The low bidder priced borrow excavation, ah, lvm, class b9-6 at a median $36.00 per cubic yard over the last 12 months (3 contracts) and up 177% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Mill & Overlay approximately 17 miles of I-22 beginning 1 mile west of the Landfill Road EMarshall | 135 CY | $36.00 | $74.50 | 4 |
| Aug 25, 2026 | US 49 over Big Sunflower River Tributary (Bridge No. 305.6)Coahoma | 680 CY | $25.00 | $55.00 | 6 |
| Apr 10, 2026 | Pavement Restoration on US 49 from Madison County Line to 0.8 miles North of Old Highway 4Yazoo | 240 CY | $57.50 | $57.50 | 3 |
| Jun 25, 2024 | Intersection Improvements on USRankin | 1.2K CY | $27.50 | $30.90 | 2 |
| Apr 23, 2024 | Mill & Overlay approximately 9.5 miles of SR 469 from Florence to SR 468Rankin | 24 CY | $75.00 | $75.00 | 4 |
| Jan 24, 2024 | Construction project, Harrison CountyHarrison | 5.6K CY | $27.00 | – | 1 |
| May 23, 2023 | Slide Repair on SR 555 approximately 0.5 miles north of USAdams | 500 CY | $30.00 | $27.50 | 4 |
| Oct 31, 2022 | Safety Improvements along SRLauderdale | 500 CY | $50.00 | – | 1 |
| Oct 25, 2022 | Construction project, Oktibbeha CountyOktibbeha | 21K CY | $27.50 | – | 1 |
| Sep 28, 2022 | Construction project, Jefferson CountyJefferson | 107 CY | $55.00 | $58.00 | 3 |
| Jun 28, 2022 | Construction project, Warren CountyWarren | 2.5K CY | $17.50 | $25.00 | 5 |
| Feb 23, 2022 | Construction project, Adams CountyAdams | 17K CY | $10.16 | $17.58 | 2 |
| Sep 28, 2021 | Overlay approximatelyLauderdale | 100 CY | $70.00 | $51.50 | 2 |
| Sep 29, 2020 | Construction project, Itawamba CountyItawamba | 680 CY | $27.80 | $23.40 | 2 |
| May 28, 2020 | Basin Flood Damage February 2020 in DistrictLawrence, Marion, Pearl River | 939 CY | $13.00 | $21.50 | 2 |
| Mar 24, 2020 | Construction project, Covington CountyCovington | 6.2K CY | $1.00 | $10.00 | 7 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.