6" Thermoplastic Double Drop Traffic Stripe, Continuous White: Mississippi winning bid prices

The low bidder priced 6" thermoplastic double drop traffic stripe, continuous white at a median $8,930 per mile over the last 12 months (3 contracts), up 13% from the year before and up 24% since 2024.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$8,930
3 contracts
Median, prior 12 months
$7,900
23 contracts
Median, 2024
$7,200
9 contracts
Winner vs. field
level with
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$7,000$7,500$8,000$8,500$9,000$9,5002020202120222023202420252026*$8,600
Price vs. quantityEvery winning price since 2020 (log scale)
$4,000$6,000$8,000$10,000$12,00010
Does quantity matter?Median winning price by quantity band
$0$2,000$4,000$6,000$8,000$10,000$8,930≤9.75$8,5009.75–16$7,80016–30$7,600>30

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Oct 28, 2025Placement of Audible Stripe on MS 433 from Yazoo County Line to Ebenezer-Coxburg Road in BHolmes, Yazoo31 MI$3,850–1
Oct 28, 2025Mill, Level & Overlay approximately 4 miles of US 49 from US 11 to beginning of divided seForrest2 MI$8,930$9,7152
Oct 28, 2025Mill & Overlay approximately 6 miles on I-20 from Clinton to MS 18Hinds17 MI$9,500$9,5003
Sep 23, 2025Mill & Overlay approximately 1.1 miles of MS 370 from US 45 to MS 145Lee3 MI$9,000$9,0003
Sep 23, 2025Scrub Seal & Overlay approximately 6 miles of SR 27 from I-55 to the Hinds County LineCopiah11 MI$9,200$9,2004
Sep 16, 2025Mill & Overlay approximately 7 miles on I-55 from Byram to McDowell RoadHinds15 MI$10,000$10,0004
Aug 26, 2025Overlay approximately 4.6 miles of SR 552 from the beginning of State Maintenance to SR 28Jefferson9 MI$9,500$9,5003
Aug 26, 2025Mill & Overlay approximately 19.5 miles of US 49W from Ruleville to the Coahoma County LinSunflower37 MI$7,600$7,6003
Jul 31, 2025Mill & Overlay approximately 14 miles of I-22 in Union County from the junction at SR 30 tUnion, Pontotoc36 MI$9,000$9,0002
Jul 22, 2025Mill & Overlay approximately 8 miles of US 49 East from 0.2 mile north of the SR 12 IntersHolmes14 MI$7,600–1
May 28, 2025Overlay approximately 17.7 miles of SR 450 from SR 1 to US 61Bolivar35 MI$7,900–1
May 28, 2025Remove & Replace OGFC Lift on approximately 2 miles of I-220 from the Hinds County Line toMadison, Hinds32 MI$8,700$8,7002
Apr 30, 2025Mill & Overlay & Concrete Rehabilitation on approximately 2 miles of SR 25 from the BOSM tHinds8 MI$7,000$7,0003
Mar 25, 2025Mill & Overlay approximately 7 miles of I-20 from 5.1 miles east of SR 15 to 2.3 miles easNewton14 MI$8,600–1
Mar 25, 2025Concrete Pavement Rehabilitation on approximately 2.3 miles of US 82 through IndianolaSunflower5 MI$7,900$8,6683
Feb 25, 2025Mill & Overlay approximately 9 miles of US 51 from the Madison City Limits to Dinkins StreMadison17 MI$7,900$7,9002
Feb 25, 2025Remove & Replace approximately 13 miles of OGFC on I-20 from East Brandon to the Scott CouRankin27 MI$9,700$9,7003
Jan 28, 2025Mill & Overlay approximately 7 miles of SR 16 from lane mile 13.195 to 0.5 miles east of tLeake, Neshoba29 MI$6,800$6,8002
Jan 28, 2025Widen & Overlay approximately 11 miles of SR 28 from 2.4 miles east of Dennis Cross Road tJefferson21 MI$7,800$7,8002
Dec 5, 2024Overlay approximately 3 miles of US 61 from the end of the 4-Lane Section to SR 547Claiborne5 MI$7,500$7,5002

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.