The low bidder priced joint sealant at a median $2,500 per mile over the last 12 months (9 contracts), up 39% from the year before and up 52% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Mill & Overlay approximately 13.7 miles of I-59 from 0.5 miles north of the McNeil Exit toPearl River | 55 MI | $2,300 | – | 1 |
| Oct 27, 2026 | Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery | 15 MI | $1,700 | – | 1 |
| Oct 27, 2026 | Construction project, Madison CountyMadison | 34 MI | $1,799 | $1,921 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 25 MI | $5,600 | $5,800 | 3 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 24 MI | $3,900 | $2,845 | 6 |
| May 27, 2026 | Intersection Improvements on US 45 from Misso Road to Magnolia Drive, and Mill & Overlay aNoxubee | 23 MI | $2,500 | $2,125 | 2 |
| Apr 28, 2026 | OGFC Lift on I-55 from the Mississippi State Line to MS 568Pike | 16 MI | $2,800 | $2,988 | 2 |
| Nov 25, 2025 | Mill & Overlay approximately 10 miles on US 45A from the Chickasaw County Line to the Lee Monroe | 21 MI | $3,300 | $3,275 | 4 |
| Oct 28, 2025 | Mill & Overlay approximately 6 miles on I-20 from Clinton to MS 18Hinds | 63 MI | $1,900 | $2,100 | 3 |
| Sep 16, 2025 | Mill & Overlay approximately 7 miles on I-55 from Byram to McDowell RoadHinds | 65 MI | $2,260 | $2,100 | 4 |
| Aug 26, 2025 | Mill & Overlay approximately 3.5 miles of US 45 from the beginning of the 4-Lane divided sMonroe | 18 MI | $1,500 | $1,500 | 3 |
| Aug 26, 2025 | Mill & Overlay approximately 4.3 miles of I-55 Carroll Co from the Montgomery County Line Carroll, Montgomery | 14 MI | $1,500 | – | 1 |
| Jul 31, 2025 | Mill & Overlay approximately 14 miles of I-22 in Union County from the junction at SR 30 tUnion, Pontotoc | 86 MI | $1,800 | $2,150 | 2 |
| Mar 25, 2025 | Mill & Overlay approximately 4 miles of I-69 from 0.95 miles north of I-269 to 0. 51 2 milDeSoto | 7 MI | $1,450 | $1,325 | 2 |
| Mar 25, 2025 | Mill & Overlay approximately 7 miles of I-20 from 5.1 miles east of SR 15 to 2.3 miles easNewton | 27 MI | $2,260 | – | 1 |
| Nov 26, 2024 | Mill & Overlay approximately 5 miles of I-22 from the Union County Line to the Belden ExitLee, Pontotoc | 23 MI | $1,800 | $2,300 | 3 |
| May 29, 2024 | Overlay approximatelyRankin | 22 MI | $2,100 | $2,150 | 4 |
| Mar 26, 2024 | Pavement Restoration of approximately 5 miles of I-55 from SR 24 to US 98 & Roundabout ConPike | 20 MI | $3,000 | $3,200 | 2 |
| Oct 24, 2023 | Overlay approximatelyRankin | 68 MI | $1,970 | $2,500 | 3 |
| Jun 27, 2023 | Safety Improvements on approximatelyLowndes | 27 MI | $5,000 | $4,100 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.