BidCrew Data / Mississippi / Prices / Guard Rail, Class A, Type 1, Thrie Beam, Transition Section
MDOT pay item · 606-B013

Guard Rail, Class A, Type 1, Thrie Beam, Transition Section: Mississippi winning bid prices

The low bidder priced guard rail, class a, type 1, thrie beam, transition section at a median $50.33 per linear foot over the last 12 months (4 contracts), up 5% from the year before and up 31% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$50.33
4 contracts
Median, prior 12 months
$48.00
3 contracts
Median, 2020
$38.50
2 contracts
Winner vs. field
level with
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$0$50$100$1502020202120222023202420252026*$50.33
Price vs. quantityEvery winning price since 2020 (log scale)
$0$50$100$150$20010100
Does quantity matter?Median winning price by quantity band
$0$25$50$75$100$95.00≤25$48.5025–45$51.5045–97$51.65>97

The last 18 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Oct 27, 2026Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery116 LF$51.65–1
Jun 5, 2026Mill & Overlay approximately 10.1 miles of MS 178 from the Marshall County Line to the UniBenton56 LF$49.00$50.783
Apr 28, 2026OGFC Lift approximately 5.3 miles on I-20 from MS 18 to US 80 (East Brandon)Rankin30 LF$56.00$56.003
Apr 10, 2026Asphalt Overlay approximately 12 miles SR 28 from Jefferson County Line to 1 mile East of Copiah100 LF$37.05$35.636
Aug 26, 2025Mill & Overlay approximately 4.3 miles of I-55 Carroll Co from the Montgomery County Line Carroll, Montgomery118 LF$48.00–1
Mar 25, 2025Mill & Overlay approximately 7 miles of I-20 from 5.1 miles east of SR 15 to 2.3 miles easNewton50 LF$20.70–1
Jan 28, 2025Widen & Overlay approximately 11 miles of SR 28 from 2.4 miles east of Dennis Cross Road tJefferson25 LF$53.00$53.002
May 29, 2024Overlay approximatelyClarke50 LF$54.00–1
Nov 28, 2023Construction project, Warren CountyWarren25 LF$70.00$65.004
Oct 24, 2023Overlay approximatelyRankin15 LF$110$1103
Jan 25, 2023Overlay approximately 1.4 miles of SR 822 (Old US 80) from the BOSM to East of SRWarren125 LF$55.00–1
Aug 23, 2022Overlay project, Hinds & Rankin CountyHinds, Rankin88 LF$85.00–1
Jan 25, 2022Overlay approximatelyYazoo4 LF$135$1352
Jan 25, 2022Overlay approximately 7.5 miles on USLauderdale13 LF$165–1
Sep 28, 2021Overlay approximatelyLincoln188 LF$54.00$54.002
Jun 22, 2021Overlay approximatelyHinds25 LF$95.00$95.002
Feb 25, 2020Overlay approximatelyNewton40 LF$41.00–1
Jan 28, 2020Overlay approximatelyLauderdale13 LF$36.00–1

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.