The low bidder priced granular material, lvm, class 3, group d at a median $48.50 per cubic yard over the last 12 months (6 contracts), down 12% from the year before and up 62% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Sep 22, 2026 | Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha | 7.1K CY | $47.00 | – | 4 |
| Jun 5, 2026 | Mill & Overlay approximately 9 miles of SR 25 from US 45A to US 45Monroe | 1.5K CY | $50.00 | $50.00 | 2 |
| May 27, 2026 | Mill & Overlay 10 miles of SR 371 from the Mantachie Corp. limit to the Prentiss County LiItawamba | 3.8K CY | $45.00 | $45.00 | 3 |
| Apr 10, 2026 | Mill & Overlay approximately 7 miles of US 82 from 1 mile east of Military Road to the AlaLowndes | 3.9K CY | $60.00 | $59.00 | 2 |
| Feb 24, 2026 | Mill & Overlay approximately 9 miles of SR 397 from the Kemper County Line to Robertson RoWinston | 3.5K CY | $70.00 | $65.00 | 4 |
| Nov 25, 2025 | Mill & Overlay approximately 10 miles on US 45A from the Chickasaw County Line to the Lee Monroe | 22K CY | $35.00 | $46.00 | 4 |
| Sep 23, 2025 | Mill & Overlay approximately 1.1 miles of MS 370 from US 45 to MS 145Lee | 900 CY | $55.00 | $55.00 | 3 |
| Aug 26, 2025 | Mill & Overlay approximately 3.5 miles of US 45 from the beginning of the 4-Lane divided sMonroe | 3.0K CY | $40.00 | $47.00 | 3 |
| Jul 22, 2025 | Mill & Overlay approximately 10 miles of SR 389 from US 82 to the Clay County LineOktibbeha | 6.5K CY | $61.00 | $61.47 | 2 |
| Jul 22, 2025 | Mill & Overlay approximately 3 miles on US 45A from the beginning of the 5-Lane section toClay | 75 CY | $201 | $150 | 2 |
| Jul 22, 2025 | Mill & Overlay approximately 5.5 miles of SR 25 from 1.3 miles north of Platsburg Road to Winston | 6.0K CY | $45.00 | $65.75 | 2 |
| May 28, 2025 | Mill & Overlay approximately 3 miles of SR 178 from North Access Road to Old SR 25Itawamba | 800 CY | $55.00 | $85.00 | 4 |
| Nov 26, 2024 | Mill & Overlay approximately 15 miles of US 45A from the Noxubee County Line to the Clay CLowndes | 13K CY | $45.00 | $45.00 | 3 |
| Jul 23, 2024 | Overlay approximatelyChickasaw | 7.8K CY | $42.00 | $43.50 | 4 |
| Jun 25, 2024 | Overlay approximatelyPontotoc | 5.0K CY | $44.00 | $47.15 | 4 |
| May 29, 2024 | Overlay approximatelyLowndes | 700 CY | $50.00 | $60.00 | 3 |
| Apr 23, 2024 | Mill & Overlay approximately 9 miles of SR 14 from 6 miles west of SR 15 to 3 miles east oWinston | 4.0K CY | $70.00 | $70.00 | 3 |
| Jul 25, 2023 | Mill & Overlay approximately 9.5 miles of SR 389 from the Clay County Line to SRChickasaw | 4.0K CY | $67.00 | $67.50 | 2 |
| Jun 27, 2023 | Safety Improvements on approximatelyLowndes | 6.7K CY | $65.00 | $65.00 | 2 |
| Apr 25, 2023 | Overlay approximatelyCalhoun | 6.5K CY | $70.00 | $70.00 | 3 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.