BidCrew Data
BidCrew Data / Mississippi / Prices / 19-mm, ST, Asphalt Pavement
MDOT pay item · 403-A006 / 907-403-A006

19-mm, ST, Asphalt Pavement: Mississippi winning bid prices

The low bidder priced 19-mm, st, asphalt pavement at a median $160 per ton over the last 12 months (33 contracts), down 10% from the year before and up 30% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$160
33 contracts
Median, prior 12 months
$178
36 contracts
Median, 2020
$123
28 contracts
Winner vs. field
2% below
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$100$150$200$2502020202120222023202420252026*$163
Price vs. quantityEvery winning price since 2020 (log scale)
$0$100$200$300$400$500101001.0K10K
Does quantity matter?Median winning price by quantity band
$0$50$100$150$200$199≤242$179242–700$158700–2.0K$146>2.0K

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Oct 27, 2026Overlay approximately 7 miles of MS 48 from SR 24 to Magnolia Progress RoadPike183 TON$173$1733
Oct 27, 2026Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery125 TON$422–1
Oct 27, 2026Construction project, Madison CountyMadison35K TON$140$1403
Oct 27, 2026Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren1.8K TON$192$2003
Oct 27, 2026Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin4.5K TON$108$1284
Oct 27, 2026Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson473 TON$158–1
Sep 29, 2026Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin24K TON$132$1506
Sep 1, 2026Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie2.7K TON$168$1726
Aug 25, 2026Bridge Replacement on SR 486 (Bridge No. 1.0)Neshoba130 TON$250$2664
Aug 25, 2026SR 145 Bridge Replacement (Bridge No. 210.8), Known as Federal Aid Project No. STBG-0053-0Lee489 TON$178$2018
Jul 28, 2026Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest4.3K TON$148$1623
Jul 28, 2026Widening on I-10 at MS 605 WB RampHarrison839 TON$226$2153
Jun 30, 2026Thin Lift Overlay approximately 10.1 miles of MS 35 from 4 Forks to the Grenada County LinCarroll225 TON$197$2503
Jun 23, 2026Overlay approximately 8.5 miles of MS 587 from the Marion County Line to the Northern ErviLawrence671 TON$152$1804
Jun 23, 2026Thin Lift Overlay approximately 8.5 miles of SR 514 from SR 513 to SR 145, approximately 0Clarke, Jasper3.4K TON$148$1523
Jun 5, 2026Mill & Overlay approximately 10.1 miles of MS 178 from the Marshall County Line to the UniBenton1.4K TON$183$1833
Jun 5, 2026Overlay approximately 14.3 miles of MS Highway 7 beginning at the Lafayette County Line goMarshall2.3K TON$147–1
May 27, 2026Widening of US 51 from Glenwild to North StreetGrenada275 TON$220$2482
May 27, 2026Overlay approximately 11.4 miles of SR 15 from Ovett-Scarbrough Road to south of Tuckers CJones29 TON$200$2382
May 27, 2026Bridge Replacement on SR 15 over Cypress Branch on Bridge No. 15.7Harrison879 TON$149$1465

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.