MDOT pay item · 249-A001

Riprap for Erosion Control: Mississippi winning bid prices

The low bidder priced riprap for erosion control at a median $126 per ton over the last 12 months (21 contracts), up 26% from the year before and up 71% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$126
21 contracts
Median, prior 12 months
$100
18 contracts
Median, 2020
$73.60
11 contracts
Winner vs. field
level with
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$50$75$100$125$150$1752020202120222023202420252026*$130
Price vs. quantityEvery winning price since 2020 (log scale)
$0$100$200$3001101001.0K10K
Does quantity matter?Median winning price by quantity band
$0$50$100$150$121≤54$10054–158$94.88158–601$84.58>601

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Oct 27, 2026Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery250 TON$138–1
Oct 27, 2026Construction project, Madison CountyMadison8.0K TON$122$1223
Oct 27, 2026Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren685 TON$165$1553
Oct 27, 2026Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin64 TON$175$1154
Oct 27, 2026Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson605 TON$107–1
Sep 29, 2026Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin1.5K TON$140$1336
Sep 22, 2026Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha130 TON$100–4
Sep 1, 2026Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike935 TON$118$1203
Sep 1, 2026Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie1.6K TON$100$92.286
Aug 25, 2026Bridge Replacement on SR 486 (Bridge No. 1.0)Neshoba20 TON$200$1534
Aug 25, 2026SR 145 Bridge Replacement (Bridge No. 210.8), Known as Federal Aid Project No. STBG-0053-0Lee50 TON$150$80.008
Jul 28, 2026Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest75 TON$130$1303
Jul 28, 2026Bank Stabilization on SR 12 over Big Black River (Bridge No. 83.4)Holmes, Attala720 TON$80.25$10110
May 27, 2026Bridge Replacement on SR 427 (Bridge No. 4.4) between SR 488 & SR 16Leake1.0K TON$84.15$1188
May 27, 2026Bridge Replacement on SR 15 over Cypress Branch on Bridge No. 15.7Harrison25 TON$110$1255
May 27, 2026Restricted Crossing U-Turn (RCUT) on US 84 at MS 33Franklin78 TON$150$1502
May 8, 2026Level & Overlay approximately 8.4 miles on SR 18 from Smith County Line to east of Bay SprJasper245 TON$172$1503
Apr 28, 2026I-10 Jackson County Welcome CenterJackson75 TON$126$1264
Apr 28, 2026I-10 Jackson County Welcome CenterJackson53 TON$436$4264
Nov 25, 2025Bridge Replacement on SR 481 between SR 902 & SR 35 (Bridge Nos. 2.1 & 2.3)Smith62 TON$96.00$1157

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.