The low bidder priced red-clear reflective high performance raised markers at a median $12.00 per each over the last 12 months (67 contracts), flat from the year before and up 68% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Overlay approximately 7 miles of MS 48 from SR 24 to Magnolia Progress RoadPike | 93 EA | $15.89 | $15.50 | 3 |
| Oct 27, 2026 | OGFC Lift on I-59 from US 45 to approximately 0.248 miles north of the Russell InterchangeLauderdale | 5.3K EA | $10.00 | – | 1 |
| Oct 27, 2026 | Fog Seal approximately 6.2 miles of I-59 from 0.8 mile north of CR 39 to the Jasper/ClarkeJasper, Clarke | 4.3K EA | $9.00 | $9.50 | 2 |
| Oct 27, 2026 | Fog Seal approximately 5 miles of I-59 from the Forrest County Line to the Forrest County Lamar, Forrest | 3.8K EA | $11.00 | – | 1 |
| Oct 27, 2026 | Mill & Overlay approximately 13.7 miles of I-59 from 0.5 miles north of the McNeil Exit toPearl River | 3.9K EA | $11.00 | – | 1 |
| Oct 27, 2026 | Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery | 8.1K EA | $10.50 | – | 1 |
| Oct 27, 2026 | Construction project, Madison CountyMadison | 6.1K EA | $19.70 | $17.62 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 1.6K EA | $12.95 | $15.00 | 3 |
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 420 EA | $20.00 | $17.25 | 4 |
| Oct 27, 2026 | Mill & Overlay approximately 17 miles of I-22 beginning 1 mile west of the Landfill Road EMarshall | 2.1K EA | $12.80 | $12.00 | 4 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 4.1K EA | $19.25 | $21.25 | 6 |
| Sep 22, 2026 | Installation of Audible Thermoplastic Traffic Markings & Thermoplastic Pavement Markings oDeSoto, Panola, Tate | 658 EA | $5.00 | $6.63 | 2 |
| Sep 22, 2026 | Remove OGFC & Replace with Micro-Surface on I-55 for approximately 14.1 miles from approxiDeSoto, Tate | 3.7K EA | $12.60 | $12.93 | 3 |
| Sep 22, 2026 | Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha | 1.6K EA | $9.00 | – | 4 |
| Sep 22, 2026 | Bridge Repair on US 45 over Norfolk Southern Railroad (Bridge Nos. 275.6A & 275.6B)Alcorn | 20 EA | $17.65 | $17.00 | 7 |
| Aug 25, 2026 | Mill & Overlay approximately 0.5 miles East of US 61Washington | 1.0K EA | $9.00 | – | 1 |
| Aug 25, 2026 | Mill & Overlay approximately 11 miles of US 61 from 0.5 miles North of US 80/SR27 IntersecWarren | 3.3K EA | $12.00 | $12.00 | 3 |
| Aug 21, 2026 | Emergency Bridge Repair on I-55 over SR 32 (Bridge No. 226.7B)Yalobusha | 2 EA | $50.00 | $45.00 | 5 |
| Jul 28, 2026 | Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest | 1.2K EA | $11.50 | $11.50 | 3 |
| Jul 28, 2026 | Bridge Repair on US 98 over I-59 (Bridge No. 149.1)Lamar | 44 EA | $16.00 | $16.25 | 4 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.