The low bidder priced loose riprap, size 300 at a median $116 per ton over the last 12 months (39 contracts), up 13% from the year before and up 93% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Bridge Repair on MS 19 over the Big Black River (Bridge No. 114.9)Attala | 1.1K TON | $170 | $138 | 4 |
| Oct 27, 2026 | Construction project, Madison CountyMadison | 6.9K TON | $122 | $125 | 3 |
| Oct 27, 2026 | Construction project, Madison CountyMadison | 7.0K TON | $122 | $125 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 482 TON | $165 | $155 | 3 |
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 65 TON | $125 | $121 | 4 |
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 4.5K TON | $101 | – | 1 |
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 6.8K TON | $107 | – | 1 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 9.0K TON | $116 | $123 | 6 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 2.0K TON | $132 | $126 | 6 |
| Sep 22, 2026 | Bridge Repair on SR 532 over Stream (Bridge No. 13.5)Covington | 113 TON | $156 | $165 | 6 |
| Sep 22, 2026 | Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha | 240 TON | $80.00 | – | 4 |
| Sep 22, 2026 | Bridge Repair on US 82 over Bogue Phalia (Bridge No. 22.1B) & Bridge Repair on MS 438 overWashington | 2.2K TON | $220 | $210 | 4 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 4.4K TON | $122 | $120 | 3 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 1.2K TON | $122 | $122 | 3 |
| Sep 1, 2026 | Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie | 500 TON | $70.00 | $89.63 | 6 |
| Sep 1, 2026 | Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie | 8.9K TON | $83.50 | $88.13 | 6 |
| Aug 25, 2026 | Bridge Replacement on SR 486 (Bridge No. 1.0)Neshoba | 497 TON | $120 | $119 | 4 |
| Aug 25, 2026 | Bridge Repair on SR 434 on Bridge No. 0.7 and Bridge Rehabilitation on SR 434 on Bridge NoSharkey | 1.5K TON | $135 | $135 | 3 |
| Aug 25, 2026 | SR 145 Bridge Replacement (Bridge No. 210.8), Known as Federal Aid Project No. STBG-0053-0Lee | 450 TON | $63.50 | $63.25 | 8 |
| Aug 25, 2026 | Mill & Overlay approximately 11 miles of US 61 from 0.5 miles North of US 80/SR27 IntersecWarren | 40 TON | $120 | $120 | 3 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.