The low bidder priced random clearing at a median $10,000 per acre over the last 12 months (1 contracts), up 111% from the year before and up 8% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$10,000
1 contracts
Median, prior 12 months
$4,736
2 contracts
Median, 2020
$9,300
3 contracts
Winner vs. field
level with
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$0$10,000$20,000$30,0002020202120222023202420252026*$10,000
Price vs. quantityEvery winning price since 2020 (log scale)
$0$10,000$20,000$30,000$40,000$50,000110
Does quantity matter?Median winning price by quantity band
$0$10,000$20,000$30,000$12,200≤2$25,6502–8$7,5008–26$13,250>26

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
May 27, 2026Mill & Overlay 10 miles of SR 371 from the Mantachie Corp. limit to the Prentiss County LiItawamba1 ACRE$10,000$10,5003
May 28, 2025Remove & Replace OGFC Lift on approximately 2 miles of I-220 from the Hinds County Line toMadison, Hinds11 ACRE$8,972$8,9722
Feb 25, 2025Bank Stabilization on SR 37 over Oakohay Creek (Bridge No. 4.3)Covington1 ACRE$500$5,9458
Oct 22, 2024Remove & Replace OGFC on approximately 9 miles of I-55 from US 98W to the bridge south of Lincoln, Pike96 ACRE$15,101–1
Apr 23, 2024Mill & Overlay approximately 12 miles of SR 7 from 2 miles south of Morgan City to Itta BeLeflore1 ACRE$12,500$12,5003
Oct 24, 2023Overlay approximatelyRankin11 ACRE$7,500$7,5003
Nov 22, 2022Construction project, Hinds CountyHinds9 ACRE$2,850$2,4256
Sep 28, 2022Construction projectDistrict 51 ACRE$4,500–1
Sep 28, 2022Overlay approximatelyMontgomery2 ACRE$42,000–1
Jul 27, 2022Construction project, Hinds CountyHinds19 ACRE$12,936$12,9363
Apr 26, 2022Construction project, Hinds CountyHinds63 ACRE$13,250$24,6252
Mar 22, 2022Overlay approximatelyCarroll60 ACRE$10,865–1
Nov 23, 2021Grade, Drain, Bridge & Pave 4-Lane for approximately 9 miles of the USWashington2 ACRE$25,000$19,2502
Sep 28, 2021Overlay approximatelyLincoln77 ACRE$12,000$10,6902
Jun 22, 2021Overlay approximatelyJefferson Davis65 ACRE$23,000$25,7502
May 25, 2021Construction project, Madison CountyMadison1 ACRE$12,200$10,8504
Mar 23, 2021Construction project, Jackson CountyJackson5 ACRE$4,950$6,5003
Jan 26, 2021Overlay approximatelyCarroll4 ACRE$43,000–1
Jul 28, 2020And IM-0059-01(126) / 107825302 in Forrest & Lamar Mill & Overlay approximately 7 miles onForrest, Lamar26 ACRE$6,700$9,1252
Apr 28, 2020Construction project, Pearl River CountyPearl River8 ACRE$42,000$40,0003

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.

Price this item against every competitor

BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.

Request access