The low bidder priced special sections, guard rail bridge end connector at a median $1,959 per each over the last 12 months (3 contracts), down 24% from the year before and up 39% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Jun 23, 2026 | Overlay approximately 8.5 miles of MS 587 from the Marion County Line to the Northern ErviLawrence | 4 EA | $1,269 | $1,172 | 4 |
| Apr 28, 2026 | OGFC Lift on I-55 from the Mississippi State Line to MS 568Pike | 16 EA | $1,959 | $2,104 | 2 |
| Mar 24, 2026 | Overlay approximately 11.7 miles of MS 27 from US 84 to the Copiah County LineLawrence | 12 EA | $2,100 | $2,175 | 4 |
| Apr 1, 2025 | Mill & Overlay approximately 4 miles of SR 15 from Queen Street to north of Audubon DriveJones | 4 EA | $3,724 | $3,952 | 3 |
| Mar 25, 2025 | Mill & Overlay approximately 7 miles of I-20 from 5.1 miles east of SR 15 to 2.3 miles easNewton | 12 EA | $2,584 | – | 1 |
| Jan 28, 2025 | Overlay approximately 10 miles of SR 43 from SR 481 to the Madison County LineRankin | 2 EA | $1,250 | $1,250 | 4 |
| Sep 25, 2024 | Overlay approximatelyCovington | 4 EA | $1,090 | $1,090 | 3 |
| Aug 27, 2024 | Construction project, Lowndes CountyLowndes | 4 EA | $5,400 | $5,400 | 3 |
| May 29, 2024 | Overlay approximatelyRankin | 8 EA | $935 | $935 | 4 |
| Apr 23, 2024 | Mill & Overlay approximately 9.5 miles of SR 469 from Florence to SR 468Rankin | 2 EA | $1,300 | $1,300 | 4 |
| Aug 22, 2023 | Overlay approximatelySimpson | 4 EA | $2,450 | $2,450 | 4 |
| May 23, 2023 | Overlay approximatelyWinston | 2 EA | $3,150 | $3,150 | 3 |
| Sep 28, 2022 | Overlay approximatelyWinston | 12 EA | $1,250 | – | 1 |
| Jul 27, 2021 | Mill & Overlay approximately 9 miles on SR 22 from SR 463 to the Beginning of theMadison | 8 EA | $1,300 | $1,300 | 2 |
| Sep 22, 2020 | Overlay approximatelyJones | 4 EA | $1,575 | $1,538 | 4 |
| Jan 28, 2020 | Overlay approximatelyLauderdale | 16 EA | $1,250 | – | 1 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.