The low bidder priced temporary traffic stripe, legend at a median $1.50 per linear foot over the last 12 months (72 contracts), down 25% from the year before and up 50% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Overlay approximately 7 miles of MS 48 from SR 24 to Magnolia Progress RoadPike | 4.0K LF | $0.53 | $0.53 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 13.7 miles of I-59 from 0.5 miles north of the McNeil Exit toPearl River | 332 LF | $0.60 | – | 1 |
| Oct 27, 2026 | Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery | 200 LF | $2.75 | – | 1 |
| Oct 27, 2026 | Construction project, Madison CountyMadison | 2.6K LF | $2.10 | $1.17 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 1.5K LF | $0.50 | $0.63 | 3 |
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 246 LF | $2.00 | $1.70 | 4 |
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 216 LF | $1.18 | – | 1 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 12K LF | $0.75 | $0.88 | 6 |
| Sep 22, 2026 | Mill & Overlay approximately 2.5 miles of US 49 from SR 1 to the Isle of Capri ParkwayCoahoma | 360 LF | $3.10 | – | 1 |
| Sep 22, 2026 | Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha | 619 LF | $2.00 | – | 4 |
| Sep 22, 2026 | Bridge Repair on US 82 over Bogue Phalia (Bridge No. 22.1B) & Bridge Repair on MS 438 overWashington | 192 LF | $2.75 | $2.69 | 4 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 119 LF | $2.10 | $2.10 | 3 |
| Aug 25, 2026 | Overlay approximately 3.6 miles of MS 550 from SR 28 to the Lincoln County LineJefferson | 300 LF | $1.52 | $1.66 | 4 |
| Aug 25, 2026 | Overlay approximately 2.9 miles of MS 354 from the junction of MS 15 to the end of state mTippah | 1.7K LF | $3.00 | $3.00 | 3 |
| Aug 25, 2026 | Mill & Overlay approximately 0.5 miles East of US 61Washington | 500 LF | $2.00 | – | 1 |
| Aug 25, 2026 | Bridge Repair on SR 434 on Bridge No. 0.7 and Bridge Rehabilitation on SR 434 on Bridge NoSharkey | 144 LF | $2.15 | $2.00 | 3 |
| Aug 25, 2026 | Mill & Overlay approximately 11 miles of US 61 from 0.5 miles North of US 80/SR27 IntersecWarren | 4.0K LF | $0.50 | $0.60 | 3 |
| Aug 25, 2026 | US 49 over Big Sunflower River Tributary (Bridge No. 305.6)Coahoma | 192 LF | $1.75 | $11.00 | 6 |
| Jul 28, 2026 | Thin Lift Overlay approximately 10.2 miles of MS 467 from beginning of maintenance to SoutHinds | 2.0K LF | $1.00 | $1.00 | 3 |
| Jul 28, 2026 | Widening on I-10 at MS 605 WB RampHarrison | 176 LF | $0.59 | $1.04 | 3 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.