BidCrew Data / Mississippi / Prices / 6" Thermoplastic Traffic Stripe, Continuous White
MDOT pay item · 907-626-B006

6" Thermoplastic Traffic Stripe, Continuous White: Mississippi winning bid prices

The low bidder priced 6" thermoplastic traffic stripe, continuous white at a median $8,200 per mile over the last 12 months (35 contracts), down 3% from the year before and flat since 2024.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$8,200
35 contracts
Median, prior 12 months
$8,450
4 contracts
Median, 2024
$8,200
1 contracts
Winner vs. field
level with
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$7,500$8,000$8,500$9,000$9,5002020202120222023202420252026*$8,200
Price vs. quantityEvery winning price since 2020 (log scale)
$5,000$7,500$10,000$12,500$15,000$17,50010
Does quantity matter?Median winning price by quantity band
$0$2,000$4,000$6,000$8,000$10,000$9,000≤8.5$8,1588.5–15$7,80015–19$8,700>19

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Oct 27, 2026Overlay approximately 7 miles of MS 48 from SR 24 to Magnolia Progress RoadPike14 MI$10,064$9,6003
Oct 27, 2026OGFC Lift on I-59 from US 45 to approximately 0.248 miles north of the Russell InterchangeLauderdale11 MI$7,900–1
Oct 27, 2026Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery16 MI$8,400–1
Oct 27, 2026Construction project, Madison CountyMadison14 MI$10,390$12,3503
Oct 27, 2026Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren35 MI$10,250$10,2503
Sep 29, 2026Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin6 MI$20,139$22,1506
Sep 22, 2026Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha13 MI$7,500–4
Sep 1, 2026Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie4 MI$9,500$9,7386
Aug 25, 2026Overlay approximately 3.6 miles of MS 550 from SR 28 to the Lincoln County LineJefferson7 MI$8,608$9,4144
Aug 25, 2026Overlay approximately 2.9 miles of MS 354 from the junction of MS 15 to the end of state mTippah6 MI$9,000$9,0003
Aug 25, 2026Mill & Overlay approximately 0.5 miles East of US 61Washington3 MI$7,900–1
Aug 25, 2026Mill & Overlay approximately 11 miles of US 61 from 0.5 miles North of US 80/SR27 IntersecWarren21 MI$9,500$9,5003
Jul 28, 2026Thin Lift Overlay approximately 10.2 miles of MS 467 from beginning of maintenance to SoutHinds21 MI$5,900$5,9003
Jun 30, 2026Mill & Overlay approximately 6 miles of MS 348 from the Union County Line to just west of Lee13 MI$8,000$8,0005
Jun 23, 2026Overlay approximately 8.5 miles of MS 587 from the Marion County Line to the Northern ErviLawrence17 MI$7,403$8,1364
Jun 5, 2026Mill & Overlay approximately 2 miles of SR 24 from Lower Woodville Road to US 61Wilkinson4 MI$16,000$16,1712
Jun 5, 2026Overlay approximately 8 miles of SR 27 from the Louisiana State Line to High School DriveWalthall17 MI$9,600$9,0493
Jun 5, 2026Mill & Overlay approximately 3 miles of MS 16/149 from MS 3 to US 49Yazoo6 MI$7,600–1
Jun 5, 2026Mill & Overlay approximately 9 miles of US 84 Westbound Lanes from Collins to the Jones CoCovington8 MI$8,000$8,9003
May 27, 2026Thin Lift Overlay of MS 16 from Thompson Drive to the Intersection of MS 15Neshoba12 MI$8,116$8,0005

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.