The low bidder priced bituminous tack coat at a median $4.29 per gallon over the last 12 months (9 contracts), up 8% from the year before and up 2% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | OGFC Lift on I-59 from US 45 to approximately 0.248 miles north of the Russell InterchangeLauderdale | 14K GAL | $4.44 | – | 1 |
| Oct 27, 2026 | Fog Seal approximately 6.2 miles of I-59 from 0.8 mile north of CR 39 to the Jasper/ClarkeJasper, Clarke | 23K GAL | $4.29 | $5.00 | 2 |
| Oct 27, 2026 | Fog Seal approximately 5 miles of I-59 from the Forrest County Line to the Forrest County Lamar, Forrest | 16K GAL | $4.35 | – | 1 |
| Oct 27, 2026 | Mill & Overlay approximately 13.7 miles of I-59 from 0.5 miles north of the McNeil Exit toPearl River | 33K GAL | $8.00 | – | 1 |
| Oct 27, 2026 | Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery | 24K GAL | $4.00 | – | 1 |
| Oct 27, 2026 | Construction project, Madison CountyMadison | 39K GAL | $4.40 | $4.50 | 3 |
| Jun 23, 2026 | Overlay and OGFC Lift from east of the Shorecrest Road Overpass to approximately 0.9 mile Harrison | 22K GAL | $4.00 | $5.00 | 2 |
| Apr 28, 2026 | OGFC Lift on I-55 from the Mississippi State Line to MS 568Pike | 22K GAL | $4.05 | $3.90 | 2 |
| Apr 28, 2026 | OGFC Lift approximately 5.3 miles on I-20 from MS 18 to US 80 (East Brandon)Rankin | 21K GAL | $3.77 | $3.79 | 3 |
| Aug 26, 2025 | Mill & Overlay approximately 4.3 miles of I-55 Carroll Co from the Montgomery County Line Carroll, Montgomery | 23K GAL | $4.25 | – | 1 |
| Jul 31, 2025 | Mill & Overlay approximately 14 miles of I-22 in Union County from the junction at SR 30 tUnion, Pontotoc | 32K GAL | $4.00 | $4.75 | 2 |
| May 28, 2025 | Remove & Replace OGFC Lift on approximately 2 miles of I-220 from the Hinds County Line toMadison, Hinds | 39K GAL | $3.29 | $3.52 | 2 |
| Mar 25, 2025 | Mill & Overlay approximately 4 miles of I-69 from 0.95 miles north of I-269 to 0. 51 2 milDeSoto | 12K GAL | $3.75 | $3.63 | 2 |
| Mar 25, 2025 | Mill & Overlay approximately 7 miles of I-20 from 5.1 miles east of SR 15 to 2.3 miles easNewton | 24K GAL | $3.98 | – | 1 |
| Feb 25, 2025 | Remove & Replace approximately 13 miles of OGFC on I-20 from East Brandon to the Scott CouRankin | 47K GAL | $3.56 | $3.56 | 3 |
| Feb 25, 2025 | Remove & Replace approximately 17 miles of OGFC on I-10 from the Pearl River Bridge to wesHancock | 67K GAL | $4.50 | – | 1 |
| Nov 26, 2024 | Mill & Overlay approximately 5 miles of I-22 from the Union County Line to the Belden ExitLee, Pontotoc | 4.0K GAL | $6.00 | $5.50 | 3 |
| Oct 22, 2024 | Remove and Replace OGFC on approximately 20 miles of I-59 from North of Rocky Creek to theJones | 65K GAL | $5.30 | – | 1 |
| Oct 22, 2024 | Remove & Replace OGFC on approximately 9 miles of I-55 from US 98W to the bridge south of Lincoln, Pike | 20K GAL | $4.25 | – | 1 |
| Oct 22, 2024 | Bridge Repair on I-20 over the Big Black River & Reliefs (Bridge Nos. 17.3A, 17.3B, 17.7A,Hinds, Warren | 730 GAL | $3.90 | $5.55 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.