Thermoplastic Double Drop Legend, White: Mississippi winning bid prices

The low bidder priced thermoplastic double drop legend, white at a median $12.50 per square foot over the last 12 months (5 contracts), down 3% from the year before and up 4% since 2024.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$12.50
5 contracts
Median, prior 12 months
$12.95
37 contracts
Median, 2024
$12.00
15 contracts
Winner vs. field
level with
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$10$12.5$15$17.5$202020202120222023202420252026*$12.35
Price vs. quantityEvery winning price since 2020 (log scale)
$0$10$20$30$40$50$60101001.0K10K
Does quantity matter?Median winning price by quantity band
$0$5$10$15$20$19.00≤141$12.00141–586$15.45586–1.7K$12.00>1.7K

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Sep 22, 2026Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha582 SF$8.00–4
Apr 28, 2026I-10 Jackson County Welcome CenterJackson55 SF$16.70$17.064
Nov 25, 2025Mill & Overlay approximately 10 miles on US 45A from the Chickasaw County Line to the Lee Monroe300 SF$10.00$9.004
Nov 25, 2025Safety Improvements on US 84 at MS 184 & at MS 588 in CollinsCovington1.2K SF$12.50$12.054
Oct 28, 2025Mill & Overlay approximately 6 miles on I-20 from Clinton to MS 18Hinds3.0K SF$15.00$15.003
Sep 23, 2025Mill & Overlay approximately 1.1 miles of MS 370 from US 45 to MS 145Lee800 SF$12.00$12.003
Sep 23, 2025Bridge Replacement on SR 704 (Bridge No. 162.5)Benton126 SF$20.00$21.904
Sep 23, 2025Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette5.9K SF$18.00$18.003
Sep 16, 2025Mill & Overlay approximately 7 miles on I-55 from Byram to McDowell RoadHinds1.5K SF$25.00$25.004
Sep 4, 2025Roundabout on I-55 at the Brookway Boulevard InterchangeLincoln819 SF$17.40$17.903
Aug 26, 2025Mill & Overlay approximately 4 miles of SR 302 from 0.25 mile west of Malone Road to 0.06 DeSoto7.9K SF$12.00$12.202
Aug 26, 2025Mill & Overlay approximately 19.5 miles of US 49W from Ruleville to the Coahoma County LinSunflower1.6K SF$8.00$8.003
Aug 26, 2025Mill & Overlay approximately 3.5 miles of US 45 from the beginning of the 4-Lane divided sMonroe40 SF$8.00$8.003
Aug 26, 2025Bridge Repair on US 72 over KCS Railroad (Bridge No. 64.4)Alcorn100 SF$33.00$31.504
Jul 31, 2025Safety Improvements on MS 67 from US 49 to the I-10 "Superstreets" CorridorHarrison18K SF$12.00$12.003
Jul 31, 2025Mill & Overlay approximately 14 miles of I-22 in Union County from the junction at SR 30 tUnion, Pontotoc2.4K SF$15.00$15.002
Jul 22, 2025Mill & Overlay approximately 8 miles on US 49 east from US 82 to 300 north of SR 442Leflore80 SF$12.00$12.002
Jul 22, 2025Mill & Overlay approximately 8 miles of US 49 East from 0.2 mile north of the SR 12 IntersHolmes126 SF$12.00–1
Jun 24, 2025Mill & Overlay on I-55 ramps at the SR 463 interchangeMadison492 SF$13.00$13.003
Jun 24, 2025Directional Median Installation on US 49 at Siloam Road and a Traffic Signal at SR 149Simpson372 SF$10.50$10.002

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.

Price this item against every competitor

BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.

Request access