BidCrew Data / Mississippi / Prices / Removal of Guard Rail
MDOT pay item · 202-B136

Removal of Guard Rail: Mississippi winning bid prices

The low bidder priced removal of guard rail at a median $8.55 per linear foot over the last 12 months (20 contracts), up 18% from the year before and up 19% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$8.55
20 contracts
Median, prior 12 months
$7.25
18 contracts
Median, 2020
$7.20
6 contracts
Winner vs. field
level with
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$4$6$8$10$12$142020202120222023202420252026*$8.55
Price vs. quantityEvery winning price since 2020 (log scale)
$5$10$15$201001.0K10K
Does quantity matter?Median winning price by quantity band
$0$2.5$5$7.5$10$10.00≤600$8.75600–1.5K$8.001.5K–3.2K$9.00>3.2K

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Oct 27, 2026Fog Seal approximately 6.2 miles of I-59 from 0.8 mile north of CR 39 to the Jasper/ClarkeJasper, Clarke7.5K LF$6.25$6.882
Oct 27, 2026Fog Seal approximately 5 miles of I-59 from the Forrest County Line to the Forrest County Lamar, Forrest1.2K LF$6.00–1
Oct 27, 2026Mill & Overlay approximately 13.7 miles of I-59 from 0.5 miles north of the McNeil Exit toPearl River14K LF$6.00–1
Oct 27, 2026Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson1.1K LF$5.72–1
Sep 22, 2026Bridge Repair on SR 348 over Kings Creek (Bridge No. 0.9)Union25 LF$59.00$60.006
Aug 25, 2026Mill & Overlay approximately 0.5 miles East of US 61Washington316 LF$10.40–1
Aug 25, 2026Mill & Overlay approximately 11 miles of US 61 from 0.5 miles North of US 80/SR27 IntersecWarren3.0K LF$9.33$9.333
Jul 28, 2026Micro-Surface approximately 14 miles of SR 512 & SR 513Clarke4.3K LF$10.70$11.762
Jul 28, 2026Widening on I-10 at MS 605 WB RampHarrison115 LF$11.00$11.003
Jun 23, 2026Widen & Overlay approximately 2 miles of SR 26 from the east end of the Pearl River BridgePearl River4.4K LF$11.00–1
Jun 23, 2026Overlay and OGFC Lift from east of the Shorecrest Road Overpass to approximately 0.9 mile Harrison7.1K LF$7.00$7.502
Jun 23, 2026Thin Lift Overlay approximately 8.5 miles of SR 514 from SR 513 to SR 145, approximately 0Clarke, Jasper2.6K LF$11.00$8.003
Jun 5, 2026Mill & Overlay approximately 3 miles of MS 16/149 from MS 3 to US 49Yazoo575 LF$8.30–1
May 8, 2026Scrub Seal and Overlay approximately 8 miles of SR 12 from Black Creek in Lexington to EllHolmes2.1K LF$8.00$8.142
Apr 28, 2026Overlay approximately 14.5 miles on US 98 from 1.05 miles east of SR 29 to the Greene CounPerry4.4K LF$8.80$9.282
Apr 10, 2026Asphalt Overlay approximately 12 miles SR 28 from Jefferson County Line to 1 mile East of Copiah1.8K LF$11.65$11.206
Feb 24, 2026Widen & Overlay approximately 10 miles of SR 149 from 0.3 Miles South of SR 14 to US 49WHumphreys225 LF$8.30$8.152
Feb 24, 2026Overlay approximately 5.3 miles of SR 27 from 0.2 mile south of Old Highway 27 to 0.35 milCopiah1.2K LF$5.75$5.965
Oct 28, 2025Bridge Repair on Old West Point Road over US 82 (Bridge No. 160.3)Lowndes600 LF$5.50$5.884
Oct 28, 2025Mill, Level & Overlay approximately 4 miles of US 49 from US 11 to beginning of divided seForrest850 LF$10.25$11.132

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.