Size 610 Crushed Stone Base, LVM: Mississippi winning bid prices

The low bidder priced size 610 crushed stone base, lvm at a median $80.00 per cubic yard over the last 12 months (5 contracts), up 33% from the year before and down 19% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$80.00
5 contracts
Median, prior 12 months
$60.00
3 contracts
Median, 2020
$98.50
2 contracts
Winner vs. field
level with
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$50$100$150$200$2502020202120222023202420252026*$80.00
Price vs. quantityEvery winning price since 2020 (log scale)
$0$50$100$150$200$250$3001001.0K
Does quantity matter?Median winning price by quantity band
$0$50$100$150$118≤139$125139–235$90.00235–443$125>443

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Jun 5, 2026Mill & Overlay approximately 9 miles of SR 25 from US 45A to US 45Monroe1.5K CY$128–2
May 27, 2026Scrub Seal & Overlay approximately 12 miles of MS 172 from the junction of US 72 to the JuTishomingo110 CY$80.00–2
May 27, 2026Mill & Overlay approximately 7 miles of SR 4 from east of Church Street to west of the JunPrentiss300 CY$60.00$63.752
Apr 10, 2026Mill & Overlay approximately 7 miles of US 82 from 1 mile east of Military Road to the AlaLowndes120 CY$100$1002
Mar 24, 2026Mill & Overlay approximately 3 miles of SR 145 from beginning of 4-lane section near CedarPrentiss615 CY$25.00$45.002
Apr 22, 2025Mill & Overlay approximately 7 miles of SR 350 from the Alcorn County Line to SR 25Tishomingo425 CY$90.00$84.273
Nov 26, 2024Mill & Overlay approximately 15 miles of US 45A from the Noxubee County Line to the Clay CLowndes50 CY$50.00–3
Nov 26, 2024Mill & Overlay approximately 4 miles of SR 2 from US 45 to SR 350 & approximately 6 miles Alcorn224 CY$60.00–3
Jul 23, 2024Overlay approximatelyChickasaw310 CY$70.00$60.004
Apr 23, 2024Thin Lift Overlay approximately 10 miles of SR 568 from Louisiana State Line to Bankston RAmite1.9K CY$157–1
Apr 25, 2023Construction project, Pike CountyPike200 CY$200$1562
Mar 28, 2023Overlay approximatelyLawrence370 CY$230–1
Oct 31, 2022Overlay approximatelyAmite1.1K CY$181–1
Jul 27, 2022Overlay approximatelyChickasaw239 CY$183$1792
Apr 26, 2022Overlay approximatelyJefferson Davis139 CY$165–1
Apr 26, 2022Overlay approximatelyAdams124 CY$290–1
Apr 26, 2022Overlay approximatelyAdams115 CY$158–1
Mar 22, 2022Overlay approximatelyTippah130 CY$110–2
Feb 23, 2022Mill & Overlay approximately 4.Clay, Monroe165 CY$70.00$1082
Feb 23, 2022Construction project, Lincoln CountyLincoln443 CY$100–1

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.

Price this item against every competitor