BidCrew Data
BidCrew Data / Mississippi / Prices / Detectable Warning Panels
MDOT pay item · 907-608-C001

Detectable Warning Panels: Mississippi winning bid prices

The low bidder priced detectable warning panels at a median $39.02 per square foot over the last 12 months (2 contracts), down 48% from the year before and down 8% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$39.02
2 contracts
Median, prior 12 months
$75.00
2 contracts
Median, 2020
$42.50
2 contracts
Winner vs. field
level with
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$20$40$60$80$100$1202020202120222023202420252026*$39.02
Price vs. quantityEvery winning price since 2020 (log scale)
$25$50$75$100$125$15010100
Does quantity matter?Median winning price by quantity band
$0$50$100$150$120≤35$30.5035–110$42.40110–176$40.94>176

The last 17 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Oct 27, 2026Construction project, Madison CountyMadison120 SF$36.80$36.803
Apr 28, 2026I-10 Jackson County Welcome CenterJackson282 SF$41.25$34.054
Aug 26, 2025Mill & Overlay approximately 19.5 miles of US 49W from Ruleville to the Coahoma County LinSunflower35 SF$25.00$25.003
May 28, 2025Mill & Overlay approximately 3 miles of SR 178 from North Access Road to Old SR 25Itawamba9 SF$125$87.504
Jun 11, 2024Construction project, Lafayette CountyLafayette380 SF$30.00$37.505
May 29, 2024Traffic Signal Installation on US 49W at SRSunflower16 SF$120$95.002
Jan 24, 2024Construction of a Roundabout on USTate48 SF$25.00$32.502
Jan 24, 2024Intersection Improvements at SRSmith176 SF$48.00$33.105
Jan 24, 2024Interchange Reconstruction on I-10 at Diamondhead, known as Federal Aid Project No. NHPP-0Hancock126 SF$115$1153
Jan 24, 2024Construction project, Harrison CountyHarrison818 SF$40.62–1
Dec 5, 2023Bridge Replacement on US 11 at Hobolochitto Creek in Picayune (Bridge No. 11.3), known as Pearl River110 SF$25.00$29.505
Oct 24, 2023Construction project, Sunflower CountySunflower20 SF$122$73.252
Sep 28, 2022Construction project, Clarke CountyClarke20 SF$33.85$35.003
Jul 27, 2021Construction project, Harrison CountyHarrison50 SF$36.00$35.003
Jan 26, 2021Overlay approximatelyNewton40 SF$140$82.502
Apr 28, 2020Mill & Overlay approximately 2.0 miles of US 51 from Dinkins St to SRMadison180 SF$60.00$60.003
Feb 25, 2020Construction project, DeSoto CountyDeSoto160 SF$25.00$25.003

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.

Price this item against every competitor

BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.

Request access