The low bidder priced guard rail, terminal end section at a median $4,155 per each over the last 12 months (10 contracts), up 7% from the year before and up 53% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Construction project, Madison CountyMadison | 5 EA | $4,211 | $4,211 | 3 |
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 1 EA | $3,950 | $4,495 | 4 |
| Sep 22, 2026 | Bridge Repair on SR 532 over Stream (Bridge No. 13.5)Covington | 4 EA | $4,978 | $4,989 | 6 |
| Aug 25, 2026 | Bridge Repair on SR 434 on Bridge No. 0.7 and Bridge Rehabilitation on SR 434 on Bridge NoSharkey | 4 EA | $4,030 | $4,030 | 3 |
| Aug 25, 2026 | SR 145 Bridge Replacement (Bridge No. 210.8), Known as Federal Aid Project No. STBG-0053-0Lee | 4 EA | $4,000 | $4,175 | 8 |
| Jul 28, 2026 | Micro-Surface approximately 14 miles of SR 512 & SR 513Clarke | 32 EA | $4,327 | $2,189 | 2 |
| Jun 23, 2026 | Thin Lift Overlay approximately 8.5 miles of SR 514 from SR 513 to SR 145, approximately 0Clarke, Jasper | 16 EA | $4,641 | $4,200 | 3 |
| May 27, 2026 | Bridge Replacement on SR 427 (Bridge No. 4.4) between SR 488 & SR 16Leake | 4 EA | $3,945 | $3,827 | 8 |
| Apr 28, 2026 | Overlay approximately 14.5 miles on US 98 from 1.05 miles east of SR 29 to the Greene CounPerry | 20 EA | $4,300 | $4,525 | 2 |
| Nov 25, 2025 | Bridge Replacement on SR 481 between SR 902 & SR 35 (Bridge Nos. 2.1 & 2.3)Smith | 4 EA | $4,100 | $4,100 | 7 |
| Sep 4, 2025 | Roundabout on I-55 at the Brookway Boulevard InterchangeLincoln | 4 EA | $405 | $4,710 | 3 |
| Aug 26, 2025 | Mill & Overlay approximately 3.5 miles of US 45 from the beginning of the 4-Lane divided sMonroe | 4 EA | $3,600 | $3,600 | 3 |
| Jul 31, 2025 | Safety Improvements on MS 67 from US 49 to the I-10 "Superstreets" CorridorHarrison | 24 EA | $3,500 | $3,473 | 3 |
| Jul 22, 2025 | Mill & Overlay approximately 5.5 miles of SR 25 from 1.3 miles north of Platsburg Road to Winston | 4 EA | $3,150 | $3,238 | 2 |
| Jun 26, 2025 | Bridge Replacements on US 80 between Chunky & Meehan (Bridge Nos. 123.1, 123.3, 123.5 & 12Lauderdale, Madison, Newton | 16 EA | $3,900 | $4,200 | 3 |
| May 28, 2025 | Overlay approximately 7 miles of SR 15 from the intersection SR 67 North, known as FederalHarrison | 4 EA | $4,500 | $4,750 | 2 |
| Apr 22, 2025 | Mill & Overlay approximately 7 miles of SR 350 from the Alcorn County Line to SR 25Tishomingo | 12 EA | $3,750 | $3,750 | 3 |
| Apr 22, 2025 | Bridge Repair on US 80 over Pearl River Relief (Bridge No. 46.9)Rankin | 3 EA | $3,760 | – | 1 |
| Jan 28, 2025 | Bridge Repairs on SR 149 over Broad Lake (Bridge No. 206.4) & on US 49W over the Yazoo RivYazoo | 4 EA | $4,675 | $4,755 | 4 |
| Dec 5, 2024 | Mill & Overlay approximately 6 miles of SR 5 from 0.1 miles north of Shop to US 72Benton | 8 EA | $4,410 | $4,175 | 5 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.