The low bidder priced 42" reinforced concrete pipe, class iii at a median $172 per linear foot over the last 12 months (1 contracts), down 14% from the year before and up 27% since 2021.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Construction project, Madison CountyMadison | 16 LF | $172 | $246 | 3 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 96 LF | $200 | $200 | 3 |
| Mar 25, 2025 | Mill & Overlay approximately 7 miles of I-20 from 5.1 miles east of SR 15 to 2.3 miles easNewton | 16 LF | $400 | – | 1 |
| Mar 25, 2025 | Installation of Median Cable Barrier on I-22 from Coldwater River to the Marshall County LDeSoto, Marshall | 80 LF | $400 | $285 | 5 |
| Mar 4, 2025 | Grade Bridge, Pave 2-Lane on SR 19 from 0.25 miles South of SR 492 to Tucker DriveNeshoba | 416 LF | $200 | $167 | 2 |
| Feb 25, 2025 | Safety Improvements on US 49 from the crossover past US 49 at the SR 13 interchange to 100Simpson | 48 LF | $166 | $222 | 5 |
| Dec 5, 2024 | Interchange Reconstruction on I-20 at FlowersWarren | 16 LF | $169 | $235 | 3 |
| Apr 23, 2024 | Grade, Drain, Pave on SR 2 from existing SR 15 to SRTippah | 1.6K LF | $195 | $184 | 2 |
| Mar 26, 2024 | Pavement Restoration of approximately 5 miles of I-55 from SR 24 to US 98 & Roundabout ConPike | 40 LF | $275 | $308 | 2 |
| Aug 1, 2023 | Construction project, Pontotoc CountyPontotoc | 268 LF | $180 | $165 | 2 |
| Sep 28, 2022 | Construction project, Jackson CountyJackson | 88 LF | $135 | $160 | 4 |
| Sep 28, 2022 | Slide Repairs on USHinds | 32 LF | $185 | $188 | 2 |
| Feb 23, 2022 | Construction project, Calhoun CountyCalhoun | 168 LF | $130 | $142 | 5 |
| Nov 23, 2021 | Grade, Drain, Bridge & Pave 4-Lane for approximately 9 miles of the USWashington | 184 LF | $126 | $131 | 2 |
| Aug 24, 2021 | Construction project, Jackson CountyJackson | 72 LF | $145 | – | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.