The low bidder priced 30" steel pipe piling, wall thickness 0.500" at a median $460 per linear foot over the last 12 months (1 contracts), up 163% from the year before and up 207% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 1.5K LF | $460 | – | 1 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 1.8K LF | $200 | $310 | 3 |
| Jun 26, 2025 | Bridge Replacements on US 80 between Chunky & Meehan (Bridge Nos. 123.1, 123.3, 123.5 & 12Lauderdale, Madison, Newton | 2.6K LF | $175 | $245 | 3 |
| Mar 4, 2025 | Grade Bridge, Pave 2-Lane on SR 19 from 0.25 miles South of SR 492 to Tucker DriveNeshoba | 845 LF | $65.00 | $149 | 2 |
| Apr 2, 2024 | Construction project, Madison CountyMadison | 810 LF | $180 | $188 | 7 |
| Jan 31, 2024 | Bridge Replacement on USJackson | 1.8K LF | $235 | $235 | 5 |
| Dec 5, 2023 | Bridge Replacement on US 11 at Hobolochitto Creek in Picayune (Bridge No. 11.3), known as Pearl River | 1.2K LF | $185 | $215 | 5 |
| Sep 27, 2023 | Construction project, Jackson CountyJackson | 2.3K LF | $140 | $180 | 3 |
| Aug 1, 2023 | Construction project, Pontotoc CountyPontotoc | 1.0K LF | $203 | $206 | 2 |
| Feb 23, 2022 | Construction project, Calhoun CountyCalhoun | 3.0K LF | $250 | $280 | 5 |
| Apr 27, 2021 | Bridge Replacement on SRMarshall | 845 LF | $250 | – | 2 |
| Mar 23, 2021 | Bridge Replacement on USJackson | 5.1K LF | $175 | – | 4 |
| Apr 28, 2020 | Bridge Replacements on SRLeake | 825 LF | $150 | – | 1 |
| Mar 24, 2020 | Construction project, Jackson CountyJackson | 6.2K LF | $160 | – | 3 |
| Jan 28, 2020 | Construction project, Neshoba CountyNeshoba | 1.1K LF | $150 | $185 | 5 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.