The low bidder priced delineators, guard rail, yellow at a median $37.43 per each over the last 12 months (2 contracts), up 47% from the year before and up 25% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Fog Seal approximately 6.2 miles of I-59 from 0.8 mile north of CR 39 to the Jasper/ClarkeJasper, Clarke | 94 EA | $39.56 | $43.78 | 2 |
| Sep 22, 2026 | Bridge Repair on US 45 over Norfolk Southern Railroad (Bridge Nos. 275.6A & 275.6B)Alcorn | 9 EA | $35.30 | $35.30 | 7 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 66 EA | $23.89 | $23.89 | 3 |
| Aug 26, 2025 | Mill & Overlay approximately 3.5 miles of US 45 from the beginning of the 4-Lane divided sMonroe | 14 EA | $22.00 | $22.00 | 3 |
| Jul 22, 2025 | Mill & Overlay approximately 5.5 miles of SR 25 from 1.3 miles north of Platsburg Road to Winston | 14 EA | $25.00 | $25.75 | 2 |
| Feb 25, 2025 | Remove & Replace approximately 13 miles of OGFC on I-20 from East Brandon to the Scott CouRankin | 106 EA | $26.00 | $26.00 | 3 |
| Feb 25, 2025 | Remove & Replace approximately 17 miles of OGFC on I-10 from the Pearl River Bridge to wesHancock | 28 EA | $38.00 | – | 1 |
| Nov 26, 2024 | Mill & Overlay approximately 15 miles of US 45A from the Noxubee County Line to the Clay CLowndes | 84 EA | $26.00 | $26.00 | 3 |
| Oct 24, 2023 | Overlay approximatelyRankin | 213 EA | $24.00 | $24.00 | 3 |
| Jun 27, 2023 | Construction project, Rankin CountyRankin | 25 EA | $23.00 | $23.00 | 3 |
| Sep 28, 2022 | Overlay approximatelyMontgomery | 56 EA | $21.00 | – | 1 |
| Aug 23, 2022 | Overlay project, Hinds & Rankin CountyHinds, Rankin | 508 EA | $22.00 | – | 1 |
| Aug 23, 2022 | Overlay approximatelyHancock | 18 EA | $30.00 | $28.19 | 2 |
| May 24, 2022 | Overlay approximately 8.4 miles of SRAttala | 14 EA | $22.05 | – | 1 |
| Jul 27, 2021 | Overlay approximatelyClay | 44 EA | $22.00 | $22.00 | 2 |
| Jul 27, 2021 | Pavement Restoration approximately 14 miles on I-59 from the Lamar County Line to the JoneForrest, Jones | 287 EA | $23.00 | $23.82 | 2 |
| May 25, 2021 | Overlay approximatelyRankin | 14 EA | $22.00 | $22.00 | 3 |
| Mar 23, 2021 | Mill & Overlay approximately 5.4 miles of SR 25 from 2 miles South of Calvery Road to the Winston | 84 EA | $18.00 | $18.00 | 3 |
| Mar 2, 2021 | Construction project, Jefferson CountyJefferson | 7 EA | $24.71 | – | 6 |
| Sep 22, 2020 | Construction projectDistrict 5 | 25 EA | $18.00 | – | 1 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.