The low bidder priced riprap for erosion control at a median $126 per ton over the last 12 months (21 contracts), up 26% from the year before and up 71% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery | 250 TON | $138 | – | 1 |
| Oct 27, 2026 | Construction project, Madison CountyMadison | 8.0K TON | $122 | $122 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 685 TON | $165 | $155 | 3 |
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 64 TON | $175 | $115 | 4 |
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 605 TON | $107 | – | 1 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 1.5K TON | $140 | $133 | 6 |
| Sep 22, 2026 | Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha | 130 TON | $100 | – | 4 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 935 TON | $118 | $120 | 3 |
| Sep 1, 2026 | Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie | 1.6K TON | $100 | $92.28 | 6 |
| Aug 25, 2026 | Bridge Replacement on SR 486 (Bridge No. 1.0)Neshoba | 20 TON | $200 | $153 | 4 |
| Aug 25, 2026 | SR 145 Bridge Replacement (Bridge No. 210.8), Known as Federal Aid Project No. STBG-0053-0Lee | 50 TON | $150 | $80.00 | 8 |
| Jul 28, 2026 | Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest | 75 TON | $130 | $130 | 3 |
| Jul 28, 2026 | Bank Stabilization on SR 12 over Big Black River (Bridge No. 83.4)Holmes, Attala | 720 TON | $80.25 | $101 | 10 |
| May 27, 2026 | Bridge Replacement on SR 427 (Bridge No. 4.4) between SR 488 & SR 16Leake | 1.0K TON | $84.15 | $118 | 8 |
| May 27, 2026 | Bridge Replacement on SR 15 over Cypress Branch on Bridge No. 15.7Harrison | 25 TON | $110 | $125 | 5 |
| May 27, 2026 | Restricted Crossing U-Turn (RCUT) on US 84 at MS 33Franklin | 78 TON | $150 | $150 | 2 |
| May 8, 2026 | Level & Overlay approximately 8.4 miles on SR 18 from Smith County Line to east of Bay SprJasper | 245 TON | $172 | $150 | 3 |
| Apr 28, 2026 | I-10 Jackson County Welcome CenterJackson | 75 TON | $126 | $126 | 4 |
| Apr 28, 2026 | I-10 Jackson County Welcome CenterJackson | 53 TON | $436 | $426 | 4 |
| Nov 25, 2025 | Bridge Replacement on SR 481 between SR 902 & SR 35 (Bridge Nos. 2.1 & 2.3)Smith | 62 TON | $96.00 | $115 | 7 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.