BidCrew Data
BidCrew Data / Mississippi / Prices / Temporary Portable Rumble Strips
MDOT pay item · 907-619-B001

Temporary Portable Rumble Strips: Mississippi winning bid prices

The low bidder priced temporary portable rumble strips at a median $122 per linear foot over the last 12 months (38 contracts), down 4% from the year before and down 41% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$122
38 contracts
Median, prior 12 months
$127
37 contracts
Median, 2020
$207
48 contracts
Winner vs. field
level with
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$50$100$150$200$2502020202120222023202420252026*$123
Price vs. quantityEvery winning price since 2020 (log scale)
$0$100$200$300100
Does quantity matter?Median winning price by quantity band
$0$50$100$150$200$179≤66$0.00066–66$95.8566–72$145>72

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Oct 27, 2026Overlay approximately 7 miles of MS 48 from SR 24 to Magnolia Progress RoadPike132 LF$166$1073
Oct 27, 2026Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson72 LF$76.70–1
Sep 22, 2026Mill & Overlay approximately 2.5 miles of US 49 from SR 1 to the Isle of Capri ParkwayCoahoma66 LF$275–1
Aug 25, 2026Overlay approximately 3.6 miles of MS 550 from SR 28 to the Lincoln County LineJefferson66 LF$281$2914
Aug 25, 2026Overlay approximately 2.9 miles of MS 354 from the junction of MS 15 to the end of state mTippah66 LF$265$2653
Aug 25, 2026Mill & Overlay approximately 11 miles of US 61 from 0.5 miles North of US 80/SR27 IntersecWarren66 LF$235$2353
Jul 28, 2026Thin Lift Overlay approximately 10.2 miles of MS 467 from beginning of maintenance to SoutHinds66 LF$115$2603
Jul 28, 2026Micro-Surface approximately 14 miles of SR 512 & SR 513Clarke66 LF$123$1962
Jun 30, 2026Thin Lift Overlay approximately 10.1 miles of MS 35 from 4 Forks to the Grenada County LinCarroll66 LF$120$2003
Jun 23, 2026Widen & Overlay approximately 2 miles of SR 26 from the east end of the Pearl River BridgePearl River66 LF$1.00–1
Jun 23, 2026Overlay approximately 8.5 miles of MS 587 from the Marion County Line to the Northern ErviLawrence132 LF$145$1154
Jun 23, 2026Mill & Overlay approximately 3.87 miles of SR 149 from US 49S to US 49NStone66 LF$36.00$18.502
Jun 5, 2026Mill & Overlay approximately 10.1 miles of MS 178 from the Marshall County Line to the UniBenton66 LF$260$2603
Jun 5, 2026Mill & Overlay approximately 2 miles of SR 24 from Lower Woodville Road to US 61Wilkinson66 LF$120$2372
Jun 5, 2026Mill & Overlay approximately 9 miles of SR 25 from US 45A to US 45Monroe66 LF$200$1442
Jun 5, 2026Overlay approximately 8 miles of SR 27 from the Louisiana State Line to High School DriveWalthall132 LF$91.00$91.003
Jun 5, 2026Mill & Overlay approximately 3 miles of MS 16/149 from MS 3 to US 49Yazoo66 LF$97.45–1
May 27, 2026Scrub Seal & Overlay approximately 12 miles of MS 172 from the junction of US 72 to the JuTishomingo66 LF$260$2602
May 27, 2026Mill & Overlay approximately 7 miles of SR 4 from east of Church Street to west of the JunPrentiss66 LF$260$2602
May 27, 2026Mill & Overlay 10 miles of SR 371 from the Mantachie Corp. limit to the Prentiss County LiItawamba66 LF$260$2603

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.

Price this item against every competitor