The low bidder priced structure excavation at a median $29.38 per cubic yard over the last 12 months (24 contracts), down 16% from the year before and up 18% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery | 9 CY | $33.00 | – | 1 |
| Oct 27, 2026 | Construction project, Madison CountyMadison | 2.9K CY | $35.70 | $40.00 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 291 CY | $23.50 | $27.06 | 3 |
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 569 CY | $1.00 | $21.93 | 4 |
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 583 CY | $9.51 | – | 1 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 3.9K CY | $6.50 | $28.13 | 6 |
| Sep 22, 2026 | Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha | 154 CY | $50.00 | – | 4 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 3.0K CY | $25.75 | $24.50 | 3 |
| Sep 1, 2026 | Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie | 270 CY | $20.00 | $20.50 | 6 |
| Aug 25, 2026 | Mill & Overlay approximately 11 miles of US 61 from 0.5 miles North of US 80/SR27 IntersecWarren | 25 CY | $55.00 | $68.00 | 3 |
| Jul 28, 2026 | Thin Lift Overlay approximately 10.2 miles of MS 467 from beginning of maintenance to SoutHinds | 692 CY | $65.00 | $65.00 | 3 |
| Jul 28, 2026 | Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest | 65 CY | $42.00 | $42.00 | 3 |
| Jun 23, 2026 | Roundabout on US 51 at Green T RoadDeSoto | 543 CY | $25.00 | $27.50 | 6 |
| May 27, 2026 | Traffic Signal Improvements on MS 16 at Van Buren, and Mill & Overlay approximately 6 mileLeake | 240 CY | $50.00 | $25.15 | 4 |
| May 27, 2026 | Overlay approximately 11.4 miles of SR 15 from Ovett-Scarbrough Road to south of Tuckers CJones | 2 CY | $150 | $146 | 2 |
| May 27, 2026 | Bridge Replacement on SR 15 over Cypress Branch on Bridge No. 15.7Harrison | 660 CY | $9.50 | $18.00 | 5 |
| May 27, 2026 | Restricted Crossing U-Turn (RCUT) on US 84 at MS 33Franklin | 173 CY | $1.00 | $28.00 | 2 |
| May 27, 2026 | Intersection Improvements on US 45 from Misso Road to Magnolia Drive, and Mill & Overlay aNoxubee | 28 CY | $100 | $103 | 2 |
| May 8, 2026 | Level & Overlay approximately 8.4 miles on SR 18 from Smith County Line to east of Bay SprJasper | 54 CY | $19.00 | $19.00 | 3 |
| Apr 28, 2026 | Restricted Crossing U-Turn (RCUT) on US 278 at CR 217/405Lafayette | 280 CY | $25.00 | $25.00 | 5 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.