The low bidder priced stone matrix asphalt, 9.5 mm mixture at a median $180 per ton over the last 12 months (15 contracts), down 3% from the year before and up 11% since 2021.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Mill & Overlay approximately 13.7 miles of I-59 from 0.5 miles north of the McNeil Exit toPearl River | 37K TON | $180 | – | 1 |
| Oct 27, 2026 | Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery | 21K TON | $188 | – | 1 |
| Oct 27, 2026 | Construction project, Madison CountyMadison | 45K TON | $194 | $195 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 18K TON | $203 | $210 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 17 miles of I-22 beginning 1 mile west of the Landfill Road EMarshall | 48K TON | $159 | $182 | 4 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 13K TON | $170 | $196 | 6 |
| May 27, 2026 | Intersection Improvements on US 45 from Misso Road to Magnolia Drive, and Mill & Overlay aNoxubee | 34K TON | $191 | $195 | 2 |
| May 8, 2026 | Level & Overlay approximately 8.4 miles on SR 18 from Smith County Line to east of Bay SprJasper | 400 TON | $168 | $240 | 3 |
| Apr 28, 2026 | OGFC Lift on I-55 from the Mississippi State Line to MS 568Pike | 26K TON | $152 | $166 | 2 |
| Apr 28, 2026 | OGFC Lift approximately 5.3 miles on I-20 from MS 18 to US 80 (East Brandon)Rankin | 1.5K TON | $213 | $287 | 3 |
| Apr 10, 2026 | Mill & Overlay approximately 7 miles of US 82 from 1 mile east of Military Road to the AlaLowndes | 18K TON | $198 | $199 | 2 |
| Apr 10, 2026 | Pavement Restoration on US 49 from Madison County Line to 0.8 miles North of Old Highway 4Yazoo | 14K TON | $149 | $158 | 3 |
| Mar 24, 2026 | Mill & Overlay approximately 3 miles of SR 145 from beginning of 4-lane section near CedarPrentiss | 1.1K TON | $229 | $232 | 2 |
| Oct 28, 2025 | Mill, Level & Overlay approximately 4 miles of US 49 from US 11 to beginning of divided seForrest | 11K TON | $163 | $162 | 2 |
| Oct 28, 2025 | Mill & Overlay approximately 6 miles on I-20 from Clinton to MS 18Hinds | 19K TON | $157 | $157 | 3 |
| Sep 16, 2025 | Mill & Overlay approximately 7 miles on I-55 from Byram to McDowell RoadHinds | 33K TON | $135 | $157 | 4 |
| Aug 26, 2025 | Mill & Overlay approximately 4.3 miles of I-55 Carroll Co from the Montgomery County Line Carroll, Montgomery | 20K TON | $178 | – | 1 |
| Aug 26, 2025 | Remove & Replace High Friction Surface Treatment (Bridge Nos. 96.3A & 96.3B) on I-55 northHinds | 375 TON | $325 | $395 | 3 |
| Jul 31, 2025 | Mill & Overlay approximately 14 miles of I-22 in Union County from the junction at SR 30 tUnion, Pontotoc | 43K TON | $185 | $198 | 2 |
| Jul 22, 2025 | Mill & Overlay approximately 3 miles on US 45A from the beginning of the 5-Lane section toClay | 8.0K TON | $197 | $199 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.