The low bidder priced interstate directional signs, bolted extruded aluminum panels, ground mounted at a median $34.98 per square foot over the last 12 months (8 contracts), up 11% from the year before and up 19% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Construction project, Madison CountyMadison | 378 SF | $33.90 | $33.90 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 978 SF | $45.00 | $50.00 | 3 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 395 SF | $36.00 | $35.73 | 6 |
| Jul 28, 2026 | Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest | 638 SF | $41.20 | $37.00 | 3 |
| Jul 28, 2026 | Widening on I-10 at MS 605 WB RampHarrison | 502 SF | $33.96 | $33.96 | 3 |
| Jul 28, 2026 | Traffic Signal and Interchange Modifications on US 45 & US 278Lee | 45 SF | $25.00 | $25.00 | 5 |
| Apr 28, 2026 | I-10 Jackson County Welcome CenterJackson | 100 SF | $32.60 | $37.00 | 4 |
| Nov 25, 2025 | Safety Improvements on US 84 at MS 184 & at MS 588 in CollinsCovington | 513 SF | $36.00 | $33.75 | 4 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 438 SF | $29.09 | $29.09 | 3 |
| Sep 4, 2025 | Roundabout on I-55 at the Brookway Boulevard InterchangeLincoln | 63 SF | $31.20 | $32.25 | 3 |
| Jun 26, 2025 | Bridge Replacements on US 80 between Chunky & Meehan (Bridge Nos. 123.1, 123.3, 123.5 & 12Lauderdale, Madison, Newton | 6 SF | $26.00 | $28.00 | 3 |
| Apr 1, 2025 | Roundabout Construction on SR 15 at SR 16 & Bridge Replacements on Weyerhaeuser Street oveNeshoba | 343 SF | $29.00 | $31.57 | 2 |
| Feb 25, 2025 | Safety Improvements on US 49 from the crossover past US 49 at the SR 13 interchange to 100Simpson | 343 SF | $33.75 | $33.00 | 5 |
| Feb 4, 2025 | Roundabout Construction on SR 15 at SR 16 & Bridge Replacements on Weyerhaeuser Street oveNeshoba | 343 SF | $43.20 | – | 1 |
| Jan 28, 2025 | Mill & Overlay approximately 7 miles of SR 16 from lane mile 13.195 to 0.5 miles east of tLeake, Neshoba | 26 SF | $32.00 | $32.00 | 2 |
| Dec 5, 2024 | Interchange Reconstruction on I-20 at FlowersWarren | 521 SF | $37.75 | $37.65 | 3 |
| Oct 22, 2024 | Construction of a Roundabout on SR 3 at Willie Morris ParkwayYazoo | 176 SF | $48.50 | – | 1 |
| Mar 26, 2024 | Pavement Restoration of approximately 5 miles of I-55 from SR 24 to US 98 & Roundabout ConPike | 4.5K SF | $28.75 | $27.38 | 2 |
| Jan 24, 2024 | Interchange Reconstruction on I-10 at Diamondhead, known as Federal Aid Project No. NHPP-0Hancock | 161 SF | $44.00 | $42.55 | 3 |
| Dec 5, 2023 | Widening of I-10 from Diamondhead to County Farm Road, Installation of ITS Components fromHancock, Harrison | 2.8K SF | $40.00 | – | 1 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.