The low bidder priced temporary portable rumble strips at a median $122 per linear foot over the last 12 months (38 contracts), down 4% from the year before and down 41% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Overlay approximately 7 miles of MS 48 from SR 24 to Magnolia Progress RoadPike | 132 LF | $166 | $107 | 3 |
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 72 LF | $76.70 | – | 1 |
| Sep 22, 2026 | Mill & Overlay approximately 2.5 miles of US 49 from SR 1 to the Isle of Capri ParkwayCoahoma | 66 LF | $275 | – | 1 |
| Aug 25, 2026 | Overlay approximately 3.6 miles of MS 550 from SR 28 to the Lincoln County LineJefferson | 66 LF | $281 | $291 | 4 |
| Aug 25, 2026 | Overlay approximately 2.9 miles of MS 354 from the junction of MS 15 to the end of state mTippah | 66 LF | $265 | $265 | 3 |
| Aug 25, 2026 | Mill & Overlay approximately 11 miles of US 61 from 0.5 miles North of US 80/SR27 IntersecWarren | 66 LF | $235 | $235 | 3 |
| Jul 28, 2026 | Thin Lift Overlay approximately 10.2 miles of MS 467 from beginning of maintenance to SoutHinds | 66 LF | $115 | $260 | 3 |
| Jul 28, 2026 | Micro-Surface approximately 14 miles of SR 512 & SR 513Clarke | 66 LF | $123 | $196 | 2 |
| Jun 30, 2026 | Thin Lift Overlay approximately 10.1 miles of MS 35 from 4 Forks to the Grenada County LinCarroll | 66 LF | $120 | $200 | 3 |
| Jun 23, 2026 | Widen & Overlay approximately 2 miles of SR 26 from the east end of the Pearl River BridgePearl River | 66 LF | $1.00 | – | 1 |
| Jun 23, 2026 | Overlay approximately 8.5 miles of MS 587 from the Marion County Line to the Northern ErviLawrence | 132 LF | $145 | $115 | 4 |
| Jun 23, 2026 | Mill & Overlay approximately 3.87 miles of SR 149 from US 49S to US 49NStone | 66 LF | $36.00 | $18.50 | 2 |
| Jun 5, 2026 | Mill & Overlay approximately 10.1 miles of MS 178 from the Marshall County Line to the UniBenton | 66 LF | $260 | $260 | 3 |
| Jun 5, 2026 | Mill & Overlay approximately 2 miles of SR 24 from Lower Woodville Road to US 61Wilkinson | 66 LF | $120 | $237 | 2 |
| Jun 5, 2026 | Mill & Overlay approximately 9 miles of SR 25 from US 45A to US 45Monroe | 66 LF | $200 | $144 | 2 |
| Jun 5, 2026 | Overlay approximately 8 miles of SR 27 from the Louisiana State Line to High School DriveWalthall | 132 LF | $91.00 | $91.00 | 3 |
| Jun 5, 2026 | Mill & Overlay approximately 3 miles of MS 16/149 from MS 3 to US 49Yazoo | 66 LF | $97.45 | – | 1 |
| May 27, 2026 | Scrub Seal & Overlay approximately 12 miles of MS 172 from the junction of US 72 to the JuTishomingo | 66 LF | $260 | $260 | 2 |
| May 27, 2026 | Mill & Overlay approximately 7 miles of SR 4 from east of Church Street to west of the JunPrentiss | 66 LF | $260 | $260 | 2 |
| May 27, 2026 | Mill & Overlay 10 miles of SR 371 from the Mantachie Corp. limit to the Prentiss County LiItawamba | 66 LF | $260 | $260 | 3 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.