The low bidder priced ultra thin asphalt pavement at a median $128 per ton over the last 12 months (13 contracts), down 2% from the year before and up 65% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Aug 25, 2026 | Overlay approximately 3.6 miles of MS 550 from SR 28 to the Lincoln County LineJefferson | 2.5K TON | $120 | $141 | 4 |
| Aug 21, 2026 | Emergency Slope Repair & Pipe Cleanout on SR 26George, Perry | 5.7K TON | $127 | $149 | 3 |
| Jul 28, 2026 | Thin Lift Overlay approximately 10.2 miles of MS 467 from beginning of maintenance to SoutHinds | 7.3K TON | $130 | $134 | 3 |
| Jun 30, 2026 | Thin Lift Overlay approximately 10.1 miles of MS 35 from 4 Forks to the Grenada County LinCarroll | 9.9K TON | $150 | $150 | 3 |
| Jun 23, 2026 | Thin Lift Overlay approximately 8.5 miles of SR 514 from SR 513 to SR 145, approximately 0Clarke, Jasper | 20K TON | $139 | $141 | 3 |
| May 27, 2026 | Thin Lift Overlay of MS 16 from Thompson Drive to the Intersection of MS 15Neshoba | 12K TON | $134 | $151 | 5 |
| May 27, 2026 | Buildings project, George CountyGeorge | 10K TON | $145 | – | 1 |
| May 27, 2026 | Overlay approximately 11.4 miles of SR 15 from Ovett-Scarbrough Road to south of Tuckers CJones | 18K TON | $128 | $135 | 2 |
| May 8, 2026 | Level & Overlay approximately 8.4 miles on SR 18 from Smith County Line to east of Bay SprJasper | 8.9K TON | $105 | $140 | 3 |
| Apr 28, 2026 | Ultra-Thin Overlay & Safety Improvements on approximately 8 miles of existing SR 482 from Neshoba | 4.5K TON | $154 | $157 | 4 |
| Apr 28, 2026 | Overlay approximately 14.5 miles on US 98 from 1.05 miles east of SR 29 to the Greene CounPerry | 23K TON | $106 | $105 | 2 |
| Feb 24, 2026 | Mill & Overlay approximately 3.4 miles of SR 854 from SR 39 to the Naval Air StationLauderdale | 6.3K TON | $125 | $166 | 3 |
| Oct 28, 2025 | Overlay approximately 6 miles on SR 28 from Mize to Taylorsville, known as Project No. SP-Smith | 4.1K TON | $128 | $126 | 4 |
| Sep 23, 2025 | Thin Lift approximately 2.3 miles of SR 555 from the end of the 4-Lane section to the end Adams | 1.6K TON | $146 | $146 | 2 |
| Sep 23, 2025 | Thin Lift approximately 2.3 miles of SR 555 from the end of the 4-Lane section to the end Adams | 1.6K TON | $173 | $182 | 2 |
| Aug 26, 2025 | Level & Overlay approximately 12.5 miles of SR 528 from the west end of the Talahalla CreeJasper | 20K TON | $139 | $139 | 3 |
| Jul 22, 2025 | Thin Lift & Overlay approximately 16 miles of SR 43 from just south of Wheats Curve to thePearl River | 13K TON | $122 | $141 | 2 |
| May 28, 2025 | Overlay approximately 7 miles of SR 15 from the intersection SR 67 North, known as FederalHarrison | 10.0K TON | $117 | $129 | 2 |
| Dec 5, 2024 | Overlay approximately 7 miles of SR 15 from the Stone County Line south 7.4 miles, known aHarrison, Stone | 25K TON | $119 | $124 | 2 |
| Sep 25, 2024 | Overlay approximatelyPerry | 16K TON | $106 | $124 | 3 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.