MDOT pay item · 201-D001

Random Clearing: Mississippi winning bid prices

The low bidder priced random clearing at a median $880 per station over the last 12 months (45 contracts), down 12% from the year before and up 55% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$880
45 contracts
Median, prior 12 months
$1,000
27 contracts
Median, 2020
$568
4 contracts
Winner vs. field
level with
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$250$500$750$1,000$1,250$1,5002020202120222023202420252026*$885
Price vs. quantityEvery winning price since 2020 (log scale)
$0$1,000$2,000$3,000101001.0K
Does quantity matter?Median winning price by quantity band
$0$500$1,000$1,500$1,250≤85$70085–222$766222–454$662>454

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Oct 27, 2026Overlay approximately 7 miles of MS 48 from SR 24 to Magnolia Progress RoadPike391 STA$1,138$1,1003
Oct 27, 2026OGFC Lift on I-59 from US 45 to approximately 0.248 miles north of the Russell InterchangeLauderdale454 STA$880–1
Oct 27, 2026Fog Seal approximately 6.2 miles of I-59 from 0.8 mile north of CR 39 to the Jasper/ClarkeJasper, Clarke769 STA$550$7082
Oct 27, 2026Fog Seal approximately 5 miles of I-59 from the Forrest County Line to the Forrest County Lamar, Forrest519 STA$940–1
Oct 27, 2026Mill & Overlay approximately 13.7 miles of I-59 from 0.5 miles north of the McNeil Exit toPearl River1.3K STA$850–1
Oct 27, 2026Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery909 STA$1,044–1
Oct 27, 2026Construction project, Madison CountyMadison16 STA$2,734$2,9373
Oct 27, 2026Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren785 STA$1,715$1,7153
Oct 27, 2026Mill & Overlay approximately 17 miles of I-22 beginning 1 mile west of the Landfill Road EMarshall893 STA$800$8744
Sep 29, 2026Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin12 STA$1,563$3,6256
Sep 22, 2026Remove OGFC & Replace with Micro-Surface on I-55 for approximately 14.1 miles from approxiDeSoto, Tate329 STA$978$1,2743
Jul 28, 2026Thin Lift Overlay approximately 10.2 miles of MS 467 from beginning of maintenance to SoutHinds759 STA$750$7503
Jul 28, 2026Micro-Surface approximately 14 miles of SR 512 & SR 513Clarke700 STA$690$9172
Jun 23, 2026Widen & Overlay approximately 2 miles of SR 26 from the east end of the Pearl River BridgePearl River217 STA$700–1
Jun 23, 2026Overlay approximately 8.5 miles of MS 587 from the Marion County Line to the Northern ErviLawrence692 STA$635$5714
Jun 23, 2026Mill & Overlay approximately 3.87 miles of SR 149 from US 49S to US 49NStone146 STA$1,000$8502
Jun 23, 2026Overlay and OGFC Lift from east of the Shorecrest Road Overpass to approximately 0.9 mile Harrison260 STA$1,175$1,1382
Jun 23, 2026Thin Lift Overlay approximately 8.5 miles of SR 514 from SR 513 to SR 145, approximately 0Clarke, Jasper1.3K STA$537$4893
Jun 5, 2026Mill & Overlay approximately 10.1 miles of MS 178 from the Marshall County Line to the UniBenton261 STA$1,200$1,2503
Jun 5, 2026Overlay approximately 14.3 miles of MS Highway 7 beginning at the Lafayette County Line goMarshall234 STA$865–1

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.