The low bidder priced electric cable, aerial supported in conduit, imsa 20-1, awg 14, 8 conductor at a median $5.15 per linear foot over the last 12 months (3 contracts), up 5% from the year before and up 106% since 2021.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Construction project, Madison CountyMadison | 380 LF | $5.25 | $3.76 | 3 |
| Jul 28, 2026 | Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest | 2.3K LF | $5.15 | $5.15 | 3 |
| Jul 28, 2026 | Traffic Signal and Interchange Modifications on US 45 & US 278Lee | 215 LF | $3.00 | $3.70 | 5 |
| Jun 24, 2025 | Directional Median Installation on US 49 at Siloam Road and a Traffic Signal at SR 149Simpson | 164 LF | $5.85 | $4.50 | 2 |
| Apr 22, 2025 | Intersection Improvements on US 49 from Desoto Park Road to 500' south of East Wortham RoaHarrison | 230 LF | $4.00 | $4.75 | 2 |
| May 29, 2024 | Traffic Signal Installation on US 49W at SRSunflower | 309 LF | $3.00 | $3.75 | 2 |
| Jan 31, 2024 | Intersection Improvements on USDeSoto | 300 LF | $2.30 | $1.10 | 4 |
| Jan 24, 2024 | Intersection Improvements at SRSmith | 305 LF | $4.20 | $4.15 | 5 |
| Jan 24, 2024 | Construction project, Harrison CountyHarrison | 1.0K LF | $4.64 | – | 1 |
| Dec 5, 2023 | Bridge Replacement on US 11 at Hobolochitto Creek in Picayune (Bridge No. 11.3), known as Pearl River | 450 LF | $3.60 | $4.75 | 5 |
| Dec 5, 2023 | Add 2 Lanes on US 49 from O'Neal Road to north of School Road, known as Federal Aid ProjecHarrison | 740 LF | $4.21 | $4.11 | 2 |
| Aug 22, 2023 | Intersection Improvements on USMadison | 254 LF | $3.85 | $4.55 | 3 |
| Aug 1, 2023 | Construction project, Pontotoc CountyPontotoc | 299 LF | $3.00 | $3.00 | 2 |
| Jan 25, 2023 | Construction project, Newton CountyNewton | 252 LF | $3.60 | $4.50 | 3 |
| Oct 25, 2022 | Intersection Improvements on SR 3Phillips Contracting Co., Inc. - Columbus, MS J. M. DuncaDeSoto | 349 LF | $1.80 | $1.85 | 4 |
| Oct 25, 2022 | Construction project, Harrison CountyHarrison | 4.6K LF | $3.70 | $3.70 | 3 |
| Oct 25, 2022 | Grade, Drain, Bridge & Pave 4-Lane approximately 9 miles of SR 57 from I-10 to Vancleave, Jackson | 244 LF | $4.50 | $4.90 | 2 |
| Feb 23, 2022 | Construction project, Hinds CountyHinds | 230 LF | $5.00 | $4.50 | 2 |
| Jan 25, 2022 | Construction project, Hancock CountyHancock | 9.0K LF | $3.30 | $2.88 | 4 |
| Apr 27, 2021 | Intersection Improvements on US 84 at Reservoir Road / Magnolia Hill Road & SR 184Wayne | 343 LF | $2.50 | – | 4 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.