The low bidder priced removal of curb & gutter, all types at a median $12.50 per linear foot over the last 12 months (7 contracts), down 50% from the year before and down 29% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 60 LF | $28.75 | $40.88 | 3 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 10K LF | $12.50 | $16.15 | 6 |
| Jul 28, 2026 | Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest | 1.9K LF | $18.00 | $16.00 | 3 |
| May 27, 2026 | Restricted Crossing U-Turn (RCUT) on US 84 at MS 33Franklin | 1.8K LF | $8.00 | $12.82 | 2 |
| May 27, 2026 | Intersection Improvements on US 45 from Misso Road to Magnolia Drive, and Mill & Overlay aNoxubee | 1.5K LF | $15.00 | $15.38 | 2 |
| Apr 28, 2026 | Restricted Crossing U-Turn (RCUT) on US 278 at CR 217/405Lafayette | 787 LF | $10.00 | $20.00 | 5 |
| Nov 25, 2025 | Safety Improvements on US 84 at MS 184 & at MS 588 in CollinsCovington | 3.1K LF | $7.20 | $12.10 | 4 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 7.5K LF | $10.00 | $10.00 | 3 |
| Sep 4, 2025 | Roundabout on I-55 at the Brookway Boulevard InterchangeLincoln | 391 LF | $14.40 | $17.50 | 3 |
| Aug 26, 2025 | Mill & Overlay approximately 19.5 miles of US 49W from Ruleville to the Coahoma County LinSunflower | 25 LF | $30.00 | $30.00 | 3 |
| Jul 31, 2025 | Safety Improvements on MS 67 from US 49 to the I-10 "Superstreets" CorridorHarrison | 2.4K LF | $16.00 | $16.00 | 3 |
| Jul 22, 2025 | Mill & Overlay approximately 3 miles of US 98 from 400 feet west of Weathersby Drive to thLamar, Forrest | 70 LF | $44.00 | $41.00 | 2 |
| Apr 30, 2025 | Mill & Overlay & Concrete Rehabilitation on approximately 2 miles of SR 25 from the BOSM tHinds | 46 LF | $52.25 | $52.25 | 3 |
| Apr 1, 2025 | Mill & Overlay approximately 4 miles of SR 15 from Queen Street to north of Audubon DriveJones | 824 LF | $10.00 | $10.00 | 3 |
| Apr 1, 2025 | Roundabout Construction on SR 15 at SR 16 & Bridge Replacements on Weyerhaeuser Street oveNeshoba | 1.2K LF | $25.00 | $26.45 | 2 |
| Mar 25, 2025 | Bridge Replacement on Old Brandon Road (Bridge No. 48.6)Rankin | 44 LF | $19.25 | $32.00 | 3 |
| Feb 4, 2025 | Roundabout Construction on SR 15 at SR 16 & Bridge Replacements on Weyerhaeuser Street oveNeshoba | 1.2K LF | $25.60 | – | 1 |
| Jan 28, 2025 | Wayne Installation of Ramp Gates on I-59 from the Louisiana State Line to north of US 84 &Lincoln, Pike, Forrest, Jones, Lamar, Pearl River, Adams | 408 LF | $200 | $115 | 3 |
| Jan 28, 2025 | Drainage Improvements on US 61 near BlakelyWarren | 685 LF | $17.09 | – | 1 |
| Dec 5, 2024 | Mill & Overlay approximately 6 miles of SR 5 from 0.1 miles north of Shop to US 72Benton | 75 LF | $25.00 | $18.00 | 5 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.