlay approximately 7 miles of SR 15 from the intersection SR 67 North, known as FederalHarrison | 6 MI | $4,500 | $4,500 | 2 |
| Apr 30, 2025 | Scrub Seal & Micro-Surfacing approximately 1.6 miles of SR 305 from End No Access (Golf CoDeSoto | 3 MI | $5,350 | $5,649 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.