The low bidder priced unclassified excavation, fm, ah at a median $13.20 per cubic yard over the last 12 months (21 contracts), down 29% from the year before and up 96% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery | 733 CY | $20.00 | – | 1 |
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 11K CY | $20.45 | $30.78 | 3 |
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 47K CY | $8.00 | $10.00 | 4 |
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 10K CY | $6.79 | – | 1 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 90K CY | $11.00 | $20.65 | 6 |
| Sep 22, 2026 | Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha | 8.7K CY | $12.00 | – | 4 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 7.3K CY | $17.95 | $16.50 | 3 |
| Sep 1, 2026 | Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie | 22K CY | $5.00 | $7.21 | 6 |
| Jul 28, 2026 | Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest | 2.9K CY | $18.00 | $23.90 | 3 |
| Jul 28, 2026 | Widening on I-10 at MS 605 WB RampHarrison | 137 CY | $15.00 | $22.77 | 3 |
| Jun 23, 2026 | Roundabout on US 51 at Green T RoadDeSoto | 5.2K CY | $15.00 | $19.00 | 6 |
| May 27, 2026 | Bridge Replacement on SR 427 (Bridge No. 4.4) between SR 488 & SR 16Leake | 1.4K CY | $8.85 | $13.82 | 8 |
| May 27, 2026 | Bridge Replacement on SR 15 over Cypress Branch on Bridge No. 15.7Harrison | 155 CY | $11.50 | $15.00 | 5 |
| May 27, 2026 | Restricted Crossing U-Turn (RCUT) on US 84 at MS 33Franklin | 9.5K CY | $12.00 | $15.13 | 2 |
| May 8, 2026 | Level & Overlay approximately 8.4 miles on SR 18 from Smith County Line to east of Bay SprJasper | 700 CY | $16.00 | $16.00 | 3 |
| Apr 28, 2026 | Restricted Crossing U-Turn (RCUT) on US 278 at CR 217/405Lafayette | 4.8K CY | $19.10 | $19.10 | 5 |
| Apr 28, 2026 | I-10 Jackson County Welcome CenterJackson | 8.8K CY | $13.20 | $12.35 | 4 |
| Feb 3, 2026 | Slide Repair on US 61 Southbound across from Fire Tower RoadAdams | 776 CY | $7.00 | $9.00 | 4 |
| Nov 25, 2025 | Bridge Replacement on SR 481 between SR 902 & SR 35 (Bridge Nos. 2.1 & 2.3)Smith | 3.7K CY | $7.10 | $8.50 | 7 |
| Nov 25, 2025 | Safety Improvements on US 84 at MS 184 & at MS 588 in CollinsCovington | 3.0K CY | $20.00 | $21.30 | 4 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.