Unclassified Excavation, FM, AH: Mississippi winning bid prices

The low bidder priced unclassified excavation, fm, ah at a median $13.20 per cubic yard over the last 12 months (21 contracts), down 29% from the year before and up 96% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$13.20
21 contracts
Median, prior 12 months
$18.50
18 contracts
Median, 2020
$6.75
11 contracts
Winner vs. field
8% below
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$0$5$10$15$20$252020202120222023202420252026*$12.60
Price vs. quantityEvery winning price since 2020 (log scale)
$0$20$40$60101001.0K10K100K1.0M
Does quantity matter?Median winning price by quantity band
$0$5$10$15$20$16.50≤1.4K$11.471.4K–6.0K$9.256.0K–18K$6.80>18K

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Oct 27, 2026Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery733 CY$20.00–1
Oct 27, 2026Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren11K CY$20.45$30.783
Oct 27, 2026Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin47K CY$8.00$10.004
Oct 27, 2026Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson10K CY$6.79–1
Sep 29, 2026Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin90K CY$11.00$20.656
Sep 22, 2026Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha8.7K CY$12.00–4
Sep 1, 2026Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike7.3K CY$17.95$16.503
Sep 1, 2026Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie22K CY$5.00$7.216
Jul 28, 2026Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest2.9K CY$18.00$23.903
Jul 28, 2026Widening on I-10 at MS 605 WB RampHarrison137 CY$15.00$22.773
Jun 23, 2026Roundabout on US 51 at Green T RoadDeSoto5.2K CY$15.00$19.006
May 27, 2026Bridge Replacement on SR 427 (Bridge No. 4.4) between SR 488 & SR 16Leake1.4K CY$8.85$13.828
May 27, 2026Bridge Replacement on SR 15 over Cypress Branch on Bridge No. 15.7Harrison155 CY$11.50$15.005
May 27, 2026Restricted Crossing U-Turn (RCUT) on US 84 at MS 33Franklin9.5K CY$12.00$15.132
May 8, 2026Level & Overlay approximately 8.4 miles on SR 18 from Smith County Line to east of Bay SprJasper700 CY$16.00$16.003
Apr 28, 2026Restricted Crossing U-Turn (RCUT) on US 278 at CR 217/405Lafayette4.8K CY$19.10$19.105
Apr 28, 2026I-10 Jackson County Welcome CenterJackson8.8K CY$13.20$12.354
Feb 3, 2026Slide Repair on US 61 Southbound across from Fire Tower RoadAdams776 CY$7.00$9.004
Nov 25, 2025Bridge Replacement on SR 481 between SR 902 & SR 35 (Bridge Nos. 2.1 & 2.3)Smith3.7K CY$7.10$8.507
Nov 25, 2025Safety Improvements on US 84 at MS 184 & at MS 588 in CollinsCovington3.0K CY$20.00$21.304

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.

Price this item against every competitor

BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.

Request access